B08_Attachment_01_Scope_of_Services.pdf

PDF 575 KB Posted

Attached to
SHEN 312442 Design-Build Federal contract opportunity
Solicitation number
140P2022R0050
Issued by
Department of the Interior National Park Service National Office

About this file

This is a request for proposal for a design-build project to rehabilitate approximately 54 miles of Skyline Drive and 19 overlooks associated with Skyline Drive in Shenandoah National Park. Work will include design and construction services for surface treatments such as crack sealing, chip sealing, and thin asphalt overlays, as well as 2-inch mill and overlays on 19 miles of Skyline Drive. The project also includes new pavement markings and road shoulder stabilization. The National Park Service is the contracting agency. The solicitation includes requirements for design development documents, construction documents, meetings, schedules, quality control plans, and sustainability requirements. Pricing will be on a lump sum basis for design and construction items. The response due date is March 15, 2022.

View the file

Other files for this federal contract opportunity

Other files attached to SHEN 312442 Design-Build, newest first.
File Type Posted
B08_Attachment_15_WD_Rockingham_1-7-22_0003.pdf PDF
B08_Attachment_13_WD_Madison_and_Page_1-7-22_0003.pdf PDF
Page_50_Amended_0003.pdf PDF
B08_Attachment_10_WD_Albemarle_1-7-22_0003.pdf PDF
Sol_140P2022R0050_Amd_0003.pdf PDF
A0003_Site_Visit_Attendee_List_140P20220050_0003.pdf PDF
B08_Attachment_12_WD_Greene_1-7-22_0003.pdf PDF
B08_Attachment_11_WD_Augusta_1-6-22_0003.pdf PDF
140P2022R0050_A0003_0003.pdf PDF
SHEN_312442_PreProposal_Presentation_1_24_2022_0003.pptx PPTX presentation
QA_1-27-22_0003.pdf PDF
B08_Attachment_16_WD_Warren_1-7-22_0003.pdf PDF
B08_Attachment_14_WD_Rappahannock_1-7-22_0003.pdf PDF
140P20220050_A0002_0002.pdf PDF
Sol_140P2022R0050_Amd_0002.pdf PDF
140P2022R0050_A0001_0001.pdf PDF
Sol_140P2022R0050_Amd_0001.pdf PDF
B08_Attachment_14_WD_Rappahannock_11-12-21.pdf PDF
B08_Attachment_11_WD_Augusta_11-12-21.pdf PDF
B08_Attachment_03_Skyline_Specifications.pdf PDF
B08_Attachment_02_Skyline_Drawings.pdf PDF
Sol_140P2022R0050.pdf PDF
B08_Attachment_07_Constructability_Checklist.xlsx XLSX spreadsheet
B08_Attachment_08_Submittal_List_Estimate.xlsx XLSX spreadsheet
B08_Attachment_10_WD_Albemarle_11-12-21.pdf PDF
B08_Attachment_06_Pavement_Evaluation_Report.pdf PDF
B08_Attachment_04_Overlook_Drawings.pdf PDF
B08_RFP_140P2022R0050_SHEN_312442.pdf PDF
B08_Attachment_18_SHEN_HQ_Campus_Map.pdf PDF
B08_Attachment_17_Vaccination_Forms.pdf PDF
B08_Attachment_16_WD_Warren_11-12-21.pdf PDF
B08_Attachment_15_WD_Rockingham_11-12-21.pdf PDF
B08_Attachment_13_WD_Madison_and_Page_5-28-21.pdf PDF
B08_Attachment_12_WD_Greene_11-12-21.pdf PDF
B08_Attachment_09_Proposal_Submission_Package.docx DOCX document
B08_Attachment_05_Overlook_Specifications.pdf PDF
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SHENANDOAH NATIONAL PARK

VIRGINIA

SOLICITATION NO. 140P2021R0159

PAVEMENT IMPROVEMENTS AT SHENANDOAH NATIONAL PARK

SHEN 312442

DESIGN-BUILD (DB) PROJECT SCOPE

(DB Request for Proposal (RFP))

NATIONAL PARK SERVICE (NPS)

DENVER SERVICE CENTER (DSC)

Template Date 4-10-20 | Page 2 of 45

Table of Contents

............................................................................................................................ PROJECT INTRODUCTION

1.1 SCOPE

1.2 NPS/DSC SHAREPOINT PROJECT WEBSITE

1.3 LOCATION

1.4 BACKGROUND

1.5 DESCRIPTION

1.6 SCHEDULE

DB DESIGN DEVELOPMENT (DD) DOCUMENTS:

100% DRAFT DB CONSTRUCTION DOCUMENTS (CD):

100% COMPLETE DB CONSTRUCTION DOCUMENTS (CD):

COMPLETE STAMPED AND SIGNED DB CONSTRUCTION DOCUMENTS (CD):

CONSTRUCTION:

AS-CONSTRUCTED DRAWINGS:

1.7 NPS CONTACTS & ADDRESS:

1.8 DATA AND MATERIALS PROVIDED BY NPS

............................................................................................................................ PROJECT REQUIREMENTS

2.1 GENERAL REQUIREMENTS

2.1.1 SCOPE OF WORK AND PROJECT SUMMARY/REQUIREMENTS

2.1.2 DEFINITION OF CONTRACT LINE ITEMS

2.1.3 PROGRESS PAYMENTS

2.1.4 PROJECT MEETINGS

2.1.5 PROJECT SCHEDULE

2.2 DESIGN REQUIREMENTS

2.2.1 DB DESIGN DEVELOPMENT (DD) DOCUMENTS AND DB CONSTRUCTION

DOCUMENTS (CD)

