B.08.01_Solicitation_20R6003.pdf

PDF 2 MB Posted

Attached to
Hydrant Fueling Systems Alterations
Solicitation number
W9127S20R6003
Issued by

About this file

This solicitation requests proposals for the construction of hydrant fueling system alterations at Little Rock Air Force Base. Key details include providing a new pump house near the bulk fuel farm with three 600-GPM pumps, filter separators, and associated piping and valves. Proposals are due by September 16, 2020. The award is set aside for total small businesses. The Army Corps of Engineers Engineering District in Little Rock is the contracting agency. Pricing terms include completion within 525 days and a firm fixed price contract.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Title: DLA Fuel Hydrant Alterations, Little Rock Air Force Base

Set Aside: Total Small Business Set-Aside

NAICS Code: 237120 Size Standard: $39,500,000

Magnitude of Construction: Betw een $10,000,000 & $15,000,000

A Request for Information (RFI) Review has been set up for this RFP in ProjNet https://w w w .projnet.org/projnet/. The Bidder Inquiry Key is:

N248XP-RV55SS. All questions and inquiries w ill be accepted only via the ProjNet w ebsite. The review is open from 10 AUG 20 to 31 AUG 20 12:00 pm CT

MARCUS D MITCHELL 501-340-1253

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

12-Aug-2020

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________525 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________2 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________16 Sep 2020 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

CONTRACTING DIVISION

USACE, LITTLE ROCK (W9127S)

700 W. CAPITOL AVE, RM 7315

LITTLE ROCK AR 72201-3225

W9127S

PAGE OF PAGES

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

01:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

(501) 324-5196FAX:TEL: (501) 340-5720 TEL: FAX:

W9127S20R6003 1 OF 60

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

CLIN SCHEDULE

CONTRACT LINE ITEM PRICING SCHEDULE

Item No. Description of Item Estimated Quantity

Unit Unit Price Amount

BASIC ITEMS

0001 All work complete for the Tank Farm Upgrades including tanks, piping, valves, supports, infrastructure for Automatic Tank Gauging System and other supporting work, excluding Option Item 0017.

1 JOB XXX $____________

0002 All work complete for new Bulk Pumphouse Building out to a point 5 feet outside of the building. 1 JOB XXX $____________

0003 All work complete for the two new Truck Fillstands.

1 JOB XXX $____________

0004 All work complete for the two new Truck Unload Stands and Piping. 1 JOB XXX $____________

0005 All work complete for the Fuel Fill Piping.

1 JOB XXX $____________

0006 All work complete for the Hydrant Loop Piping.

1 JOB XXX $____________

0007 All work complete for Site Preparation for new work, excluding work covered in other Basic work items and Option Items.

1 JOB XXX $____________

0008 All work complete for Site Utilities including but not limited to storm drainage systems, water and sanitary sewer systems, site electrical and communication utility systems, cathodic protection, MPC & recovery racks, and all associated excavation and backfill for the various systems, excluding work covered in Other Basic Work items and Option Items.

1 JOB XXX $____________

0009 All work complete for Site Improvements, including but not limited to various concrete and asphalt paving systems, concrete curbs, islands, bulk tank containment and dike system, dike pavement, pipe supports and mechanical pads, excluding work covered in Other Basic Work items and Option Items.

1 JOB XXX $____________

0010 All work completed for As-Built Drawings, Operation and Maintenance Manuals and Closeout Documents. 1 JOB XXX $____________

TOTAL BASIC]MOUNT (ITEMS 0001 THRU 0010) $____________

OPTION ITEMS

0011 All work complete for Hazardous Material Survey for

Asbestos Containing Materials and Lead Based Paint for existing pumphouses scheduled for demolition/alterations.

1 JOB XXX $____________

0012 Additional amount to provide ATG Equipment Systems for tanks.

1 JOB XXX $____________

0013 All work complete for demolition of existing Pumphouses 1 and 6 and associated equipment, Underground Storage Tanks, Fillstands 1 and 2 and associated equipment, piping, miscellaneous components, and generator shelter, excluding Options listed below. See Sheets GD110 and GD120 for demolition information for CLIN 0013.

