B08_Attachment_07_Constructability_Checklist.xlsx

XLSX spreadsheet 32 KB Posted

Attached to
SHEN 312442 Design-Build Federal contract opportunity
Solicitation number
140P2022R0050
Issued by
Department of the Interior National Park Service National Office

About this file

This constructability checklist template is for a design-build project to rehabilitate approximately 54 miles of Skyline Drive and 19 overlooks associated with Skyline Drive at Shenandoah National Park. The project will include design and construction services for surface treatments such as crack sealing, chip sealing, or thin overlay of hot mix asphalt, along with a 2-inch mill and overlay treatment on 19 miles of Skyline Drive. All pavement will receive new pavement markings and road shoulder stabilization. The checklist identifies constructability issues to address in developing construction documents and the request for proposal. It provides guidance on resource protection, site access, staging, permitting, phasing requirements, and other considerations. Resolution of issues will be incorporated into the final design and contract documents.

View the file

Other files for this federal contract opportunity

Other files attached to SHEN 312442 Design-Build, newest first.
File Type Posted
B08_Attachment_15_WD_Rockingham_1-7-22_0003.pdf PDF
B08_Attachment_13_WD_Madison_and_Page_1-7-22_0003.pdf PDF
A0003_Site_Visit_Attendee_List_140P20220050_0003.pdf PDF
B08_Attachment_12_WD_Greene_1-7-22_0003.pdf PDF
B08_Attachment_11_WD_Augusta_1-6-22_0003.pdf PDF
140P2022R0050_A0003_0003.pdf PDF
SHEN_312442_PreProposal_Presentation_1_24_2022_0003.pptx PPTX presentation
QA_1-27-22_0003.pdf PDF
B08_Attachment_16_WD_Warren_1-7-22_0003.pdf PDF
B08_Attachment_14_WD_Rappahannock_1-7-22_0003.pdf PDF
Page_50_Amended_0003.pdf PDF
B08_Attachment_10_WD_Albemarle_1-7-22_0003.pdf PDF
Sol_140P2022R0050_Amd_0003.pdf PDF
140P20220050_A0002_0002.pdf PDF
Sol_140P2022R0050_Amd_0002.pdf PDF
140P2022R0050_A0001_0001.pdf PDF
Sol_140P2022R0050_Amd_0001.pdf PDF
B08_Attachment_14_WD_Rappahannock_11-12-21.pdf PDF
B08_Attachment_10_WD_Albemarle_11-12-21.pdf PDF
B08_Attachment_06_Pavement_Evaluation_Report.pdf PDF
B08_Attachment_04_Overlook_Drawings.pdf PDF
B08_RFP_140P2022R0050_SHEN_312442.pdf PDF
B08_Attachment_01_Scope_of_Services.pdf PDF
B08_Attachment_18_SHEN_HQ_Campus_Map.pdf PDF
B08_Attachment_17_Vaccination_Forms.pdf PDF
B08_Attachment_16_WD_Warren_11-12-21.pdf PDF
B08_Attachment_15_WD_Rockingham_11-12-21.pdf PDF
B08_Attachment_13_WD_Madison_and_Page_5-28-21.pdf PDF
B08_Attachment_12_WD_Greene_11-12-21.pdf PDF
B08_Attachment_09_Proposal_Submission_Package.docx DOCX document
B08_Attachment_05_Overlook_Specifications.pdf PDF
B08_Attachment_11_WD_Augusta_11-12-21.pdf PDF
B08_Attachment_03_Skyline_Specifications.pdf PDF
B08_Attachment_02_Skyline_Drawings.pdf PDF
Sol_140P2022R0050.pdf PDF
B08_Attachment_08_Submittal_List_Estimate.xlsx XLSX spreadsheet
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Template

NPS Constructability Checklist
National Park Service (NPS) - Denver Service Center (DSC) | 3-20-18
For instructions, see Instructions tab below.
Date:6/25/21Project Title:Pavement Improvements at Shenandoah National Park
Park:SHENCompleted By:Hannah Rockwell, HDR inc.
PMIS:

(Project Management Information System) 312442 DBB or DB:

(Design-Bid-Build

OR Design-Build)DB
Item NumberProject IssuesSD Comments
Schematic DesignDD or RFP Comments

Design Development (DBB) OR Request for Proposal (DB) CD or RFP Resolution Construction Documents (DBB) OR Request for Proposal (RFP)

PROJECT INTRODUCTION
1ANY NON-TYPICAL CONTRACT LINE ITEMS OR MISCELLANEOUS CONTRACT CONCERNSN/A
2RECOMMENDED CONTRACT LENGTH; SEASONAL BREAKS IN CONTRACT; IDENTIFY CONTRACT TIMING ISSUES THAT NEED TO BE ADDRESSED; IDENTIFY SPECIFIC PHASING REQUIREMENTSPhasing Requirement: DB contractor will be permitted to close and work on up to 5 overlooks at any one time. No consecutive overlooks may be closed at the same time.
PERMITTING & COMPLIANCE
3

External Permit

or ApprovalLIST REQUIRED GOVERNMENT FURNISHED PERMITS AND APPROVALS: List by Agency-Type: Example: USACE-CWA404 NWP18. Include contact, and phone number.N/A
4

External Permit

or ApprovalLIST REQUIREMENTS FOR GOVERNMENT FURNISHED PERMITS: Include inspections, meetings, close out requirements, and drawings.N/A
5