2.2.2 ENVIRONMENTAL AND SUSTAINABILITY REQUIREMENTS FOR DESIGN

2.3 CONSTRUCTION REQUIREMENTS

2.3.1 ENVIRONMENTAL AND SUSTAINABILITY REQUIREMENTS

2.3.2 SCHEDULE OF VALUES

2.3.3 CONSTRUCTION SUPPORT

2.3.4 SUBMITTALS DURING CONSTRUCTION

2.3.5 CONSTRUCTION COORDINATION

2.3.6 DIGITAL IMAGES

2.3.7 QUALITY CONTROL

2.3.8 WORKING HOUR RESTRICTIONS

2.3.9 TEMPORARY SERVICES

2.3.10 ACCESS

2.3.11 PRESERVATION OF ADJACENT FEATURES

2.3.12 EXISTING UTILITIES

2.3.13 HAULING RESTRICTIONS

2.3.14 ACCIDENT PREVENTION

2.3.15 TEMPORARY CONTROLS

2.3.16 FIELD ENGINEERING

2.3.17 PROJECT CLOSE-OUT

Template Date 4-10-20 | Page 3 of 45

2.3.18 SUBSTANTIAL COMPLETION AND FINAL INSPECTION

2.4 FORMS

.............................................................................................................. PERFORMANCE REQUIREMENTS

3.1 DESIGN IMPERATIVES

3.2 SUSTAINABILITY

3.3 INTEGRATED DESIGN PRINCIPLES

3.4 FACILITY PERFORMANCE

3.5 ELEMENTS AND PRODUCTS

..................................................................................................................... TECHNICAL REQUIREMENTS

A SUBSTRUCTURE

B SHELL

C INTERIORS

D FACILITY SERVICES

E EQUIPMENT AND FURNISHINGS

F HAZARDOUS WASTE REMEDIATION

G SITE

................................................................................................................................................ ATTACHMENTS

Template Date 4-10-20 | Page 4 of 45

PROJECT INTRODUCTION

Park Acronym and PMIS Number: SHEN 312442

Project Title: Pavement Improvements at Shenandoah National Park

Project Drawing Number: TBD

1.1 Scope

In accordance with terms and conditions of the Contract, the Design-Build (DB) Contractor shall perform the work of this Request for Proposal (RFP) for the National Park Service (NPS) as described below.

Architect-Engineer (A/E) Services required in this RFP shall be performed by licensed Architects and

Engineers registered in Virginia.

The work of this task order shall be performed in accordance with the Denver Service Center (DSC)

Design-Build (DB) Workflows website.

The DB homepage includes links to design phases describing required workflow process from

Predesign (PD) through Construction Documents (CD). Each design phase webpage contains links to definitions, forms, templates, samples, and guidelines.

The DB homepage also includes links to the Design Standards and Design Deliverables sections which provide design requirements and criteria that shall be used for completing the work of this contract:

• Design Standards are arranged by discipline and/or specialty.

• DB Design Deliverables - Content and Format Requirements:

o Design phase submission requirements for:

o Technical content o Submission format (hard-copy and electronic)

In addition, the Information section has links directly to:

• Definitions: A list of terms relevant to design and construction in National Parks.

• Forms/Templates/Samples/Guidelines: A list of forms, templates, samples, and guidelines used for a typical project.

• Law/Regulations/Polices/Guidance: A list of sources for retrieving laws, regulations, policies, and guidance applicable to NPS projects.

• Quality Assurance (QA) Guideline & Review Checklists: Overview of the DSC QA Process for reviewing Design Documents.

In case of conflict between this task order and the DSC DB Workflows website, this task order shall take precedence and shall be used in lieu of conflicting portions.

The A/E remains fully responsible for determining if the standards or provisions cited on the DSC DB

Workflows website have been revised or updated. Any such conflicts between the website and the identified standard or provisions shall be brought to the attention of the Contracting Officer (CO).

https://www.nps.gov/dscw/designbuild.htm https://www.nps.gov/dscw/dstandards.htm https://www.nps.gov/dscw/del_designbuild.htm https://www.nps.gov/dscw/information.htm https://www.nps.gov/dscw/definitions.htm https://www.nps.gov/dscw/publicforms.htm https://www.nps.gov/dscw/laws-policies.htm https://www.nps.gov/dscw/qaguideline.htm

Template Date 4-10-20 | Page 5 of 45

1.2 NPS/DSC SharePoint Project Website

Use the NPS/DSC SharePoint Project website to host and manage project communication and documentation until Final Completion. The project website will be used for:

• Project directory

• Project correspondence

• Meeting agendas and minutes

• Contract modifications documentation and logs

• RFI (Request for Information) form and processing

• Task and issue management

• Photo documentation

• Baseline schedule, schedule updates and calendar management

• Submittal form and processing

• Drawing and specification document hosting, viewing, and updating

• Online document collaboration

• Reminder and tracking functions

• Archiving functions

• Notification of submittal and RFI statuses and current responsible party

Submit to Contracting Officer a list of employees needing access to the NPS/DSC SharePoint Project website. Department of Interior (DOI) will send these users an invitation to register. Once registered on the DOI website, users will be given access to the project website. For login procedures and other

SharePoint information, refer to the DSC Workflows SharePoint Project Website page.

Users are required to have Internet Explorer (IE) version 7 or later and Adobe Acrobat Professional version 9 or later.

1.3 Location

This project is located at Shenandoah National Park, located in the Blue Ridge Mountains in the

Northwestern part of Virginia. The project includes work on Skyline Drive from Mile Posts (5.63 to 15, 15 to 20, 20 to 20.63, 20.63 to 28, and 65.20 to 97.10) and intermittent overlooks and parking areas along Skyline Drive as described in the location tables in Section 1.5.

