About this file
This is a competitive sealed bid proposal document submitted to the State of Hawaii Department of Land and Natural Resources, Division of Boating and Ocean Recreation, for comprehensive site improvements at the Mala Boat Ramp in Lahaina, Maui (Project No. B48CM75A). The project encompasses demolition of existing pavement, boat washdown areas, and comfort station buildings; site grading and preparation; installation of asphalt concrete and concrete pavement for parking areas; reconstruction of the boat washdown area with drainage systems; installation of 12 solar-powered street lights; and comprehensive comfort station renovations including new fixtures, roofing, and interior finishes. The bid is organized into 20 line items, including lump-sum allowances for mobilization/demobilization, surveys, temporary site installation, asbestos abatement, site demolition, utility improvements, drainage improvements, and various specialized services. Unit-priced items include 120 cubic yards of concrete pavement, 1,205 linear feet of concrete curb, and 5,414 square yards of asphalt concrete pavement. The proposal submission deadline is May 20, 2026, with a mandatory pre-bid conference required for this project. The contract performance period is 180 consecutive calendar days from written notice to proceed, with liquidated damages of $300 per calendar day assessed for delays.
The bidder must complete the proposal form with detailed pricing for all 20 items, resulting in a total sum bid. The project offers preferences for recycled products (10 percent price reduction), Hawaii products, and apprenticeship agreements (5 percent price reduction for certified participation). Successful bidders must hold a valid State Contractor's License, Classification "A," and perform at least 20 percent of contract work with their own organization. All bids must include evidence of bid security (surety bond, certified check, or equivalent), documentation of compliance with Hawaii tax and labor laws, a complete listing of joint contractors or subcontractors with appropriate specialty licenses, and certifications regarding safety and health programs for projects exceeding $100,000. Award will be made to the lowest responsible bid after applicable preferences are applied, with the Board of Land and Natural Resources reserving the right to reject any bids, delete items as necessary to remain within available funding, or negotiate adjustments with the lowest responsive bidder if all bids exceed certified available funds. The state will hold all bids for 60 days from opening and may delay Notice to Proceed up to 365 days without additional compensation for escalation or delay claims.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P-1
P R O P O S A L
FOR
STATE OF HAWAII
DEPARTMENT OF LAND AND NATURAL RESOURCES
DIVISION OF BOATING AND OCEAN RECREATION
ENGINEERING BRANCH
Job No. B48CM75A Mala Boat Ramp Site Improvements
Lahaina, Maui, Hawaii
_________________, 2026
Engineering Branch Head Division of Boating and Ocean Recreation Department of Land and Natural Resources State of Hawaii Honolulu, Hawaii
Dear Sir:
The undersigned, having carefully examined the local conditions and all available records and information covering conditions which may affect the cost of the work to be performed, and having carefully examined the Plans and Specifications, and other contract documents, hereby proposes to furnish and pay for all materials, tools, equipment, labor and other incidental work necessary for the removal, hauling and disposal of the demolitions work from existing pavement, boat washdown area, site grading and comfort station building demolition work and installation of additional asphalt concrete (AC) pavement parking, additional concrete pavement, resurface the existing parking lot, reconstruct the existing boat washdown area and drain field, site lighting, and replacement of the restroom fixtures and doors, reroof and interior painting of the existing comfort station, and appurtenant work at Mala Boat Ramp, Lahaina, Maui, Hawaii as required or called for in this Proposal, all according to the true intent and meaning of the Notice to Bidders, Information and Instructions to Bidders, Proposal, Technical Specifications, Interim General Conditions, Plans, Permitting Documents, and any and all addenda for:
Job No. B48CM75A Mala Boat Ramp Site Improvements
Lahaina, Maui, Hawaii on file in the office of the Engineering Branch for the TOTAL SUM BID (Items 1 to 20) of:
Dollars ($ ) and will fully complete all work under this contract within 180 consecutive calendar days from the date of written notice to proceed, including date of said order, said total sum being itemized on the following pages.
P-2
PROPOSAL
Item No. Qty. Unit Description Unit Price Total
1. 1 LS
Mobilization and Demobilization.
