This is an Addendum 2 document issued by the Connecticut Department of Administrative Services (DAS) Construction Services Office on June 11, 2026, clarifying requirements for the Request for Qualifications (RFQ) solicitation for the Former School of Business HVAC Replacement project located at 501 Crescent Street, New Haven, Connecticut. The project involves conversion of the former School of Business building into the new home for the School of Education, including selective demolition and removal of existing non-serviceable VRF and Daikin Generation 1 HVAC systems, installation of new equipment, interior and exterior improvements, reconstruction of disturbed areas, FF&E provisions, and geothermal heating and cooling systems. The original QBS Submittal Booklet is due Friday, June 26, 2026, at 3:00 PM EDT. This addendum is the second issued for this procurement, following Addendum 1 dated June 9, 2026.
The addendum clarifies three critical aspects of the solicitation: (1) engineering firms may submit as the prime consultant with all required sub-consultants, including architects, as part of the team; (2) MEP firms may serve as the prime consultant and contract all sub-consultants; and (3) the project selection type is designated as a Minor Capital Project Consultant Service Selection under Section 1.9 of the RFQ, regardless of whether design fees fall below the $762,000 threshold outlined in the 1210 QBS Guidelines. Respondents should direct questions to DAS.CS.RFQ@ct.gov. Payment terms are Net 30 Days, with the primary project contact being Ryan Davis at DAS Construction Services.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Connecticut Department of
Administrative Services 1200.1
Addendum
Addendum No.: 2 Date of Addendum: June 11, 2026
CT DAS 1200.1 (Rev. 03.11.2026) 1200 Consultant Selection Forms
Connecticut Department of Administrative Services, Construction Services
Office of Legal Affairs, Policy, & Procurement 450 Columbus Boulevard, Suite 1302, Hartford, Connecticut 06103
Consultant Services Addendum For:
Contract Number: BI-RS-381-ARC
Project Title: Former School of Business HVAC Replacement Project Location: 501 Crescent Street, New Haven, CT 06515
Original QBS Submittal Booklet Due Date / Time:
Friday, June 26, 2026 / 3:00 PM
Previous Addenda: Addendum 1, dated 6/9/2026 To Firms: This Addendum forms part of the QBS Documents and modifies or clarifies the original RFQ
Web Advertisement for this Project.
The following clarifications are applicable to the RFQ Web Advertisement for the Project referenced above.
Contact For Questions: Email: DAS.CS.RFQ@ct.gov
Addendum Item No. 1:
• QUESTION: May an Engineering firm submit on the SCSU Former School of Business HVAC Replacement as a
Prime, with all of the required sub-consultants, including architects, as part of the team.
• RESPONSE: Yes
Addendum Item No. 2:
• QUESTION: Under section 1.10, Project Delivery Method, it indicates a D-B-B project with ARC consultants. Since this project is mostly MEP in nature with the need of minor architectural support and civil support, could an MEP firm be Prime and contract all the sub consultants?
• RESPONSE: Please see the response to No. 1.
Addendum Item No. 3:
• QUESTION: Under section 1.10 it indicates this is to be bid as a “Major Capital Project”. It is very likely that the design fees for this project would fall under the $762,000 limit as per 1210 QBS Guidelines for Selection and Contract Limits section 1.0. If so, please confirm this may not be considered as a Major Capital Project if that is the case.
• RESPONSE: The selection type for this project is a Minor Capital Project Consultant Service Selection, as outlined in Section 1.9 of the 1200 RFQ Web Advertisement for Consultant Services. Regardless, this project is a formal selection and the consultants will be selected from respondents to this RFP solicitation.
End of Addendum No.: 2 cc: DAS Deputy Commissioner: D. Hobbs DAS/CS ADPM for Project: J. Vigneault DAS/CS Agency Legal Director: J. Padula DAS/CS Project Manager: R. Davis DAS/CS Chief Architect: D. Barkin DAS/CS Panel Member: R. Wilfinger DAS/CS Director of Project Management: P. Simmons Agency Panel Member: P. Visentin DAS/CS Director of Support Services: C. Russell File: BI-RS-381 DAS/CS QBS Unit: R. Cutler / G. Fehrs / T. Wargo DAS/CS Legal Affairs: R. Tamborra / A. Buzzard / C. Phelps / T. Keating Observers and Others: J. Ruggiero / E. Lessne mailto:DAS.CS.RFQ@ct.gov