1 JOB XXX $____________

0014 All work complete for pavements and miscellaneous selective demolition of the existing Type II underground hydrant piping including but not limited to pipe abandonment and grouting for lateral control pits and lines, control pit covers and associated paving, excluding pavements included in CLIN item 0009. See Sheets GD110 and GD120 for demolition information for CLIN 0014. See Note 6 on these sheets for pavement work.

1 JOB XXX $____________

0015 All work complete for abatement of asbestos containing pipe and tank gaskets in Facilities 70 and 1346, 290 Gasket $________/gask et

0016 All work complete for abatement of asbestos containing pipe insulation (assume 6-inch pipe) in Facilities 70 and 1346, 585 Lineal Foot

(LF)

$______/Lineal Foot

0017 All work complete for abatement of lead paint for existing pumphouses. 1015 Square Feet

(SF)

$______/SF $____________

0018 All work complete for handling, and proper disposal of petroleum contaminated soil and notification to regulatory agencies for petroleum contaminated soil that cannot be reused on-site for backfill purposes. Stockpiling and testing is included in Basic Work Items.

25 Cubic Yards (CY)

$__________/C Y

0019AA

0019BB

All work complete for containerizing, and proper disposal of petroleum contaminated groundwater and notification to regulatory agencies for petroleum contaminated groundwater for petroleum contaminated groundwater that cannot be discharged to sanitary sewer.

For the first 400 gallons

Over 400 gallons

4000_

Gallons

Gallons

$_______/gallon

$_______/gallon

0020 Add an extended warranty for a period of one (1) year following the expiration of the original one (1) year warranty period.

1 JOB XXX $____________

TOTAL OPTION ITEMS AMOUNT (ITEMS 0011 THRU 0020)

TOTAL AMOUNT (BASIC PLUS ALL OPTION ITEMS) $____________

Notes:

1. Duration of the base bid including any options that may be awarded is 525 Days.

2. Offerors must insert a price on all numbered items of the CLIN pricing schedule. Failure to do so may result in the offer being unacceptable. Additions will be subject to verification by the Government. In case of variation between the Job (lump-sum) prices and the total amount, the lump-sum prices will be considered the price. In case of variation between the unit prices and the extensions, the unit prices will be considered the price submitted. The Government reserves the right to exercise the options Item 0011 through 0013 and option 0020 within 180 days after issuance of Notice to Proceed. The government reserves the right to exercise Option Items 0014 through 0016 after work is completed for Option Item 0011. The Government reserves the right to exercise Option Item 0017 within 180 calendar days after Notice to Proceed. The Government reserves the right to exercise Option Items 0018 and 0019 anytime during performance of the work. See FAR 52.217-5 Evaluation of Options. CLIN Item 0019 - See

AFARS 5152,211-9001 VARIATION IN ESTIMATED QUANTITIES – SUBLINE ITEMS.

3. (FAR 52.217-5) EVALUATION OF OPTIONS (JUL 1990)

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

(End of provision)

4. (FAR 52.232-18) AVAILABILITY OF FUNDS (APR 1984)

Funds are not presently available for this contract. The Government's obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.

5. (AFARS 5152.211-9001) VARIATIONS IN ESTIMATED QUANTITIES - SUBLINE ITEMS (DEC 2019)

This Variation in Estimated Quantities Clause is applicable only to item No.0019.

(a) Variation from the estimated quantity in the actual work performed under any second or subsequent subline item or elimination of all work under such a second or subsequent subline item will not be the basis for an adjustment in contract unit price.

(b) Where the actual quantity of work performed for item No.0019 is less than 85 percent of the quantity of the first subline item listed under such item, the Contractor will be paid at the contract unit price for that subline item for the actual quantity of work performed and, in addition, an equitable adjustment shall be made in accordance with the clause at Federal Acquisition Regulation (FAR) 52.211-18, Variation in Estimated Quantities.