Not to Exceed 10% of the Sum of Bid Items 2 – 15.
2. 1 LS Pre- and Post-Construction Surveys, including all labor, materials, equipment and incidentals as required.
3. 1 LS
Temporary Construction Site Installation and Maintenance including, but not limited to: Erosion, Sediment and Dust Control BMPs; Staging Areas; Temporary Traffic Control as required during the period of construction. This Item includes all submittals, agreements, permits, maintenance, monitoring and reporting, and all other incidentals, in place complete.
4. 1 LS
Asbestos Report and Abatement, including but not limited to: asbestos investigation and written report identifying asbestos-containing materials (ACMs) on site, perform abatement(if required), including proper containment, removal, disposal, and all other incidentals. in place complete.
5. 1 LS
Site Demolition and Removal, including but not limited to:
removal/disposal of concrete curbs; a.c. and concrete pavement; pavement striping; signage; gravel/soil; street lights; trees; certain portions of water lateral and appurtenances; certain portions of electrical lines and appurtenances; and all other appurtenant work indicated on the drawings, in place complete.
6. 1 LS
Water Service Lateral and Utility Improvements, including all piping, fittings, valves, hose bibbs and bollards;
connection to existing water line; trench excavation and backfill; cushion material; compaction; existing utility cover replacements; and all other appurtenant work indicated on the drawings, in place complete.
7. 1 LS
Drainage Improvements, including but not limited to: drain piping; trench drain; drain manhole; storm chambers;
inspection ports; excavation and backfill; cushion material;
geotextile fabric; geogrid; compaction; and all other appurtenant work indicated on the drawings, in place
8. 120 CY
Concrete Pavement, including but not limited to: concrete pavement; reinforcing steel; aggregate base course;
geotextile fabric; joints; concrete pavement transitions;
excavation and backfill; and all other appurtenant work
9. 1205 LF Concrete Curb, including but not limited to: barriers; curb or flush curb, as shown on plans, in place complete.
P-3
10. 5414 SY
AC Pavement, including but not limited to: State Mix V pavement; compacted base course, prime coat; sawcutting;
speed bump; excavation and backfill; and all other
11. 1 LS
Striping, including but not limited to: 4" wide striping;
symbols; and all other appurtenant work indicated on the drawings, in place complete.
12. 1 LS
Signage and Barriers, including but not limited to:
aluminum signs; sign posts; concrete footing, concrete jersey barriers; and all other appurtenant work indicated on the drawings, in place complete.
13. 12 EA
Solar Powered Street Light, including, but not limited to: entire assembly; wiring; grounding rod;
reinforced concrete foundation; bollards; excavation and backfill; and all other appurtenant work
14. 1 LS
Existing Comfort Station Demolition and Removal, including but not limited to: removal/disposal water fixtures and piping; tiles; partitions; and all other
15. 1 LS
Existing Comfort Station Improvements, including but not limited to: piping; valves; water closet;
lavatory; partitions; refurbish interior; roofing upgrades; and all other appurtenant work indicated on the drawings, in place complete.
16. 1 LS Allowance for Archaeological Monitoring Services $40,000.00*
17. 1 LS
Allowance for Offsite Storage Area, including but not limited to: obtaining any necessary permits/clearances/right-of-entry.
$25,000.00*
18. 1 LS
Allowance for Field Office, including but not limited to: establishment of office; office equipment and furniture; window-type air conditioning unit(s);
telephone service; potable water supply or service;
sanitary facilities; internet and wifi; electrical servie and lighting; miscellaneous equipment; and all other incidentals, in place complete.
$20,000.00*
19. 1 LS Allowance for Project Sign $5,000.00*
20. 1 LS Additional work as directed and approved by the Engineer.
Allowance $100,000.00*
TOTAL SUM BID (Items 1-20, Inclusive)
* Allowance Items shall be included in Total Sum Bid. Use of and payment for this item authorized only when written approval for its use is given by the Officer-in-Charge. Any unused Allowance monies shall remain with the State upon completion of the project.
Contractor shall not make a claim in the event that the State chooses to delete any Allowable Cost from the Contract.
