Sheet1 Attachment 2 - EXHIBIT 2 - NPS WWI Memorial Equipment, Systems, and Maintenance Items

LIGHTING

Equipment Qty Structure Room Location Description Required Maintenance

Interior Lights
G1201 StorageWest Below Grade StructureLED vaportight linear indoor ratedMaintain fixture and replace LED board if outage occurs
G2301 StorageWest Below Grade StructureLED vandal-proof indoor sconceMaintain fixture and replace LED board if outage occurs
E1301 StorageWest Below Grade StructureLED thermoplastic emergency battery unitSelf-diagnostic test button monthly to confirm battery is charging properly
E2201 StorageWest Below Grade StructureLED thermoplastic emergency battery unit and exit signSelf-diagnostic test button monthly to confirm battery is charging properly
G302 Electrical RoomWest Below Grade StructureLED vaportight linear indoor ratedMaintain fixture and replace LED board if outage occurs
E1102 Electrical RoomWest Below Grade StructureLED thermoplastic emergency battery unitSelf-diagnostic test button monthly to confirm battery is charging properly
G203 StairWest Below Grade StructureLED vaportight linear indoor ratedMaintain fixture and replace LED board if outage occurs
G1103 StairWest Below Grade StructureLED vaportight linear outdoor ratedMaintain fixture and replace LED board if outage occurs
E1203 StairWest Below Grade StructureLED thermoplastic emergency battery unit with wet guardSelf-diagnostic test button monthly to confirm battery is charging properly
G804 Fountain Equipment RoomWest Below Grade StructureLED vaportight linear indoor ratedMaintain fixture and replace LED board if outage occurs
E1104 Fountain Equipment RoomWest Below Grade StructureLED thermoplastic emergency battery unitSelf-diagnostic test button monthly to confirm battery is charging properly
Exterior Lights
FA/FA-129Outdoors15th Street, Pennsylvania Ave, 14th StreetLED PoleMaintain fixture and replace LED board and / or driver if outage occurs
FB/FB-138OutdoorsThroughoutLED PoleMaintain fixture and replace LED board and / or driver if outage occurs
FC40lfOutdoorsPershing MemorialLED Bench LightMaintain fixture and replace LED board and / or driver if outage occurs
FD/FD-134OutdoorsBelvedere, South Berm Ramp, Lower Plaza (North)LED Step LightMaintain fixture and replace LED board and / or driver if outage occurs
FE/FE-151lfOutdoorsPershing MemorialLED Strip LightMaintain fixture and replace LED board and / or driver if outage occurs
FF9OutdoorsPennsylvania AveLED PoleMaintain fixture and replace LED board and / or driver if outage occurs
FG61lfOutdoorsBelvedereLED Strip LightMaintain fixture and replace LED board and / or driver if outage occurs
FJ/FJ-12OutdoorsSouth Terrace, Lower Plaza (North)LED PoleMaintain fixture and replace LED board and / or driver if outage occurs
FK14OutdoorsPoolLED Fountain LightMaintain fixture and replace LED board and / or driver if outage occurs
FL2OutdoorsPershing MemorialLED PoleMaintain fixture and replace LED board and / or driver if outage occurs
FM12OutdoorsUpper TerraceLED UplightMaintain fixture and replace LED board and / or driver if outage occurs
FR12OutdoorsUpper TerraceLED PoleMaintain fixture and replace LED board and / or driver if outage occurs
PLUMBING SYSTEMS

Equipment Qty Structure Room Location Description Required Maintenance

Condensate Sump Pump1Security ClosetLittle Giant Model VCMA-15Annual - Inspect Unit, clean tank and line, manually operate valve.
Trap Primer Valve1Fountain Equipment RoomPPP Model PT1320Annual - Inspect Unit, manually test operation with traps exposed to verify.
Fixtures
Drinking Fountain1OutdoorsMDF Model 10145SMFAMaintain Fixture with no longer than a 24 hour down time during the active season As Needed - Unclog and Repair Valves faucets, etc.

Every 6 Months - Rebuild Regulators

*toilet*Future addition of restroom
*sink*Future addition of restroom
*mop sink*storage area
Drainage
Floor Drain3Fountain Equipment RoomJosam Model 32300-81As Needed - Unclog/snake
Backflow Preventer
Backflow Preventer1Fountain Equipment RoomZurn Model 375XLAnnual - Test, Calibrate, and Certify by Certified Backflow Technician and repair as

needed

Backwater Valve BWV-1Fountain Equipment RoomJosam Model 67500Annual - Inspect/clean
Backwater Vavle BWV-2Fountain Equipment RoomJosam Model 67720Annual - Inspect/clean