(c) If the actual quantity of work performed under item Nos. 0019 exceeds 115% or is less than 85% of the total estimated quantity of the subline item under that item and/or if the quantity of work performed under the second subline item or any subsequent subline item under item Nos. 0019 exceeds 115% or is less than 85% of the estimated quantity of any such subline item, and if such variation causes an increase or a decrease in the time required for performance of this contract the contract completion time will be adjusted in accordance with the clause FAR 52.211-18, Variation in Estimated Quantities.

(End of clause)

CLAUSES INCORPORATED BY REFERENCE

52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 52.217-5 Evaluation Of Options JUL 1990 52.232-13 Notice Of Progress Payments APR 1984 52.236-28 Preparation of Proposals--Construction OCT 1997 252.215-7013 Supplies and Services Provided by Nontraditional Defense

Contractors.

JAN 2018

CLAUSES INCORPORATED BY FULL TEXT

52.211-6 BRAND NAME OR EQUAL (AUG 1999)

(a) If an item in this solicitation is identified as “brand name or equal,” the purchase description reflects the characteristics and level of quality that will satisfy the Government's needs. The salient physical, functional, or performance characteristics that “equal” products must meet are specified in the solicitation.

(b) To be considered for award, offers of “equal” products, including “equal” products of the brand name manufacturer, must--

(1) Meet the salient physical, functional, or performance characteristic specified in this solicitation;

(2) Clearly identify the item by--

(i) Brand name, if any; and

(ii) Make or model number;

(3) Include descriptive literature such as illustrations, drawings, or a clear reference to previously furnished descriptive data or information available to the Contracting Officer; and

(4) Clearly describe any modifications the offeror plans to make in a product to make it conform to the solicitation requirements. Mark any descriptive material to clearly show the modifications.

(c) The Contracting Officer will evaluate “equal” products on the basis of information furnished by the offeror or identified in the offer and reasonably available to the Contracting Officer. The Contracting Officer is not responsible for locating or obtaining any information not identified in the offer.

(d) Unless the offeror clearly indicates in its offer that the product being offered is an “equal” product, the offeror shall provide the brand name product referenced in the solicitation.

(End of provision)

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a firm fixed price contract resulting from this solicitation.

(End of provision)

52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY

2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of provision)

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance

Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

Pulaski County 15.7% Nationwide Goal 6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Little Rock Air Force Base, Jacksonville (Pulaski County), AR

(End of provision)

52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT--CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American --Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested--

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of provision)

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of provision)

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

US Army Corps of Engineers Attn: Marcus D. Mitchell, Contracting Officer 700 W. Capitol Avenue Room 7315 Little Rock, AR 72201

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of provision)

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for-- 25 August 2020at 1:00 PM CDT

(c) Participants will meet at-- 19th CES Parking Lot, 528 Thomas Avenue on the LRAFB

(End of provision)

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/content/regulations

(End of provision)

SITE VISIT INFORMATION

Pre-Proposal Site Visit

When: 20-AUG-2020

Time: 1:00 PM CST

Base Access Location: Little Rock AFB Visitors Center 1500 Vandenberg Blvd.

Jacksonville, AR 501-987-3425

Base Access Requirements: REAL ID compliant valid driver's licenses are required (reference https://www.dhs.gov/real-id). Current Air Force IDs or retired military IDs are also acceptable.

Drivers will need current registration and proof of insurance for their vehicle (or a rental agreement). The Government will provide the required sponsorships and subsequent escorting. DO NOT enter the installation without your escort.

Please also ensure that each person requesting access does not have any current warrants or civil actions pending (he/she will not be allowed on the installation if they do). Also see ENCLOSURE 1, “Negative Fitness Determination For Installation Access” on page 2 of 2.

Base Access COVID-19 Protocols: At the Visitors Center, facemasks are required and document exchange will be "touchless." Only one party will be allowed in the Visitors Center at a time so please arrive early and anticipate a slow process. NOTE: Security Forces will be asking about travel history. If your travel history indicates that you have arrived from a COVID-19 hotspot (or your state ID indicates you reside in a hotspot), access will likely be denied.