P-4
RECYCLED PRODUCTS PREFERENCE
This project allows a 10% price preference for recycled products in accordance with HRS 103D-1005.
Bidders are required to complete this section. FAILURE TO COMPLETE THIS SECTION MAY BE
SUFFICIENT CAUSE FOR REJECTION OF THE BID.
Only the following products are being considered for the recycled product preference. Please indicate your selection of recycled or non-recycled product by indicating its cost FOB jobsite unloaded in the schedule below, including applicable General Excise & Use Taxes.
RECYCLED NONRECYCLED
DESCRIPTION PRODUCT COST PRODUCT COST
The bidder requesting a recycled product preference by his selection above, shall also complete and submit the form “CERTIFICATION OF RECYCLED CONTENT” as shown in the Interim General Conditions and provide all supporting information with this proposal. Additional information may be requested to qualify a product.
The following definitions are applicable to the CERTIFICATION OF RECYCLED CONTENT form:
"Post-consumer recovered material" means any product used by a consumer, including a business that purchases the material, that has served its intended end use, and that has been separated or diverted from the solid waste stream for the purpose of use, reuse, or recycling.
"Product" includes materials, manufactures, supplies, merchandise, goods, wares, and foodstuffs.
"Recovered material” means waste material and by-products that have been separated, diverted, or removed from the solid waste stream after a manufacturing process for the purpose of use, reuse, or recycling.
Recovered material does not include those materials and by-products that are generated and normally reused on-site or within original manufacturing processes (such as mill broke, in the case of paper products).
"Recycled content” means the percentage of a product composed of recovered material, or post-consumer recovered material, or both.
"Recycled product” means a product containing recovered material, or post-consumer recovered material, or both.
The bidder agrees that preference for recycled products shall be taken into consideration to determine the low bidder in accordance with said Section and the rules promulgated, however, the award of contract will be in the amount of the bid offered exclusive any preference.
P-5
APPRENTICESHIP AGREEMENT PREFERENCE
1. If applicable to this project, any bidder seeking the preference must be a party to an apprenticeship agreement registered with the State Department of Labor and Industrial Relations (DLIR) at the time the bid is submitted for each apprenticeable trade the bidder will employ to construct the project. “Employ” means the employment of a person in an employer-employee relationship.
a. The apprenticeship agreement shall be registered with the DLIR and conform to the requirements of Hawaii Revised Statues Chapter 372.
b. Subcontractors do not have to be a party to an apprenticeship agreement for the bidder to obtain preference.
c. The bidder is not required to have apprentices in its employ at the time the bid is submitted to qualify for the preference.
2. A bidder seeking the preference must state the apprenticeable trade the bidder will employ for each trade to be employed to perform the work by submitting a completed signed original Certification Form 1 verifying the participation in an apprenticeship program registered with DLIR. “Apprenticeable trade” shall have the same meaning as “apprenticeable occupation” pursuant to Hawaii Administrative Rules (HAR) 12-30-5.
a. The Certification Form 1 shall be authorized by an apprenticeship sponser listed on the
DLIR list of registered apprenticeship programs. “Sponsor” means an operator of an apprenticeship program and in whose name the program is approved and registered with the DLIR pursuant to HAR 12-30-1.
b. The authorization shall be an original signature by an authorized official of the apprenticeship sponsor.
c. The completed signed original Certification Form 1 for each trade must be submitted with the bid. Previous certifications shall not apply.
d. When filling out the Certification Form 1, the name of Apprenticeable Trade and
Apprenticeship Sponsor must be the same as recorded in the List of Contruction Trades in Registered Apprenticeship Programs that is posted on the DLIR website. “Registered apprenticeship program” means a construction trade program approved by the DLIR pursuant to HAR 12-301 and 12-30-4.
e. The Certification Form 1 and the List of Construction Trades in Registered Apprenticeship
Programs is available on the DLIR website at: http://hawaii.gov/labor/wdd.