1.4 Background

Skyline Drive runs from north to south through Shenandoah National Park. The wearing surface for Skyline

Drive has deteriorated due to continued use over time. There are two PS&E sets for this project, which will be referred to as Plan set 1 and Plan set 2 from here on. Plan set 1 includes work at locations where 2” mill and overlay and double chip seal work along Skyline Drive will be performed as detailed below in Table

1.5a. Plan set 2 includes work at various overlooks and ¾” mill and overlay on a section of Skyline

Drive as detailed in Table 1.5b.

https://www.nps.gov/dscw/precon_spproj.htm

Template Date 4-10-20 | Page 6 of 45

1.5 Description

The proposed pavement improvements will remain within the limits of the existing roadway and existing overlooks along Skyline Drive. Work on these project locations include, but are not limited to, chip seal, milling, overlay, roadway excavation and reconstruction, aggregate topsoil treatment, aggregate roadway treatment, planting, curb stops, subbase stabilization, and pavement markings. See the tables below for

Skyline Drive and various overlook work locations:

Table 1.5a

Plan set 1 Work Locations

PMIS Route Number and Name

MP

To

MP

From

Segment

Distance Treatment Designation

(Miles)

310791a Skyline Drive (North) RT. 10A 5.63 15.00 9.37 Double Chip Seal

310791b Skyline Drive (North) RT. 10A 20.00 28.00 8.00 Double Chip Seal

310792a Skyline Drive (Central) RT. 10B 65.20 65.77 0.57 2” mill and overlay

310792b Skyline Drive (South) RT. 10C 65.77 69.00 3.23 2” mill and overlay

310793a Skyline Drive (South) RT. 10C 69.00 71.50 2.50 2” mill and overlay

310793b Skyline Drive (South) RT. 10C 71.50 74.00 2.50 2” mill and overlay

310794a Skyline Drive (South) RT. 10C 74.00 76.50 2.50 2” mill and overlay

310794b Skyline Drive (South) RT. 10C 76.50 79.00 2.50 2” mill and overlay

310795a Skyline Drive (South) RT. 10C 79.00 81.50 2.50 2” mill and overlay

310795b Skyline Drive (South) RT. 10C 81.50 84.00 2.50 2” mill and overlay

310791c Skyline Drive (South) RT. 10C 84.00 97.10 13.10 Double Chip Seal

Table 1.5b

Plan set 2 Work Locations

PMIS Route Number and Name

MP

To

MP

From

Segment

Distance Treatment Designation

(Miles)

222238 Skyline Drive 15.00 20.00 5.00 0.75" mill and overlay

222238 Mount Marshall Trailhead Parking 15.90 10' width Transition Mill

222238 Rangeview Overlook, Entrance #1 17.10 10' width Transition Mill

222238 Rangeview Overlook, Entrance #2 17.15 10' width Transition Mill

222238 Gimlet Ridge Overlook 18.42 10' width Transition Mill

222238 Mount Marshall Overlook 19.02 10' width Transition Mill

222238 Keyser Run Road Parking 19.38 10' width Transition Mill

222238 Little Hogback Overlook, Entrance #1 19.72 10' width Transition Mill

222238 Little Hogback Overlook, Entrance #2 19.76 10' width Transition Mill

222238 Jewell Hollow Overlook Parking 40.00 0.75" mill and overlay

222238 Hazeltop Ridge Overlook Parking 54.60 0.75" mill and overlay

222238 Baldface Mountain Overlook Parking 61.50 0.75" mill and overlay

Template Date 4-10-20 | Page 7 of 45

222238 South River Overlook Parking 63.00 0.75" mill and overlay

222238 Hensley Hollow Overlook Parking 64.60 0.75" mill and overlay

222238 Bacon Hollow Overlook Parking 69.40 0.75" mill and overlay

222238 Eaton Hollow Overlook Parking 70.80 0.75" mill and overlay

222238 Rocky Mount Overlook Parking 71.40 0.75" mill and overlay

222238 Loft Mountain Overlook Parking 74.60 0.75" mill and overlay

222238 Two Mile Run Overlook Parking 76.50 0.75" mill and overlay

222238 Brown Mountain Overlook Parking 77.10 0.75" mill and overlay

222238 Ivy Creek Overlook Parking 77.80 0.75" mill and overlay

222238 Rocky Top Overlook Parking 78.30 0.75" mill and overlay

222238 Horsehead Overlook Parking 88.9 0.75" mill and overlay

222238 Riprap Overlook Parking 91.7 0.75" mill and overlay

222238 Moormans River Overlook Parking 92.3 0.75" mill and overlay

222238 Crimora Lake Overlook Parking 92.9 0.75" mill and overlay

222238 Sawmill Run Overlook Parking, Entrance #1 95.6 0.75" mill and overlay

222238 Sawmill Run Overlook Parking, Entrance #2 96.6 0.75" mill and overlay

1.6 Schedule

Complete work in this RFP according to following schedule:

DB Design Development (DD) Documents:

Submit DB Design Development Documents no later than 30 calendar days after award.

Complete NPS Review no later than 15 calendar days after submitting DB Design Development

Documents.

70% Draft DB Construction Documents (CD):

Continue work on 70% Draft DB Construction Documents during DB Design Development Documents review. After receiving DB Design Development review comments, address and incorporate comments in 70% Draft DB Construction Documents.

Submit 75% Draft DB Construction Documents and responses to NPS Review form with responses to

DB Design Development Documents no later than 30 calendar days after submitting DB Design

Development Documents.