MECHANICAL SYSTEMS

Equipment Qty Structure Room Location Description Required Maintenance

EF-1 1 Fountain Equipment Room Inline - Suspended Greenheck Model BSQ-180-5 Every 3 Months - Check Belt Tension (Adjust/Replace When Needed) Annual - Lubricate SAE 20 Electric Motor Oil Annual Exercise Shutoff Switch

EF-21Electrical RoomInline - SuspendedGreenheck Model BSQ-070-4
EF-31StorageInline - SuspendedGreenheck Model BSQ-130HP-3
UH-11Fountain Equipment RoomPropellerMarkel Model F2F5103NAnnual - Inspect unit and Clean Unit Casing, Fan, and Motor

Annual - Inspect Wiring and Contactors Annual - Exercise Shutoff Switch

UH-21Fountain Equipment RoomPropellerMarkel Model F2F5103N
UH-31Fountain Equipment RoomPropellerMarkel Model F2F5103N
UH-41Fountain Equipment RoomPropellerMarkel Model F2F5103N
UH-51StorageWall MountedMarkerl Model J3455TAnnual - Inspect unit and Clean Unit Casing, Fan, and Motor

Annual - Inspect Wiring and Contactors Annual - Exercise Shutoff Switch UH-6 1 Electrical Room Propeller Markel Model F2F5105N Annual - Inspect unit and Clean Unit Casing, Fan, and Motor Annual - Inspect Wiring and Contactors Annual - Exercise Shutoff Switch

UH-71StoragePropellerMarkel Model F2F5105N
UH-81StoragePropellerMarkel Model F2F5105N
UH-91StoragePropellerMarkel Model F2F5105N
UH-101StoragePropellerMarkel Model F2F5105N
UH-111StoragePropellerMarkel Model F2F5105N
UH-121StorageWall MountedMarkerl Model J3455TAnnual - Inspect unit and Clean Unit Casing, Fan, and Motor

Annual - Inspect Wiring and Contactors Annual - Exercise Shutoff Switch ACU-1 1 Security Closet Wall Mounted Mitsubishi Model PUY-A24NHA7 Monthly - Inspect Unit and Replace Filters Monthly - Inspect and Replace Belt as Needed (B-55) Every 3 Months - Check/Add Refrigerant as Needed Annual - Inspect Contactors, Wiring and Relays Annual - Exercise Shutoff Switch ACCU-1 1 Storage Wall Mounted Mitsubishi Model PKA-A24KA7 Monthly - Inspect unit Every 3 Months - Check/Add Refrigerant as Needed Annual - Inspect/Tighten Wiring Annual - Clean Unit Annual - Exercise Shutoff Switch Annual - Clean Condenser Coils Fire Dampers 6 Electrical Room Duct Mounted Ruskin DIBD40 Annual - Inspect/test per NFPA

ELECTRICAL SYSTEMS

Equipment Qty Structure Room Location Description Required Maintenance

System
Electrical Distribution System1West Below Grade StructureUtility meter, distribution switchboard, panelboards, lighting and controls, mechanical equipment, water feature equipmentAs required: A licensed electrician should be available to troubleshoot and repair electrical malfunctions.
Grounding and Bonding1PoolEquipotential grounding grid below pool surfacesAnnual test to ensure integrity of grounding and bonding system to protect patrons that may enter the water feature areas.
Lighting Protection1Flag pole, sculptureLightning protection conductors, air terminals, and copper platesAnnual test to inspect connections and ensure integrity of system.
Panels
DP-11Electrical RoomWest Below Grade Structure2000A, 208Y/120V,3PH,4W switchboard, service entrance ratedAnnual - clean dust from panelboard interiors and electrical room Annual - inspect for loose wiring connections and tighten.
RP11Electrical RoomWest Below Grade Structure100A MLO, 208Y/120V,3PH,4W receptacle panelboard, 42-poles
LP11Electrical RoomWest Below Grade Structure225A MLO, 208Y/120V,3PH,4W lighting panelboard, 54-poles
CPPA1Fountain Equipment RoomWest Below Grade Structure300A MCB, 208Y/120V,3PH,4W water feature panelboard
Lighting Racks
Lighting Control Panel2Electrical RoomWest Below Grade Structure24/32-pole lighting relay panels for site lighting controlsBiannual cleaning of dust from interior of panels, fans, and filters.
GFCI
GFCI receptaclesWest Below Grade StructureGFCI rated receptaclesAnnual - test GFCI and reset, clean from dust and debris
GFCI receptaclesSiteGFCI rated receptacles with weatherproof coverAnnual - test GFCI and reset, clean from dust and debris, replace damaged covers