Where: Meet at 19th CES Parking Lot, 528 Thomas Ave. (BRING BOOTS FOR SITE WALK)

- Formal questions will not be answered verbally at the meeting. It is required that you submit all of your formal questions through the ProjNet process. A Request for Information (RFI) Review has been set up for this solicitation in ProjNet https://www.projnet.org/projnet/. The Bidder Inquiry Key is: N248XP-RV55SS.

The RFI review is open from 10 AUG 20 until 31 AUG 20 at 12:00 pm CT.

Site Visit COVID-19 Protocols: Due to the current COVID-19 response efforts and keeping in line with the CDC’s, the Air Force’s, and DoD’s guidance on social distancing, the protocols/requirements for visitors at Little Rock Air Force Base consist of the following:

- No more than ten (10) total participants (including government and offeror personnel) shall be allowed to the formal pre-proposal site visit meeting. This will equate to no more than one (1) representative from each offeror being allowed to attend the “formal” meeting. However, it should be noted that each offeror may bring a maximum of three (3) people to view and walk the site. The formal meeting will either be held in an area that will provide sufficient social distancing or be held outdoors, weather permitting.

- Facemasks are required.

Section 00 21 16 - Instructions to Proposers

INSTRUCTIONS TO OFFERORS

1. Submission of Offers. Submit signed and dated offer at or before the exact time specified in this solicitation. Failure to provide all required documents or information may exclude the offeror(s) from further consideration. Both the electronic copy and paper/hard copy offer will be accepted at the address identified below. Only signed offers submitted on the SF 1442 will be accepted. Emailed and faxed proposals will not be considered.

Submit proposals to:

CONTRACTING DIVISION

USACE, LITTLE ROCK (W9127S)

ATTN: MARCUS D. MITCHELL

700 W. CAPITOL AVENUE, RM 7315

LITTLE ROCK AR 72201-3225

The Packaging:

The Proposals shall be marked:

“Proposals for Solicitation Number: W9127S20R6003 DLA Hydrant Fueling System Alterations LRAFB “DO NOT OPEN”

a. Electronic submissions via email or fax will not be accepted. Offers should be mailed through a commercial/Government carrier or hand carried.

b. This is an electronic solicitation release. No hard copies will be mailed.

Amendments to the solicitation will be posted through the Federal Business Opportunities www.beta.SAM.gov website. It is the responsibility of each Offeror to review the webpage for notice of amendments, updates, or changes to current information.

c. Questions and/or comments relative to these documents should be submitted via e-mail to Mr. Marcus D. Mitchell at Marcus.D.Mitchell@usace.army.mil.

d. Technical inquiries and questions relating to proposal procedures are to be submitted via ProjNet at http://www.projnet.org/projnet . To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system. To self-register go to web page identified above please use the following directions:

Click BID tab select Bidder Inquiry, select agency USACE; enter Key for this solicitation listed below, and your e-mail address, click login.

Fill in all required information and click create user. Verify that information on next screen is correct and click continue.

From this page you may view all proposal inquiries or add inquiry

Offerors will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.

The Solicitation Number is: W9127S20R6003 The Bidder Inquiry Key is: N248XP-RV55SS The Review will be open from August 10, 2020 through August 31, 2020 at 12:00 PM

CDT

Offerors are requested to review the solicitation in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals

Oral explanations or instructions are not binding. Any information given to an offeror which impacts the solicitation and/or offer will be given in the form of a written amendment to the solicitation.

As this is a competitive negotiation acquisition, there is no public bid opening and no information will be given out as to the number of Offerors or the results of the competition until an award is made.

Section 00 22 00 - Supplementary Instructions

EVALUATION CRITERIA

PROPOSAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS

a. REQUIREMENT FOR SEPARATE PRICE AND NON-PRICE PROPOSALS.

(1) Each Offeror must submit both a Price Proposal and a Non Price Factor Proposal. The Price Proposal and the Non Price Factor Proposal must be submitted as separate volumes. Ensure that the outside of each separate volume is clearly marked to indicate its contents; and the identity of the offeror.