Complete NPS Review no later than 15 calendar days after receiving 70% Draft DB Construction

95% Draft DB Construction Documents (CD):

Submit 95% Draft DB Construction Documents and NPS Review form with responses to 70% Draft DB

Construction Documents review comments no later than 30 calendar days after submitting 70% Draft

DB Construction Documents.

Template Date 4-10-20 | Page 8 of 45

Complete NPS review no later than 15 calendar days after receiving 95% Draft DB Construction

100% Complete Stamped and Signed DB Construction Documents (CD):

Submit Complete Stamped and Signed DB Construction Documents and NPS Review form with responses to 95% Draft DB Construction Documents review comments no later than 15 calendar days after receiving NPS review comments.

Construction:

Construction begins when Contracting Officer issues DB Start Work Notice.

Complete construction no later than September 30, 2023 for substantial completion and final inspection of all construction activities and project close out.

As-Constructed Drawings:

Complete As-Constructed Drawings no later than 21 calendar days after Substantial Completion.

Submit DB Design Development (DD) Documents, DB Construction Documents (CD), and As-

Constructed Drawings to NPS Project Manager (PM).

1.7 NPS Contacts & Address:

Contractual:

Contracting Officer (CO): Jeremiah Rogers, 303-969-2633, Jeremiah_Rogers@nps.gov

Contract Specialist (CS): Jeremiah Rogers, 303-969-2633, Jeremiah_Rogers@nps.gov

Technical:

Project Manager (PM): Jason Hand, (303) 987-2877, Jason_Hand@nps.gov

Project Specialist (PS): Troy Siefert, (303) 987-6655, Troy_Siefert@nps.gov

Contracting Officer’s Representative (COR): Troy Siefert, (303) 987-6655, Troy_Siefert@nps.gov

Alternate Contracting Officer’s Representative (COR): Jason Hand, (303) 987-2877, Jason_Hand@nps.gov

Address:

National Park Service - Denver Service Center

12795 West Alameda Parkway

Post Office Box 25287

Denver, Colorado 80225

1.8 Data and Materials Provided by NPS

NPS will provide to DB Contractor the following data and materials. (Add as attachments in Section 5.)

Template Date 4-10-20 | Page 9 of 45

• Project Program

• Basis of Design Report (BDR)

• Approved Schematic Design Preferred Alternative Documents

• NPS Project Sustainability Checklist

• Audio Visual Design Drawings

• Cultural Resource Reports (CLRs)

• Environmental Assessment (EA)

• Existing Drawings

• Existing Equipment Layout Plans

• Existing Site Map and Underground Utilities

• Finding of No Significant Impact (FONSI)

• Pavement Evaluation Report

• Hazmat Reports

• Historic Drawings

• Historic Photographs

• Historic Structure Reports (HSRs)

• Park Design Guidelines

PROJECT REQUIREMENTS

2.1 General Requirements

2.1.1 Scope of Work and Project Summary/Requirements

The project will consist of, the design and construction of chip seal, micro surfacing, milling, asphalt overlay, roadway excavation and reconstruction, aggregate topsoil treatment, aggregate roadway treatment, planting, curb stops, subbase stabilization, and pavement markings. The project includes work on Skyline Drive and intermittent overlooks and parking areas along Skyline Drive as described in

Tables 1.5a and 1.5b.

The project will include, but not be limited to:

• Construct project

• Provide as-constructed drawings.

• Provide schedule of construction work.

• Provide survey.

• Review Schematic Design preferred alternative provided in the RFP package.

• Review site data.

• Secure work area and provide for continued access to the facility.

• Submit DB Design Development and DB Construction Documents for review and approval, as required.

• Permits include the following:

o General NPDES Permit for Discharges of Stormwater from Construction Activities.

o Section 404 Nationwide Permit (if there will be fill or dredge in Waters of the US).

o Section 401 Water Quality Certification (if a Section 404 Permit is required).

o NPS Special User Permit (if the Park requires one for construction activity).

Template Date 4-10-20 | Page 10 of 45

• Upon award, determine and provide design schedule of work.

2.1.2 Definition of Contract Line Items

In general, explain what is included in each contract line item, limits or cut-off points where one item ends and another begins. If no item exists for a portion of the work, include costs in a related line item.

A. Contract Line Item No. [0001] Skyline Drive, MP 15.00 to MP 20.00 (Rt. 010A) Construction

(PMIS 222246)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

B. Contract Line Item No. [0002] Jewell Hollow Overlook Parking (Rt. 1025) Construction (PMIS

222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

C. Contract Line Item No. [0003] Hazeltop Ridge Overlook Parking (Rt. 1038) Construction (PMIS

222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

D. Contract Line Item No. [0004] Baldface Mountain Overlook Parking (Rt. 1041) Construction

(PMIS 222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

E. Contract Line Item No. [0005] South River Overlook Parking (Rt. 1042) Construction (PMIS

222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

Template Date 4-10-20 | Page 11 of 45

F. Contract Line Item No. [0006] Hensley Hollow Overlook Parking (Rt. 1043) Construction (PMIS

222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

G. Contract Line Item No. [0007] Bacon Hollow Overlook Parking (Rt. 1047) Construction (PMIS

222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

H. Contract Line Item No. [0008] Eaton Hollow Overlook Parking (Rt. 1048) Construction (PMIS

222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

I. Contract Line Item No. [0009] Rocky Mount Overlook Parking (Rt. 1049) Construction (PMIS

222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

J. Contract Line Item No. [0010] Loft Mountain Overlook Parking (Rt. 1051) Construction (PMIS

222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

K. Contract Line Item No. [0011] Two Mile Run Overlook Parking (Rt. 1052) Construction (PMIS

222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

L. Contract Line Item No. [0012] Brown Mountain Overlook Parking (Rt. 1053) Construction

(PMIS 222238)