IRRIGATION SYSTEM

EquipmentQtyStructureRoomLocationDescriptionRequired Maintenance
Pump1Fountain Equipment Room (04)West Below Grade StructureModel No.: SHSTV-1-(?K)-3-460-3-21-60Turn off the pump in late october to early november, turn on in spring (after last frost) - refer to winterization procedure

per warranty, during warranty period

Raindbird controller1Fountain Equipment Room (04)West Below Grade StructureESP4ME3 w/ expansion ESPSM6bi-weekly to monthly use the water budget feature to adjust system run times based on current weather conditions
Wireless rain/freeze sensors1Exterior wall (TBD)model WR2-RFC
Dripline20K'All through out the landscapingRain Bird XFCV-06-12Visually check for leaks weekly repair as needed
Air Relief Valve18In landscaped bedsRain Bird ARV050Keep area around valve clear

BRONZE SCULPTURE CONSERVATION

Material Qty Structure Area/Item Required Maintenance

Bronze 1 Sculpture* Fountain Wall (install late '23 NLT May '24) Triannual - Wash, cold wax and buff Quarterly - Remove cobwebs (4 times per year) 3rd year of contract - Hot wax

1MedallionBelvedere
1Pershing Statue
Tactile ModelBelvedere
Skate StopsTriannual - Wash, cold wax and buff
HandrailsAnnual - clean with soft cotton rag and mild degergent, spot patinate as needed
GENERAL MASONRY CLEANING

Equipment Qty Structure Location Required Maintenance

Granite Masonry Biannual - cleaning of general soiling Every five years - Handwash with non-acidic gel/heat pressurized water, rinse until neutral pH achieved

WATER AND POOL FEATURES
See Fountain Technologies O & M manuals for additional maintenance routine
EquipmentQtyStructureRoomLocationDescriptionRequired Maintenance
Pool Area CaulkingTotal CaulkPrior to Spring Startup - Repair/Caulk Pool Joints Approx. Recaulk up to 500 LF
Pumps
DP-11Fountain Equipment Room15 HP Display Feature PumpMonthly
DP-21Fountain Equipment Room25 HP Display Feature PumpVisual Inspection for corrosion Odor test for burnt windings
DP-31Fountain Equipment Room5 HP Display Feature PumpOdor test for burnt windings
FP-12Fountain Equipment Room7.5 HP Filter PumpHeat test for over heating of motors & operating temperature
RP-11Fountain Equipment Room3 HP Recirculating Pump
Filtration Tanks
FA-11Fountain Equipment RoomFilter AssemblyWeekly - Pressure change increase check & back wash system as required
BS-11Fountain Equipment Room16" Basket StrainerDaily - Visual Inspection for debris and clean out as required
BS-21Fountain Equipment Room10" Basket StrainerDaily - Visual Inspection for debris and clean out as required
Water Treatment
CHMT-13Fountain Equipment Room40 Gallon TankDaily - Visual Inspection for liquid chemical levels and fill as required
CHMP-13Fountain Equipment RoomChemical PumpsWeekly - Visual inpsection of pumps & verification of operating parameters
UV -11Fountain Equipment RoomUV Sterilizer and UV StrainerWeekly - UV bulb inspection, operating temperature, dosing rate
Monthly - UV bulb cleaning
WH-11Fountain Equipment RoomHot Water HeaterDaily - Winter season check tempertaure set points are being maintained
WH-21Fountain Equipment RoomHot Water HeaterDaily - Winter season check tempertaure set points are being maintained
Fountain Electrical Equipment
VFD-11Fountain Equipment Room15 HP Variable Frequency DriveMonthly - Audio check of proper operation, manual inspection for overheating
VFD-21Fountain Equipment Room25 HP Variable Frequency DriveMonthly - Audio check of proper operation, manual inspection for overheating
VFD-31Fountain Equipment Room5 HP Variable Frequency DriveMonthly - Audio check of proper operation, manual inspection for overheating
VFD-41Fountain Equipment Room7.5 HP Variable Frequency DriveMonthly - Audio check of proper operation, manual inspection for overheating
VFD-51Fountain Equipment Room3 HP Variable Frecuency DriveMonthly - Audio check of proper operation, manual inspection for overheating
CPPA-11Fountain Equipment RoomControl PanelQuarterly - Visual check for burnt or loose connections, HMI check for errors
UV -11Fountain Equipment RoomUV Sterilizer Control PanelQuarterly - Visual check for burnt or loose connections
WT-11Fountain Equipment RoomWater Treatment ControllerDaily - Manually check chemical readings to pool water samples, alarms or errors
Fountain Miscellaneous Equipment
EW-11Fountain Equipment RoomEmergency Eyewash & HeaterQuarterly - Manual check for proper operation
V-XFountain Equipment RoomMotorized, Actuated, Solenoid Controlled ValvesQuarterly - Manual check for proper operation