Attachment J-D Certification of Progress Payments.doc

DOC document 119 KB Posted

Attached to
Safety and Reliability Upgrade, KSC Institutional Power Systems, Phase 4. Federal contract opportunity
Solicitation number
80KSC021R0023
Issued by
National Aeronautics and Space Administration Kennedy Space Center

About this file

This solicitation requests proposals for Safety and Reliability Upgrade work at the Kennedy Space Center Institutional Power Systems in Phase 4. The scope of work involves replacing five 15kV load break switches and two substations at Operations Support Building 1 with new electrical equipment including switchgears, transformers, load break switches, and vacuum fault interrupters. Additional requirements include installation of PLCs, equipment racks, control and power wiring, and sensing devices at the new substations. The project also demands abatement of coatings containing asbestos, heavy metals, and PCBs during removal and replacement of existing equipment. Careful phasing of the work will be necessary to minimize downtime for the operational facility. The award value is estimated between $1-5 million. The performance period is 730 calendar days. This is a small business set-aside solicitation issued by NASA's Kennedy Space Center.

View the file

Other files for this federal contract opportunity

Other files attached to Safety and Reliability Upgrade, KSC Institutional Power Systems, Phase 4., newest first.
File Type Posted
Amendment 06 signed.pdf PDF
Amendment 05 signed.pdf PDF
Amendment 04 signed.pdf PDF
Amendment 03 signed.pdf PDF
Amendment 02 signed.pdf PDF
Amendment 01 signed.pdf PDF
Section L Appendix 4 - Past Performance Questionnaire.docx DOCX document
Attachment J-A Project Deliverables.pdf PDF
Attachment J-B KSC Project Specific Requirements.pdf PDF
Section L Appendix 2 - Acceptable Identity Guide.docx DOCX document
Section L Appendix 5 - Badging Request Form (Secure Area).docx DOCX document
80KSC021R0023 - RFP.pdf PDF
Section L Appendix 1 - KSC Form 28-889 Visitor Badge Request.pdf PDF
Section L Appendix 3 - Pre-Proposal Inquiry Form.xlsx XLSX spreadsheet
Attachment J-C Wage Determination FL20210001 Mod 3.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CERTIFICATION OF PROGRESS PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS

BASED ON A PERCENTAGE OR STAGE OF COMPLETION

(NOV 2014)

SECTION 1 – IDENTIFICATION INFORMATION

1. TO: NAME AND ADDRESS OF CONTRACTING OFFICE (Include Zip Code)

2. FROM: NAME AND ADDRESS OF CONTRACTOR (INCLUDE ZIP CODE, EMAIL ADDRESS, AND PHONE NUMBER)

3. INVOICE NUMBER:
4. INVOICE DATE:
5. CONTRACT NUMBER:
6. PROJECT LOCATION:

7. PROJECT DESCRIPTION:

SECTION 2 – STATUS OF COSTS UNDER THIS CONTRACT THROUGH________________________________

(DATE)

8. ORIGINAL CONTRACT SUM – (Enter The Original Contract Award Amount)
$
9. NET CHANGES – (Enter The Net Dollar Amount Via Changes)
$
10. CONTRACT SUM TO DATE – (Enter The Dollar Amount of the Contract To Date) – (ITEM 8 + 9)
$
11. TOTAL COMPLETED AND STORED TO DATE:
$
12. RETAINANGE – (Enter The Retainage Amount)
$
13. TOTAL EARNED LESS RETAINAGE – (Item 11 less 12)
$
14. PROGRESS PAYMENTS PREVIOUSLY PAID:
$
15. CURRENT PAYMENT DUE: (Item 13 less 14)
$
16. OUTSTANDING BALANCE – (Line 10 Less 13)
$
17. Amount Approved by the Contracting Officer
$

18. PAYMENT CERTIFICATION:

In accordance with the FAR 52.232-5, Payments Under Fixed-Price Construction Contracts, I hereby certify, to the best of my knowledge and belief, that –

a) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract:

b) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

c) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract;

d) This certification is not to be construed as final acceptance of a subcontractor’s performance; and

e) All quality requirements associated with the progress payment CLIN , including but not limited to submission and approval of shop drawings, test reports, Operation and Maintenance (O&M) documentation, equipment and material verification, etc, have been satisfied.

(Name) (Date) (Title)

NAME AND TITLE OF CONTRACTOR REPRESENTATIVE SIGNING THIS FORM:

SIGNATURE:

NAME AND TITLE OF CONTRACTING OFFICER:

SIGNATURE:

Invoice Number
Contract Number

BLK 18. continued –

Para e through j apply to those contracts that contain a contract clause that authorize high cost material/equipment in accordance with Payment for Material Clause in Section H of the Contract.

The following certification relates to high cost material/equipment : 1) high cost material/equipment (with unit or total costs equal to or greater than $50,000 at time of order placement), such as, steel, electrical cabling, transformers, switchgear, HVAC equipment, pumps, machinery, pipe and fittings, and precast/prestressed concrete piles, etc.; 2) long lead special order items; or 3) materials that have been fabricated off-site to the point where they are identifiable to an item of work required under this contract. All materials/equipment submitted for progress payments, must be adequately insured and protected from theft and exposure. Materials that will not be paid for prior to installation include, but are not limited to, bulk quantities such as nails, fasteners, conduits, wall board, insulation, wall covering etc.

e) Attached is a certified paid vendor invoices with canceled check showing title to the items vests with the prime contractor, and includes the value of the material and labor incorporated into the item,

f) The material/equipment will be used to perform this contract only and that; I agree that title to the material/equipment shall vest with the Government, upon payment of the requested progress payment; and that title to any excess material/equipment will vest with the contractor upon the completion and acceptance of the CLIN.

g) The material/equipment conforms to contract requirements and is documented on the Government approved shop drawing(s) for this contract,

h) The attached inventory checklists has been jointly validated by the contractor, contract administrator, and/or Government construction inspector,

i) The attached accepted delivery tickets states the delivery location, and

j) The material/equipment shall not be removed from the delivery location without prior written permission of the Contracting Officer.

CERTIFIED BY:

Signature Signature

Title Quality Manager

Name and Address of Contractor Date

Date

STATEMENT OF VALUES

Project/Job Name:

Payment/Application Number:

Contract Number:

Payment/Application Date:

PCN Number:

Period Through Date:

Item No.
Description of Work
Scheduled Value
Work Completed
Total Completed and Stored to Date
%
Balance to Finish
Previous Application
Completed This Period
Materials Presently Stored
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00

Totals

0
0
0
0
0
0
0

subcontractor payment schedule

Date:

Progress Payment #:

Contractor:

Contract #:

Delivery Order #:

Subcontractor Name
Subcontract Amount
Amount

Paid TO DATE

Due This Period
Total Payments

Authorized High Cost Material/Equipment – Payments to Subcontractors

Name of SubContractor
Date Paid
Voucher No. or Reference
Check Number
Contract Value
Amt. Withheld
Amt. Pd

TOTAL

CLIN Retainage Summary

10% of completed work

10% of approved material

Total CLIN Retainage Withheld

Total remaining CLIN retainage to be paid

File details come from the government source that posted it. Updated .