Template Date 4-10-20 | Page 12 of 45

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

M. Contract Line Item No. [0013] Ivy Creek Overlook Parking (Rt. 1054) Construction (PMIS

222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

N. Contract Line Item No. [0014] Rocky Top Overlook Parking (Rt. 1055) Construction (PMIS

222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

O. Contract Line Item No. [0015] Horsehead Overlook Parking (Rt. 1060) Construction (PMIS

222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

P. Contract Line Item No. [0016] Riprap Overlook Parking (Rt. 1061) Construction (PMIS 222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

Q. Contract Line Item No. [0017] Moormans River Overlook Parking (Rt. 1062) Construction

(PMIS 222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

R. Contract Line Item No. [0018] Crimora Lake Overlook Parking (Rt. 1063) Construction (PMIS

222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

Template Date 4-10-20 | Page 13 of 45

S. Contract Line Item No. [0019] Sawmill Run Overlook Parking (Rt. 1065) Construction (PMIS

222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

T. Contract Line Item No. [0020] Sawmill Ridge Overlook Parking (Rt. 1066) Construction (PMIS

222238)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

U. Contract Line Item No. [0021] Skyline Drive North, MP 5.63 to MP 15 (Rt. 010A) Construction

(PMIS 312442)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the drawings and specifications.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

V. Contract Line Item No. [0022] Skyline Drive North, MP 20 to MP 28.45 (Rt. 010A) Construction

(PMIS 312442)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the drawings and specifications.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

W. Contract Line Item No. [0023] Skyline Drive Central, MP 65.20 to MP 65.77 (Rt. 010B)

Construction (PMIS 312442)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the drawings and specifications.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

X. Contract Line Item No. [0024] Skyline Drive South, MP 65.77 to MP 69 (Rt. 010C) Construction

(PMIS 312442)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the drawings and specifications.

Template Date 4-10-20 | Page 14 of 45

Y. Contract Line Item No. [0025] Skyline Drive South, MP 69 to MP 71.5 (Rt. 010C) Construction

(PMIS 312442)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the drawings and specifications.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

Z. Contract Line Item No. [0026] Skyline Drive South, MP 71.5 to MP 74 (Rt. 010C) Construction

(PMIS 312442)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the drawings and specifications.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

AA. Contract Line Item No. [0027] Skyline Drive South, MP 74 to MP 76.5 (Rt. 010C) Construction

(PMIS 312442)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the drawings and specifications.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

BB. Contract Line Item No. [0028] Skyline Drive South, MP 76.5 to MP 79 (Rt. 010C) Construction

(PMIS 312442)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the specifications and exhibits.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

CC. Contract Line Item No. [0029] Skyline Drive South, MP 79 to MP 81.5 (Rt. 010C) Construction

(PMIS 312442)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the drawings and specifications.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

DD. Contract Line Item No. [0030] Skyline Drive South, MP 81.5 to MP 84 (Rt. 010C) Construction

(PMIS 312442)

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the drawings and specifications.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

EE. Contract Line Item No. [0031] Skyline Drive South, MP 84 to MP 97.1 (Rt. 010C) Construction

(PMIS 312442)

Template Date 4-10-20 | Page 15 of 45

1. This item consists of all work for flexible pavement rehabilitation and additional treatments detailed in the drawings and specifications.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

FF. Contract Line Item No. [0032] Pavement Improvements at Shenandoah National Park (Rt. 010)

Design Services (PMIS 312442)

1. This item consists of all design work for flexible pavement rehabilitation and additional treatments detailed in the drawings and specifications.

2.1.3 Progress Payments

Design Phase - Progress payments will be based on submission, review, and acceptance of design deliverables.

Construction Phase - Progress payments will be based on percentage of work completed on items listed in approved schedule of values. Actual construction completed and in place will form basis for payment.

DB Contractor shall verify percent complete under direction of the Contracting Officer Representative unless Contracting Officer waives this requirement in a specific instance. DB Contractor shall make computations for payment based on Government’s verification of work completed and in place for periods which progress payments are requested.

DB Contractor shall furnish to Contracting Officer originals of field notes and other records relating to basis for payment. Contracting Officer shall use as necessary to determine final amount of progress payments. DB Contractor shall retain copies of material furnished to Contracting Officer.

2.1.4 Project Meetings

Design Meeting

After award of contract and acceptance of Performance and Payment bonds, Contracting Officer will arrange a design meeting with DB Contractor. Meeting agenda shall include the following as a minimum:

• Areas available for use by DB Contractor

• Access requirements of the Park

• Commissioning (review requirements in ASHRAE 0-2005 paragraphs 6 and 7)

• Design schedule (minimum two color hard copies).

• Environmental and sustainability requirements

• Natural and Cultural Resource Protection

• Payments to DB Contractor

• Review and emphasize Park needs and design objectives.

• Modifications during design

Template Date 4-10-20 | Page 16 of 45

• Schedule of Values

• Submittals during design

Preconstruction Meeting

Submit following Part 2 Project Requirement deliverables a minimum of one week prior to

Preconstruction Meeting.