Additionally, clearly identify the “original” cost/price proposal and the “original” technical proposal on the outside cover.

(2) Both the Price Proposal and the Non Price Factor Proposal must be received by the closing date and time set for receipt of proposals.

(3) No dollar amounts from the Price Proposal are to be included in the Non Price Factor

Proposal.

(4) All information intended to be evaluated as part of the Non Price Factor Proposal must be submitted as part of the Non Price Factor Proposal. Do not merely cross-reference similar material in the Price Proposal, or vice versa. Also, do not include links to websites in lieu of incorporating information into your proposal.

(5) Do not include exceptions to the terms and conditions of the solicitation in either the technical or price proposal. Should the offer include any standard company terms and conditions that conflict with the terms and conditions of the solicitation, the offer may be determined "unacceptable" and thus ineligible for award. Should the offeror have any questions related to specific terms and conditions, these should be resolved prior to submission of the offer. Notwithstanding the above, the Offeror must clearly describe in the Proposal Cover Sheet submitted with the Price Proposal any exceptions to the contractual and/or technical terms and conditions of the solicitation contained in the Offer.

b. DISCUSSIONS. The Government does not intend to enter into discussions in accordance with FAR 52.215-1, Instructions to Offerors—Competitive Acquisitions.

c. COST OR PRICING DATA. Offerors are not required to submit Cost or Pricing Data with their offers.

d. GENERAL INSTRUCTIONS.

(1) Submit only the hard-copy paper documents and the electronic files specifically authorized and/or required elsewhere in this section. Do not submit excess information, to include audio-visual materials, electronic media, etc.

(2) Use only 8 ½ by 11 inch paper for hard copy submissions, unless another paper size is specifically authorized elsewhere in this section for a particular submission. Do not use fold-outs (e.g., 11” x 14” or 11” x 17” sheets) unless specifically authorized in this section for a particular submission. Do not use a font size smaller than 10, an unusual font style such as script, or condensed print for any submission. All page margins must be at least 1 inch wide, but may include headers and footers.

(3) The preferred method for assembling your proposals is to use three-ring binders; however, the use of pressboard or other report covers with compression or other type fasteners is acceptable. Do not use spring clamps or exceed the recommended capacity of the fastener or binder. Do not use plastic multi-hole/spiral binding systems, heat binding systems, or other systems which do not facilitate the ready insertion of additional pages.

(4) “Confidential” projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can be provided to the Government as part of the Offeror’s technical proposal. Offerors that include in their proposals information that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, must be clearly marked in accordance with the instructions at FAR 52.215-1, “Instructions to Offerors— Competitive Acquisition”, paragraph (e), “Restriction on disclosure and use of data”.

(5) In the case of an Offeror that is part of a large, multi-segmented business concern, provide information directly pertaining to the specific segment of the business concern (i.e., the division, group, unit, etc.) that will perform work under the prospective contract.

(6) For submissions with page limitations, the pages will be counted as follows: One side of the paper is one page; information on both the back and front of one sheet of paper will be counted as two pages. Where authorized, fold-out pages (11" x 14" or 11" x 17") will count as one page. Pages furnished for organizational purposes only, such as a “Table of Contents” or divider tabs, are not included in the page limitation.

e. SPECIFIC INSTRUCTIONS FOR THE PRICE PROPOSAL

(1) Number of Sets of the Price Proposal. Submit two (2) Hard Copies and 2 CD ROM copies of the Price Proposal. Please note that number of copies reflected in block 13A of the SF1442 is referencing the number of hard copies for the price proposal only.

(2) Size Restrictions and Page Limits. Use only 8 ½” x 11” pages. There are no page limits set for the price proposal. However, limit your response to information required by this solicitation. Excess information will not be considered in the Government’s evaluation.

(3) Format and Contents of the Price Proposal and List of Tabs. The Price Proposal shall be appropriately labeled as such and shall be organized as indicated in the following chart. Note: If the Offeror is not required to submit any information under a listed Tab in accordance with the instructions below, that tab can be omitted. However, do not renumber the subsequent tabs.