External Permit

or ApprovalLIST REQUIRED CONSTRUCTION CONTRACTOR FURNISHED PERMITS AND APPROVALSN/A
6

External Permit

or ApprovalDESCRIBE WHERE AND HOW PERMIT REQUIREMENTS ARE INCLUDED IN DESIGN PACKAGE: For each permit, describe requirement, specification (section and paragraph) and/or drawing number.Permit requirements are listed in the RFP section 2.1.1
7
Internal ComplianceIDENTIFY COMPLIANCE REQUIREMENTS:
SHPO, NEPA, EA: List requirement, status, and date or expected date.N/A
8
Internal ComplianceCOMPLETE ALL APPROVALS: Director's, DAB, Congressional Funding issues, estimate within available funds? Adequate time to complete work within project and funding constraints?N/A
9
GeneralIDENTIFY REQUIRED SPECIAL INSPECTIONS: List inspecting or approving organization and reason required.N/A
STAGING AND MOBILIZATION
10IDENTIFY AREAS FOR STAGING INCLUDING AREAS FOR PRIME, SUBS, MATERIAL, AND PARKING; IDENTIFY AREAS FOR CONSTRUCTION CAMP IF APPLICABLE:
List drawing number(s) showing staging area(s).Refer to plan sheet 2, general notes.
11IDENTIFY TEMPORARY UTILITIES AVAILABLE FOR CONSTRUCTION: List drawing number or specification section that indentifies available utilities-electrical, phone, non-potable and potable water, sanitary-provider, meter needed, and responsible cost party.N/A
12IDENTIFY CONSTRUCTION LOGISTICS: List drawing numbers that show traffic control, access restrictions, work hour restrictions, bridges, features, other.Traffic Control: plan sheets 4-6 and Specification 01 50 00. Work Hour Restrictions: Specification 01 11 11, section 1.6.
13IDENTIFY IMPACTS TO PARK AND VISITOR OPERATIONS: List drawing number(s) or specification section(s) that identifies impacts (e.g. Visitor Impacts, Neighborhood-Urban Impacts, Detours, Closures).Refer to plan sheets 4-6 and Specification 01 50 00.
14IDENTIFY SITE ACCESS ISSUES: List drawing number(s) or specification section(s) that identify issues (e.g. remote and road type constrained sites, weather closure restrictions, road and bridge load limits, road and tunnel height restrictions, crane and helicopter requirements).N/A
SUBMITTALS
15LIST MATERIAL SUBMITTALS ON CRITICAL PATH;
FOR DESIGN-BUILD (DB), LIST MATERIAL SUBMITTALS REQUIRING GOVERNMENT APPROVALN/A
16LIST LONG LEAD ITEMS; MATERIAL AND EQUIPMENT AVAILABILITY CONCERNS, SPECIAL DELIVERY REQUIREMENTSN/A
17LIST OF SOLE SOURCE MATERIALS AND GOVERNMENT FURNISHED MATERIALS OR EQUIPMENTN/A
SITE LAYOUT / RESOURCE PROTECTION
18TYPES OF RESOURCE PROTECTION REQUIRED: List where and how requirements are included in design package.Refer to plan sheet 2, general notes.
19ACCURATE SURVEY DATA ON PLANS: BMs, TBMs, TOPONo survey data provided, 3R project approach
20PRELIMINARY SITE INVESTIGATION COMPLETE, EXISTING CONDITIONS VERIFIED AND INCLUDED IN PACKAGEPavement condition assessment complete.
21CONSTRUCTION LIMITS CLEARLY SHOWN AND DEFINED FOR BOTH ACCESS AND CONSTRUCTION: List where and how requirements are included in design package.No survey data provided, 3R project approach
22SPECIAL SIGNAGE REQUIREMENTS: Describe and list where requirements are included in design package.N/A
23LIST WORK SAFETY CONCERNS, LOCATION, AND NEEDS: Include Height, Weather, Animal, Aerial, Public Accessibility, Security, Confined Space, Pathologic, Atmospheric, and others.Skyline Drive must stay open for public use during construction, be cautious of winter and wet weather, wildlife awareness, notify park for entry point access.
DEMOLITION
24ALL EXISTING UTILITIES LOCATED AND ACCURATELY SHOWN: Describe where shown.No survey or utility locates during SD design activities, contractor will be responsible for 811 local utility locates.
25TEMPORARY SYSTEMS REQUIRED: Identify for Park or Public: Access, power, water, sanitary, covered access, exhibit relocation, movement assistance, accessibility.N/A
26SALVAGE, RECYCLING, STORAGE, AND DISPOSAL REQUIREMENTS: Who is removing salvageable equipment and where requirements are included in design package?Refer to specification 01 74 19.
27NOISE / DUST / SAFETY CONCERNS FOR PUBLIC OR ENVIRONMENT: Describe where included in design package.Refer to specification 01 57 19.12.
28CONSTRAINTS ON MEANS AND METHODS: Blasting, Burning, Tidal, Weather, Public Accessibility, Existing structures/features, Holidays and Seasonal, Permitting, other.Refer to plan sheet 2, general notes and Specification 01 11 11, section 1.6
29HAZARDOUS MATERIAL CONSIDERATIONS DEMO METHODS AND DISPOSAL STATE AND LOCAL REQUIREMENTS: Describe hazardous materials being addressed, how, and where in design package.Refer to specifications 01 35 23 and 01 74 19.
30ARCHEOLOGICAL MONITORING REQUIREMENTS: Describe what is needed and where in design package. Identify who provides monitor.Refer to specification 01 35 13.22.
CONSTRUCTION
31MATERIAL, EQUIPMENT, LABOR AVAILABILITY FOR REMOTE SITES: Describe issues and where included in design package.Availability is not anticipated to be an issue for roadway repairs.
32SITE ACCESS RESTRICTIONS TO CONSTRUCTION OPERATIONS IF DIFFERENT OR MORE SUBSTANTIAL THAN ITEMS 12 AND 14See items 12 and 14.
33ANTICIPATED WEATHER CONSIDERATIONS, CONSTRUCTION SEASON, OPTIMUM TIME TO ADVERTISE, RECOMMENDED CONTRACT LENGTHWinter construction should not be anticipated. Late winter/early spring is the best time to advertise. Estimated construction period is 6 months.
34PARK / CONCESSION IMPOSED RESTRICTIONS INCLUDED IN DESIGN PACKAGE AND IMPACTS ON SCHEDULE & COSTContractor will be permitted to close and work on up to 5 overlooks at any one time. No consecutive overlooks may be closed at the same time.
35DESCRIBE FULL SCOPE OF WORK FOR LOCAL UTILITY COMPANIES AND CONSTRUCTION CONTRACTOR FOR EACH UTILITYUtility work is not anticipated.
36DESCRIBE DISRUPTION REQUIREMENTS FOR UTILITY CONNECTIONS, CLOSURES, AND MAXIMUM ALLOWABLE INTERRUPTIONS: Describe where addressed in design package.Utility work is not anticipated.
37SPECIFIC PHASING REQUIREMENTS: Detail what and where where provided in design package.Contractor will be permitted to close and work on up to 5 overlooks at any one time. No consecutive overlooks may be closed at the same time.
38DESCRIBE SPECIALIZED MATERIALS/INSTALLATION METHODS CERTIFICATIONS/TRAINING REQUIREMENTS; DETAIL GOVERNMENT REQUIRED SPECIALTY SERVICES OR INSPECTIONS: List requirements.No special inspections, special materials or istallation methods are anticipated.
39COORDINATION WITH PARK OR CONCESSIONAIRE ON BENEFICIAL OCCUPANCY: Grand opening, fixed completion dates, etc.N/A
40ADJACENT or CONCURRENT CONTRACTS COORDINATION / OVERLAPS ON CONCURRENT OR FUTURE CONTRACTSNo concurrent contracts expected.
41VALUE ENGINEERING POTENTIALN/A
PROJECT CLOSEOUT
42TRAINING REQUIREMENTS, CERTIFICATIONS SPECIFIEDN/A
43OPERATION & MAINTENANCE (O&M) REQUIREMENTSN/A
44LIST PERMITS NEEDING CLOSURE AND POINTS OF CONTACT: Describe requirement; include specification and/or drawing location for each.See items 3 through 9.
45POST CONSTRUCTION REQUIREMENTSRefer to section 01 77 00.
46LIST LONG TERM MAINTENANCE NEEDS AND LOCATION IN THE DESIGN PACKAGE.N/A