• Accident Prevention Program (APP)

• DB Contractor’s Commissioning Plan (CCxP)

• Evidence of liability insurance coverage and workman’s compensation for DB Contractor and

Subcontractors

• Historic Preservation Treatment Program

• Letter designating your Project Superintendent

• List of required permits

• List of Subcontractors for project (same as proposal)

• Project Schedule with construction portion fully developed

• Quality Control Plan

• Schedule of Values

• Storm Water Pollution Prevention Plan (SWPPP) Submittal process

• Waste Management Plan

• Written statements from Subcontractors certifying compliance with applicable labor standard clauses

After 100% Complete DB Construction Documents are approved (or completed portions of DB

Construction Documents necessary for fast tracking the project), and before start of construction, Contracting Officer will arrange on-site Preconstruction meeting with DB Contractor. Meeting agenda will include the following as a minimum:

• Accident reporting

• Construction schedule (Provide minimum two, color hard copies and electronic copy in software it was created in.)

• Correspondence procedures

• Jobsite safety

• Labor standards

• Lines of Authority

• Modifications

• NPS/DCS SharePoint Project Website

• Park Rules and Regulations

• Payroll reports

• Progress Payments

• Resolution to comments provided by NPS on the Part 2 Project Requirements

• Roles and responsibilities

• Schedule of Values

• Submittal process

Optional DB Construction Documents

Template Date 4-10-20 | Page 17 of 45

• Access road and site constraints.

• Medical emergency processes, availability, emergency numbers, and contacts.

• Park permits.

• Burning construction waste.

• Rules of the road.

• Alcohol use.

• Housekeeping.

• Firearms.

• Pets.

• Natural and Cultural Resource concerns.

• Visitation and public relations.

• Archeological Resources Protection Requirements

• Environmental and sustainability requirements for the Project, required tracking for sustainability (related submittals), and use of NPS Project Sustainability Checklist.

• Saturdays, Sundays, holidays and night work.

• Traffic control.

Progress Meetings

DB Contractor shall participate in weekly telephone conference calls with Contracting Officer and other project team members with updates to following meeting agenda items:

• Approval of minutes of previous meetings.

• Modifications

• Review of off-site fabrication and delivery.

• Requests for Information (RFI) and issues.

• Schedule update. (Provide updated CPM (Critical Path Method) schedule.)

• Status of Project Record Drawings and O&M (Operation & Maintenance) Manuals.

• Submittal status.

• Work in progress and projected.

• Other business relating to work.

2.1.5 Project Schedule

General: DB Contractor shall upload project schedule to NPS/DSC SharePoint Project website and provide two (2) color copies after award and before design meeting. Schedule shall include detailed design phase with design deliverable submission dates, review periods, and summary construction schedule with important milestones included for both phases.

Fully develop construction portion of project schedule and submit to Contracting Officer on NPS/DSC

SharePoint Project website before Preconstruction meeting or construction begins. Update project schedule monthly throughout contract period until project substantial completion. Status date of each schedule update shall be 10 days before progress payment request date.

Construction work cannot begin until Government approval is obtained for either:

• Entire set of 100% Complete DB Construction Documents.

Template Date 4-10-20 | Page 18 of 45

• Fast track construction: 100% Complete DB Construction Documents affecting work to be constructed.

Purpose: Project schedule ensures adequate planning, coordinating, scheduling, and reporting of DB

Contractor’s design and construction activities. Project schedule will assist DB Contractor and

Contracting Officer to monitor work progress, evaluate proposed changes, and process DB Contractor's monthly progress payment requests.

Software: Latest version of Microsoft Project, Primavera Project Planner, SureTrak, or approved equal.

Schedule Development: Project schedule shall cover entire contract period. Late finish date is same as contract’s established completion date.

DB Contractor shall use Critical Path Method (CPM) with limited use of lead or lag durations between schedule activities. DB Contractor's project schedule shall consist of procurement activities (including mobilization, submittal, and fabrication and delivery of key and long-lead procurement items) and construction activities.

DB Contractor's project schedule shall consist of, but not be limited to, the following for each activity:

• Identify activities and numbers numerically (maximum 5-digit). Number activities in increments of 10.

• Concisely describe work represented by activity (maximum 48 characters). Avoid using non-standard abbreviations. Limit work related to each activity to one work trade.

• Activity duration shall be in whole working days with maximum duration 15 work days each, unless otherwise approved by Contracting Officer, except for non-construction activities including mobilization, shop drawing and sample submittals, fabrication of materials, delivery of materials and equipment, and concrete curing.

DB Contractor shall ensure project schedule includes own work and Subcontractor work.

Project schedule shall show sequence and interdependence of activities required for complete performance of work and shall be cost and resource loaded. DB Contractor shall ensure work sequences are logical and project schedule shows a coordinated work plan. Proposed durations assigned to each activity shall be DB Contractor's best estimate of time required to complete activity, considering scope and resources planned. Resource loading of each activity shall list personnel by labor category and equipment type, and capacity proposed to complete activity in duration shown. Include permit requirements and constraints. Consider and include seasonal weather conditions in planning and scheduling of work influenced by high or low ambient temperatures and wind and/or precipitation, to ensure completion of work within contract time.

Project Schedule Updates

Monthly updates: Monthly updates of project schedule shall be an integral part and basic element of estimate upon which progress payments shall be made under this contract. If, in judgment of Contracting

Officer, DB Contractor fails or refuses to provide schedule of values and complete schedule update or revision as specified hereinafter, DB Contractor shall be deemed to have not provided required information upon which progress payment may be made and shall be subject to retainage of a portion of the payment.

Template Date 4-10-20 | Page 19 of 45

Narrative: Include in report:

• Brief description actual progress made during update period.

• Actual and potential delaying activities.

• Impediments to progress.

• Issues related to inclement weather.

• Progress toward established milestones.

• Project float.

• Brief description of work anticipated to be performed in next month.

• Identify minor revisions to schedule for evaluation and accepted or rejected.

As work progresses, indicate Actual Completion percentage for each activity. If schedule update shows late finish date after contract completion date, at a minimum, include the following in narrative with submission:

• Known delays.

• Actions taken to get back on schedule.

• Pending modifications.

• Impediments or constraints affecting progress.

Progress Payments: Update currently accepted construction schedule monthly. If DB Contractor fails to provide monthly updates or revisions to currently accepted construction schedule, a portion of monthly payment may be retained until updates/revisions made.

Time Impact Analysis for Contract Modifications, Changes, Delays, and Contractor Requests

Requirements: When contract modifications or changes are initiated, delays are experienced, or DB

Contractor revises project schedule, DB Contractor shall submit to Contracting Officer a written time impact analysis illustrating influence of each modification, change, delay, or DB Contractor’s request on the contract time.

• Time Extensions: Activity delays shall not automatically mean an extension of contract time is warranted or due to DB Contractor. It is possible that modification, change, or delay will not affect existing critical activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of available total float that may exist within an activity chain of the project schedule, thereby not effecting the contract time.

Time extensions will be granted according with terms of contract.

• Float: Float is not for exclusive use or benefit for NPS or DB Contractor. Extension of contract time is granted only to extent the equitable time adjustments to activity or activities affected by modification, change, or delay exceeds total (positive or zero) float available on a particular activity.

2.2 Design Requirements

2.2.1 DB Design Development (DD) Documents and DB Construction Documents (CD)

Prepare DB Design Development Documents and DB Construction Documents using English System of

Weights and Measurements and according to DSC Design Standards and DSC Design Deliverables -https://www.nps.gov/dscw/dstandards.htm

Template Date 4-10-20 | Page 20 of 45

Content and Format Requirements for DB Design Development Documents and DB Construction

List salient characteristics for products and materials specified. Refer to Guide for Specifiers.

Deliverables

The following deliverables are required (refer to Section 1.6 for schedule) for NPS Review:

• DB Design Development (DD) Documents

Submit 8 hard and electronic, in native formats (no PDF (Portable Document Format) files), copies of the following DB Design Development Documents for review:

▪ Draft DB Design Development Drawings

▪ Divisions 2 through 49 Outline Specifications

▪ Product File

▪ Statement of Structural Tests and Special Inspections

▪ Design Calculations

• 70% Draft DB Construction Documents (CD)

Submit 8 hard and electronic, in native formats (no PDF files), copies of the following 100% Draft

DB Construction Documents for review:

▪ 70% Draft DB Construction Drawings

▪ Divisions 2 through 49 Construction Specifications (Construction Specifications

Institute (CSI) MasterFormat 04 Edition). A/E shall utilize and modify their own

Divisions 2 through 49 Construction Specifications templates.

▪ Product File

▪ Statement of Structural Tests and Special Inspections

▪ Design Calculations

▪ Checklists for internal review of drawings, specifications, calculations, and cost estimates

• Required documents for each submission are included and complete per contract requirements.

• Required documents have been through a Quality Control (QC) review.

NPS requires documentation and submittal of QC work performed.

▪ NPS Review form with responses to DB Design Development Documents review comments

• 95% Draft DB Construction Documents (CD)

Submit 8 hard and electronic, in native formats (no PDF files), copies of the following 100%

Complete DB Construction Documents for review and final approval:

▪ 95% Draft DB Construction Drawings

▪ Divisions 2 through 49 Construction Specifications

▪ Product File

▪ Statement of Structural Tests and Special Inspections

▪ Design Calculations

▪ Checklists for internal review of drawings, specifications, calculations, and cost estimates

• Required documents for each submission are included and complete per contract requirements.

• Required documents have been through a Quality Control (QC) review.

NPS requires documentation and submittal of QC work performed.

https://www.nps.gov/dscw/del_designdevelopdb.htm https://www.nps.gov/dscw/del_constructiondb.htm https://www.nps.gov/dscw/del_constructiondb.htm https://www.nps.gov/dscw/loader.cfm?csModule=security/getfile&pageid=242817

Template Date 4-10-20 | Page 21 of 45

▪ NPS Review form with responses to 70% Draft DB Construction Documents review comments

• 100% Complete Stamped and Signed DB Construction Documents (CD) o Upon final approval of 95% Draft DB Construction Documents, submit 100% Complete

Stamped and Signed DB Construction Documents per following table for construction, NPS archiving, and general use. For format and media submission requirements, see Design

Deliverables - Content and Format Requirements DB Hard Copy and Electronic Submittal

Requirements.

COMPLETE STAMPED AND SIGNED

DB CONSTRUCTION DOCUMENTS (CD)

ELECTRONIC

FORMATS *

HARD COPY

FORMATS

DB Construction Drawings ** AutoCAD Full-Size Paper

(ANSI D)

Divisions 2 through 49 Construction Specifications

PDF &

MS (Microsoft)-Word

N/A

(Not Applicable)

Product File PDF N/A

Statement of Structural Tests and Special Inspections PDF & MS-Word N/A

Supplemental Design Reports (if applicable) PDF N/A

Design Calculations PDF N/A

Checklists for internal review of drawings, specifications, calculations, and cost estimates PDF & MS-Excel N/A

NPS Review form with responses to 100% Complete DB CD review comments PDF & MS-Excel N/A

* The recipient of the electronic files is TIC (Technical Information Center).

** DB Construction Drawings shall be printed from the native software (e.g. AutoCAD .dwg or Revit .rvt).

DB Construction Drawings printed from secondary software (e.g. Adobe .pdf) are not acceptable as they often result in off-scale product.

2.2.2 Environmental and Sustainability Requirements for Design

NPS established environmental and sustainability requirements for project. Notify Contracting Officer if conflicts arise between performance of work and environmental and sustainability requirements. NPS does not intend to limit alternative means of achieving these requirements.

For sustainability requirements for design, see Part 3 Performance Requirements and NPS Project

Sustainability Checklist. Complete checklist by concisely explaining how each credit/requirement will be met.

2.3 Construction Requirements

2.3.1 Environmental and Sustainability Requirements

Specific sustainability requirements generated in design will dictate more stringent environmental requirements for this project. Refer to Part 3 Performance Requirements and NPS Project Sustainability

Checklist. General requirements:

• Site Disturbance: Minimize construction limits of project to reduce impact on site.

https://www.nps.gov/dscw/del_submitformatdb.htm https://www.nps.gov/dscw/del_submitformatdb.htm https://www.nps.gov/dscw/loader.cfm?csModule=security/getfile&pageid=387018 https://www.nps.gov/dscw/loader.cfm?csModule=security/getfile&pageid=387018

Template Date 4-10-20 | Page 22 of 45

• Toxic Chemicals: Avoid materials that can leach toxic chemicals into ground water. Do not allow toxic chemicals to enter sewers or storm drains or contaminate land or any body of water.

Refer to NPS Project Sustainability Checklist for additional requirements.

• Soil Erosion: Protect against erosion and topsoil depletion according to Stormwater Pollution

Prevention Plan (SWPPP).

• Habitats: Protect natural habitats and ecological systems on facility site as identified in

Environmental Assessment (EA).

• Noise: Minimize noise during construction. Operate power equipment according to local noise restrictions.

• Waste Management: Employ processes ensuring minimal waste output and in landfills.

Recycling is a requirement of this project. Specific recycling goals were established in NPS

Project Sustainability Checklist. Legally dispose materials unsuitable for recycling at public or private dumping areas outside the Park.

DB Contractor shall designate an on-site party (or parties) responsible for instructing workers and overseeing environmental and sustainability requirements of this project. Distribute copies of environmental and sustainability requirements to Job Site Foreman and each Subcontractor.

Waste Management Plan: Prior to scheduled Preconstruction meeting, DB Contractor shall submit draft

Waste Management Plan to Contracting Officer for approval. Develop and implement according to

ASTM E1609 and as required in contract documents. Plan shall include, but not be limited to:

• List of recycling facilities, reuse facilities, municipal solid waste landfills, and other disposal area(s) to be used. Include name, location, and phone number.

• List of proposed materials to be reused or recycled.

• List of materials that cannot be recycled or reused with explanation or justification.

• Storage and collection methods of waste and recyclables, handling procedures, and means of keeping recyclables free of contamination.

• Describe means of transporting recyclable materials and estimate frequency of emptying bins.

• Identity person or persons responsible for ensuring project recycling goals are achieved.

• Revise and resubmit Plan per Contracting Officer. Approval of DB Contractor’s Plan does not relieve DB Contractor of complying with applicable environmental regulations.

Progress Documentation: Supplemental to Waste Management Plan, document solid waste disposal, diversion, and cost/revenue analysis, and submit completed worksheet monthly. Use Appendix A -

Project Waste Management Plan Worksheet and report totals to date for column headings. Use

Appendix B for solid waste volume to weight conversions.

Prior to commencement of work, schedule and conduct meeting with Contracting Officer. Discuss proposed Waste Management Plan and develop mutual understanding of details of environmental protection.

Minimize Construction Impacts

Implement following mitigation measures to minimize impacts of construction activities:

Soil Erosion: Protect against erosion and topsoil depletion. SWPPP is required.

Template Date 4-10-20 | Page 23 of 45

Exotic Vegetation and Noxious Weeds: Prevent introduction and minimize spread of exotic vegetation and noxious weeds. Incorporate following procedures:

• Obtain fill, rock, or additional topsoil needed from a Government approved source.

• Use approved native seed and/or plants and revegetate areas disturbed by construction.

Vegetation Salvage and Revegetation Plan: Required for this project. For revegetation efforts, use approved native species and/or native seed and incorporate Park policies regarding vegetation and site restoration. Consider use of native species, plant salvage potential, exotic vegetation and noxious weeds, and pedestrian barriers. Policy related to revegetation will be referenced in NPS Management Policies

2006 (Section 9.1.3.2).

Special Status Species: To protect unknown or undiscovered threatened, endangered, or special status species, construction contract will include provisions for these discoveries. DB Contractor should contact Park for direction to evaluate special species at the site.

Visitor Experience: Incorporate following mitigation measures into action alternatives to minimize impacts of construction activities on visitor experience:

Air and Water Pollution Control: Air quality impacts are expected to be temporary and localized. To minimize these impacts, take following actions:

• To reduce tailpipe emissions, do not leave construction equipment idling longer than necessary for safety and mechanical reasons.

• To reduce construction dust, apply water to problem areas. Limit equipment to fenced project area to minimize soil disturbance and dust generation.

• Take necessary reasonable measures to reduce air and water pollution with material or equipment used during construction. Keep volatile wastes in covered containers.

• Storm Water Pollution Prevention Plan (SWPPP): Submit a SWPPP, according to applicable

State Water Resources Control Board's (SWRCB) requirements, to Contracting Officer for approval. (See Technical Requirements.) Before starting construction, DB Contractor shall implement approved SWPPP.

Cultural Resources: An Archeological Monitor will be present at work site. If archeological resources are discovered at project site while Archeological Monitor is absent, immediately stop work in vicinity of discovery and report discovery to Contracting Officer.

2.3.2 Schedule of Values

After contract award and before Design Meeting, submit schedule of dollar value based on Contract

Price Schedule. Breakdown each lump-sum item into component parts of design deliverables or construction work for which…