TAB

CONTENTS OF THE PRICE PROPOSAL

#1

The Proposal Cover Sheet

#2

The SF1442 and Acknowledgement of Amendments

#3

Section 001100, Pricing Schedule

#4

Representations, Certifications, and Other Statements of Offerors (if the offeror does not have electronic certifications in ORCA)

#5

JV Agreement, if applicable.

#6

Pre-Award Survey

#7

Offer Guarantee

(4) Detailed Submission Instructions for the Price Proposal

TAB 1: The proposal cover sheet is required by FAR 52.215-1(2) (c) (i)-(v) and must be submitted by all offerors. This provision, titled “Instructions to Offerors—Competitive Acquisition,” and the format for the proposal cover sheet as shown here:

PROPOSAL COVER SHEET

1. Solicitation Number:

2. The name, address, and telephone and facsimile numbers of the Offeror (and electronic address if available):

3. A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item. Statement to include any exceptions in technical or cost/price proposal or exceptions inherent in Offeror’s standard terms and conditions.

4. Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the Offeror’s behalf with the Government in connection with this solicitation:

5. Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.

TAB 2: The SF 1442, Solicitation, Offer, and Award is to be completed by all Offerors and duly executed with an original signature by an official authorized to bind the company in accordance with FAR 4.102. All amendments must be acknowledged by all Offerors in accordance with the instructions on the Standard Form 30, Amendment of Solicitation.

TAB 3: Section 001100, Pricing Schedule is to be completed in its entirety by all Offerors.

See Section 001100 with attached notes, for further instructions.

TAB 4: All Offerors must have electronically completed the annual representations and certifications on the “Online Representations and Certifications Application” (ORCA) website or respond with the completed representations / certifications found in the solicitation.. The offerors are responsible for ensuring that these on-line Representations and Certifications are updated as necessary to reflect changes, but at least annually to ensure that they are kept current, accurate and complete. Additionally, the offeror must also complete and return the “Representations, Certifications, and Other Statements of Offerors” included in the solicitation. If the offeror is a Joint Venture, all participants must separately complete both the ORCA Representations and Certifications.

TAB 5: If the Offeror is a Joint Venture (JV), include a copy of the JV Agreement. If a JV

Agreement has not yet been finalized/approved, indicate its status. JV Agreements must clearly indicate the percentages of the JV participants, in particular the percent of the controlling party, and a clear delineation of responsibilities and authorities between the JV parties.

TAB 6: The Pre-Award Survey (found on the following pages) must be completed by all offerors and submitted as part of their price proposal. This document will be used by the Contracting Officer for the Contracting Officer’s Determination of Responsibility done prior to contract award in accordance with FAR Part 9.

TAB 6: Offer Guarantee must be provided in accordance with FAR 52.228-1.

CONSTRUCTION CONTRACTOR EXPERIENCE DATA

PRE-AWARD SURVEY INFORMATION

DATE:

Firm Name and Telephone Number Main Office Address (Street, City, and State)

Branch Offices Services Rendered Construction Design Consultant

Organization Individual Joint Venture Partnership Corporation

Date Organized Date Incorporated:

State:

Names of Officers and Other Key Personnel

I – PRESENT PAYROLL PERSONNEL (List Number of Each Category Below) Partners:

Officers:

Other Key:

Remainder: Subtotal Permanent:

Maximum Personnel at Any Time:

Date:

Total:

II—EQUIPMENT OWNED III—FINANCIAL DATA AS OF

(DATE): Present Value ($)

Current Assets:

Acquisition Cost ($) Current Liabilities:

Net Worth:

IV—TOTAL VALUE OF CONSTRUCTION AND DEMOLITION

WORK IN PAST 6 YRS EXCLUSIVE OF JOINT VENTURE

(LIST MOST RECENT FIRST)

V—LARGEST JOB EVER

CONTRACTED

(If Other Than in Past Six Years)

$ LARGEST JOB IN PAST 6 YRS Contract Amount:

Date:

Description:

Owner:

$ Contract Amount:

Date:

Description:

Owner:

Avg. Annual Income

VI—TYPE OF WORK IN WHICH FIRM SPECIALIZES

NAME AND POSITION/TITLE OF PERSON SIGNING

SIGNATURE

NOTE: Use reverse side for explanations or detailed description of item(s) reported above.