&8&K01+016NPS Constructability Checklist, 3-20-18 | page &P of &N

Instructions

INSTRUCTIONS FOR NPS CONSTRUCTABILITY CHECKLIST
Introduction - Use the NPS Constructability Checklist as a tool to inspire, document, track, and record project issues as discussed and resolved throughout preparation of Design Development (DD), Construction Documents (CD), and Request for Proposal (RFP) documents. The end result is a completed checklist that identifies project issues and provides the background to complete contract documents (primarily Division 01 Specifications).
Title Block - Enter Date, Park, PMIS Number (Project Management Information System), Project Title, Completed By, and if DBB or DB (Design-Bid-Build (DBB) or Design (DB)) in appropriate row.
Project Issues Column - Typical constructability issues are listed under Project Issues. Insert additional issues as needed to cover project issues not listed. If issues are listed that do not apply, insert N/A.

Project issues are organized to coincide with award and construction phasing of a project. They are organized under headings typically used as summary headings in a project schedule. If these project issues have significant impact on time, impacts should be shown in a projected construction schedule developed during design. This is an effective way to accomplish construction planning, develop realistic expectations, and account for time and cost implications of project issues.

Schematic Design (SD) Column - Complete necessary research to gain full understanding of project issues that will need to be considered. Explain specific issue in general for each project issue.
Design Development (DD) or Request for Proposal (RFP) Comments Column - Develop necessary in-depth research to gain full understanding of project issues that will need to be considered. Explain specific issue in general for each project issue.
Construction Documents (CD) or Request for Proposal (RFP) Resolution Column - Develop strategy on how each project issue will be resolved contractually. Indicate how it will be resolved. Refer to specification or drawing where information is contained. Be as complete as possible. Be specific with language needed to describe a constraint, requirements for specific phasing, potential impacts to cost and schedule, etc.
General - After completing this checklist, make sure resolution to project issues have been incorporated into CDs / RFPs. The Park, Project Manager (PM), and others may be responsible for some items and this should be so noted.