3. Upon receiving the Certification Form 1, the Procurement Officer will verify that the apprenticeship program is on the List of Construction Trades in Registered Apprenticeship Programs and that the form is signed by an authorized official of the Apprenticeship Program Sponsor. If the programs and signature are not confirmed by the DLIR, the bidder will not quality for the preference.
4. If the bidder is certified to participate in an apprenticeship program for each trade which will be employed by the bidder for the project, a preference will be applied to decrease the bidder’s bid amount by five percent (5%) for evaluation purposes.
http://hawaii.gov/labor/wdd
P-6
5. Should the bidder qualify for other preferences (e.g. Hawaii Products), all applicable preferences shall be applied to the bid price.
CONTRIBUTIONS BY STATE AND COUNTY CONTRACTORS PROHIBITED
Contractors are hereby notified of the applicability of Section 11-355, HRS, which states that campaign contributions are prohibited from specified State or county government contractors during the term of the contract if the contractors are paid with funds appropriated by a legislative body.
CONDITION OF AWARD
It is understood that the award of the contract will be made on the basis of the lowest responsible Total Sum Bid (Items 1 to 26) selected by the Board of Land and Natural Resources. Write the total of bid items 1 to 26 on page P-1.
In the event the low bid is below the available funds certified by the appropriate fiscal officer, the head of the purchasing agency responsible for the procurement in question is authorized to award Additives to the lowest bidder. The award of Additives may be in any order or combination such that the Base Bid plus Additives do not exceed the available funds.
It is understood and agreed that the Board of Land and Natural Resources reserves the right to reject any and/or all bids and waive any defects when, in the Board's opinion, such rejection or waiver will be for the best interest of the State of Hawaii.
In the event all bids exceed available funds certified by the appropriate fiscal officer, the head of the purchasing agency responsible for the procurement in question is authorized in situations where time or economic considerations preclude resolicitation of work of a reduced scope to negotiate an adjustment of the bid price, including changes in the bid requirements, with the low responsible and responsive bidder, in order to bring the bid within the amount of available funds. It is understood and agreed upon that the head of the purchasing agency may delete a portion or all of any item(s) in the proposal at the stated unit or lump sum price as necessary to stay within the available funding. The bidder is responsible to make an earnest effort to represent the actual cost of each item, including all materials, labor, equipment, overhead and profit in their bid proposal to preclude claims of anticipated profit or loss of profit because of an unbalanced bid proposal.
It is also understood that if a mutually agreeable cost for the reduced scope of work necessitated by a lack of available funds cannot be agreed upon between the bidder and the head of the purchasing agency within 14 calendar days after the bid opening, then the bid may be rejected in the best interest of the purchasing agency, and the head of the purchasing agency may negotiate in progressive order (lowest to highest) with the next lowest responsible and responsive bidder.
It is also understood and agreed that the award of the contract shall be conditioned upon funds being made available for this project and further upon the right of the Board of Land and Natural Resources to hold all bids received for a period of sixty (60) days from the date of the opening thereof, unless otherwise required by law, during which time no bid may be withdrawn.
It is also understood that Notice to Proceed may be delayed up to three hundred and sixty-five (365) days after the date of bid opening, and that no additional compensation will be provided for any claim for escalation or delay for issuance of Notice to Proceed on or before that date, plus the contract time allowed for performance of work noted on Page P-1 of the [Bid] PROPOSAL form. See SPECIAL PROVISIONS, Section 3.9 for additional requirements.
It is also understood and agreed that the quantities given herewith are approximate only and are subject to increase or decrease, and that the undersigned will perform all quantities of work as either increased or decreased, in accordance with the provisions of the Contract Specifications.
P-7
It is also understood and agreed that the estimated quantities shown for the items for which a UNIT PRICE is asked in this Proposal are only for the purpose of comparing on a uniform basis, bids offered for the work under this contract, and the undersigned agrees that he is satisfied with and will at no time, dispute said estimated quantities as a means of claims for anticipated profit or loss of profit, because of a difference between the quantities of the various classes of work done or the materials and equipment installed, and the said estimated quantities. On UNIT PRICE bids, payment will be made only for the actual number of units incorporated into the finished project at the contract UNIT PRICE.
After the proposals are opened and read, the figures will be extended and/or totaled in accordance with the bid prices of the acceptable proposals and the totals will be compared. In the comparison of bids, words written in the proposal shall govern over figures and unit prices will govern over totals. Until the award of the contract, however, the right will be reserved to reject any and all proposals and to waive any defects or technicalities as may be deemed best for the interest of the State.
It is also understood and agreed that liquidated damages in the amount of THREE HUNDRED DOLLARS AND NO/100 ($300.00) for each and every calendar day in excess thereof prior to completion of the contract shall be withheld from payments due to the Contractor.
It is also understood and agreed that if this bid is accepted, the successful bidder must enter into and execute a contract with the Board of Land and Natural Resources and furnish a Performance and Payment Bond, as required by law. These bonds shall conform to provisions of Section 103D-324 and 325, Hawaii Revised Statutes and any law applicable hereto.
It is also understood and agreed that the successful bidder will provide all necessary labor, materials, tools, equipment, and other incidentals necessary to do all the work and furnish all the materials specified in the contract in the manner and time herein prescribed, and according to the requirements of the Engineer as therein set forth.
It is understood that by submitting this proposal, the undersigned is declaring that his firm has not been assisted or represented on this matter by an individual who has, in a State capacity, been involved in the subject matter of this contract in the past two years.
It is understood that by submitting this proposal in accordance with HAR 3-122-192, the undersigned is declaring that the price submitted is independently arrived without collusion.
It is also understood that by submitting this proposal, a Certification for Safety and Health Programs for bids in excess of $100,000 (in accordance with HRS 396-18), the undersigned certifies that his organization will have a written safety and health plan for this project that will be available and implemented by the Notice to Proceed date of this project. Details of the requirements of this plan may be obtained from the Department of Labor and Industrial Relations, Occupational, Safety and Health Division (HIOSH).
It is further understood and agreed that the successful bidder shall comply with paragraph 3.1.a "SUBCONTRACTING" of the General Provisions which requires that the contractor shall perform with his own organization and with the assistance of workmen under his immediate superintendence, work of a value not less than twenty percent (20%) of the value of all work embraced in the Contract, except that certain contract items of work, if specifically referred to in the special provisions, will be exempted from said twenty percent requirement.
Compliance with §103-310 HRS. As a condition of award all bidders shall comply with all laws governing entities doing business in the State, including Chapter 237 HRS (general excise tax); Chapter 383 HRS (employment security – unemployment insurance); Chapter 386 HRS (workers compensation); Chapter 392 HRS (temporary disability insurance); and Chapter 393 HRS (pre-paid health care), and shall produce all
P-8 documents to the State (DLNR, Engineering Division) required to demonstrate compliance with these subsections. Any bidder making a false affirmation or certification under this subsection shall be suspended and may be debarred from further offerings or awards pursuant to §103D-702 HRS.
RECEIPT OF ADDENDA
The bidder also acknowledges receipt of any and all addenda issued by the Engineering Division, by recording the date of receipt of the respective addenda in the space provided below:
Addendum Date Received Addendum Date Received
No. 1 No. 5 No. 2 No. 6 No. 3 No. 7 No. 4 No. 8
It is understood that failure to receive any such addendum shall not relieve the Contractor from any obligation under this Proposal as submitted.
It is also understood and agreed that if this Proposal is accepted and the undersigned should fail or neglect to contract as aforesaid, the Board may determine that the bidder has abandoned the Contract, and thereupon, forfeiture of the security accompanying his proposal shall operate and the same shall become the property of the Board.
P-9
JOINT CONTRACTORS OR SUBCONTRACTORS
TO BE ENGAGED ON THIS PROJECT
The Bidder agrees that the following is a complete listing of all joint contractors or subcontractors covered under Chapter 444, Hawaii Revised Statutes (HRS), who will be engaged by the Bidder on this project to perform the required work indicated pursuant to Section 103D-302, HRS. It is the sole responsibility of the contractor to review the requirements of this Project and determine the appropriate licenses that are required to complete the Project. The Bidder certifies that the completed listing of joint contractors or subcontractors fulfills the requirements for the project and the Bidder, together with the listed subcontractors or joint contractors have all the specialty contractor’s licenses to complete the work, except as provided for in HRS §103D-302(b). Failure of the Bidder to comply with this requirement may be just cause for rejection of the bid.
“A” General Engineering Contractors and “B” General Building Contractors are reminded that due to the Hawaii Supreme Court’s January 28, 2002 decision in Okada Trucking Co., Ltd. v. Board of Water Supply, et al., 97 Haw. 450 (2002), they are prohibited from undertaking any work, solely or as part of a larger project, which would require the general contractor to act as a specialty contractor in any area in which the general contractor has no license. Although the “A” and “B” contractor may still bid on and act as the “prime” contractor on an “A” or “B” project (See, HRS §444-7 for the definitions of an “A” and “B” project.), respectively, the “A” and “B” contractor may only perform work in the areas in which they have the appropriate contractor’s license (An “A” or “B” contractor obtains “C” specialty contractor’s licenses either on its own, or automatically under HAR § 16-77-32). The remaining work must be performed by appropriately licensed entities.
General Engineering “A” Contractors automatically have these “C” specialty contractor’s licenses: C-3, C-9, C-10, C-17, C-24, C-31a, C-32, C-35, C-37a, C-37b, C-38, C-43, C-49, C-56, C-57a, C-57b and C- 61.
General Building “B” Contractors automatically have these “C” specialty contractor’s licenses: C-5, C-6, C-10, C-12, C-24, C-25, C-31a, C-32a, C-42a and C-42b.
In completing the Joint Contractors or Subcontractors List, describe the specialty contractor’s nature and scope of work to be performed for this project and provide the complete firm name of the joint contractor or subcontractor in the respective columns. If the Bidder is a general contractor providing the work of a required specialty contractor, whose license is not automatically held pursuant to HAR 16-77-32, fill in the Bidder’s (general contractor’s) name and nature and scope of work to be performed on this project.
List only one joint contractor or subcontractor per required specialty contractor’s classification, unless within the same specialty, the work of each joint contractor or subcontractor can be described so that there is no overlap in work descriptions.
If a contractor’s license is required by law for the performance of the work which is called for in this bid, the bidder and all subcontractors must have the required license before the submission of the bidder’s proposal in the case of a non-federal aid project, and for federal-aid projects, the bidder must have the required license prior to the award of the project and all subcontractors prior to the start of the subcontracted work.
Bidders shall list only one Joint Contractor or Subcontractor per required specialty contractor’s license.
P-10
Class
Description
License No.
Joint or Subcontractor Firm
Name
P-11
Enclosed herewith is a:
1. Surety Bond (*1) )
2. Legal Tender (*2) )
3. Cashier's Check (*3) )
4. Certificate of Deposit (*3) ) in the
5. Certified Check (*3) ) amount
6. Official Check (*3) ) of
7. Share Certificate (*3) )
8. Teller's Check (*3) )
9. Treasurer's Check (*3) ) (Cross Out Those Not Applicable)
Dollars ($ ) as required by law.
Respectfully submitted, Name of Company, Joint Venture or Partnership
Contractor's License No.
By Signature (*4)
Title Print Name Date Address
Telephone No.
E-Mail Address
NOTES:
1. Please attach to this page evidence of the authority of this officer to submit bids on behalf of the Company and also the names and residence addresses of all officers of the Company.
2. Fill in all blank spaces with information asked for or bid may be invalidated. PROPOSAL
MUST BE INTACT, MISSING PAGES MAY INVALIDATE YOUR BID.
End of Proposal
| RECYCLED PRODUCTS PREFERENCE |
| RECYCLED NONRECYCLED |
| APPRENTICESHIP AGREEMENT PREFERENCE |
| CONTRIBUTIONS BY STATE AND COUNTY CONTRACTORS PROHIBITED |
| CONDITION OF AWARD |
| RECEIPT OF ADDENDA |
| JOINT CONTRACTORS OR SUBCONTRACTORS TO BE ENGAGED ON THIS PROJECT |
| NOTES: |
File details come from the government source that posted it. Updated .