SCHEDULE A

EXISTING COMMITMENTS

Contract Number and Total Value

Description of the Work

Project Owner*

Performance Period

% of work subcontracted

* PLEASE PROVIDE NAME OF ORGANIZATION, POINT OF CONTACT, AND TELEPHONE NUMBER

FOR CONTACT

SCHEDULE B

EXPERIENCE DATA

List below the principal projects the firm has completed within the past 5 years.

Contract Number and Total Value

Description of the Work

Contact Person for the project and phone number

% of work subcontracted

SCHEDULE C

EQUIPMENT AND PERSONNEL

Provide a detailed statement below as to the availability of specific plant/personnel/equipment needed in order to perform the work in accordance with the contract and schedule requirements of this Request for Proposal and resulting project. Include names of personnel and types of equipment or equipment vendors and availability of each to provide equipment in a timely manner.

f. SPECIFIC INSTRUCTIONS FOR THE NON-PRICE FACTOR PROPOSAL

(1) Number of Sets of the Technical Proposal. Submit FOUR (4) Hard Copies and FOUR (4) CD-ROM Copies of the written Non Price Proposal, with each set separately packaged.

(2) Format and Contents of the Technical Proposal and List of Tabs. The original and all copies of the technical proposal will be appropriately labeled as such. Each set shall be organized using the tabs specified in the following chart.

TAB

CONTENTS OF THE NON-PRICE FACTOR

PROPOSAL

Factor 1

TECHNICAL

Sub Factor 1.1

RELEVANT CONSTRUCTION EXPERIENCE

OF OFFEROR/PRIME

Sub Factor 1.2

PROPOSED TECHNICAL APPROACH

Factor 2

PAST PERFORMANCE

Sub Factor 2.1

PAST PERFORMANCE

(3) Page Limitations. See paragraphs d.(2) and .d.(6) in attachment 3 above for format and page count instructions. The following page limitations are established for each factor described above:

Sub Factor 1.1, Relevant Construction Experience of Offeror/Prime – Limited to 4 double-sided pages or 8 single sided pages

Sub Factor 1.2, Proposed Technical Approach– Limited to 5 double-sided pages or 10 single-sided pages; The Project Schedule shall not exceed 10 11” x 17” single-sided pages

Sub Factor 2.1, Past Performance – No page limitation

Tables of content, proposal cover letters, and tabs between proposal information do not count toward any page limitations in the proposal.

(4) Detailed Submission Requirements for the Technical Proposal. The following is a detailed description of the information to be submitted under each TAB.

(i) TAB 1: SUB FACTOR 1.1, RELEVANT CONSTRUCTION EXPERIENCE OF OFFEOR/PRIME: (Definitions for the purposes of this factor):

Relevant construction project means a construction project located on an active United States military installation (located within the continental United States, Alaska, Hawaii, or United States territory) that is capable of offloading, transferring, storing, and delivering aviation fuel, constructed for the purpose of fueling aircraft.

Substantially completed means at a minimum turned over for beneficial occupancy in its entirety (not partially turned over).

Key Subcontractor means a subcontractor who at a minimum directly performed all the major or critical aspects of a relevant construction project. Major or critical aspects are the facilities or systems for offloading, transferring, storing, and delivering aviation fuel.

The Offeror shall submit a minimum of two (2) and no more than four (4) examples of relevant construction projects on which the Offeror performed either as the prime contractor or as a Key Subcontractor (how the Offeror performed must be clearly indicated).

a) The Offeror may also submit projects where its Key Subcontractor performed either as the prime contractor or as a Key Subcontractor (how the Key Subcontractor performed must be clearly indicated); however, at least one of the total number of submitted projects must have been performed by the Offeror (i.e., all projects submitted cannot have all been performed by the Key Subcontractor). If any project submitted is that of a Key Subcontractor, it must be accompanied by a signed Letter of Commitment from that Key Subcontractor committing them as a member of the team for this project.

b) The submitted projects shall either be 100% construction progress complete or substantially complete within six (6) years from the date of issuance of this solicitation.

At least one project example shall include all elements of the following four phases of airfield fueling: [1] offload, [2] transfer (systems of pumps, filters and pipes), [3] aviation fuel storage, and [4] fuel delivery to equipment that incorporates refueler truck fill stands or otherwise complies with the direct aircraft fueling systems criteria for Type III, IV, or V hydrant fueling systems as specified in the Unified Facilities Criteria (UFC) 3-460-01. The construction contract for this project example shall be a minimum of $10 million in magnitude.

All other project examples shall include at a minimum two (2) elements of the following four (4) phases of airfield fueling, but may include multiple or all phases: [1] offload, [2] transfer (systems of pumps, filters and pipes), [3] aviation fuel storage, or [4] fuel delivery to equipment that incorporates refueler truck fillstands or otherwise complies with the direct aircraft fueling systems criteria for Type III, IV, or V hydrant fueling systems as specified in the Unified Facilities Criteria (UFC) 3-460-01. The construction contract for these project examples shall be a minimum of $7 million in magnitude.

Using a Relevant Experience Matrix similar to that shown below in Table 3, clearly identify to which phase of airfield fueling each project example submitted pertains.

Table 3: Factor A – Relevant Experience Matrix Example

Offload Transfer Aviation

Fuel Storage

Fuel Delivery to Equipment

Project #1 –IAW Para. 5.2.2 (Must have 4 phases of refueling):

Offeror, Project Title, Project Location, Contract Amount, Date of 100% completion or substantial completion

X X X X

Project #2 – IAW Para 5.2.3 (At least 2 phases of refueling):

Offeror, Project Title, Project Location, Contract Amount, Date of 100% completion or substantial completion

X X

Project #3 – IAW Para 5.2.3 (At least 2 phases of refueling):

Offeror, Project Title, Project Location, Contract Amount, Date of 100% completion or substantial completion

X X

Note: Table 3 above is an example. All projects submitted must meet all applicable requirements.

The Offeror shall also submit an explanation briefly justifying each designation in the Relevant Experience Matrix for each submitted example project. This explanation shall not exceed four (4) 8.5” x 11” double-sided pages or eight (8) 8.5” x 11” single-sided pages, regardless of the total number of projects submitted.

a) For each project submitted where work was performed as a Key Subcontractor as opposed to a prime contractor, the Offeror shall submit an additional, separate statement that includes the total contract amount, the dollar amount of the work performed as the Key Subcontractor, a description of the elements of work specifically completed by the Offeror (or the Offeror’s Key Subcontractor) while working as a Key Subcontractor, and the percentage of work performed as the Key Subcontractor of the overall project work. The statement shall also justify how the Offeror (or the Offeror’s Key Subcontractor) meets the definition of “Key Subcontractor” in the context of the example project(s) submitted. The statement shall not exceed two (2) 8.5” x 11” double-sided pages or four (4) 8.5” x 11” single-sided pages. If it is determined by the Government that based on the information provided by the Offeror that it does not in fact meet the definition of a Key Subcontractor, the project will not be considered for evaluation.

If the Offeror submits more than four (4) project examples, the Government will only evaluate the first four (4) submitted projects.

Evaluation Method for this Sub Factor:

Factor A will be evaluated to determine whether the Offeror’s submission meets the requirements of this factor. If any of the required information is not provided in the Offeror’s proposal or fails to meet the requirements, the Offeror will be evaluated as “Unacceptable.”

TAB 1 SUB FACTOR 1.1 - RELEVANT CONSTRUCTION EXPERIENCE OF

OFFEROR/PRIME

R…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .