Amendment 06 signed.pdf

PDF 645 KB Posted

Attached to
Safety and Reliability Upgrade, KSC Institutional Power Systems, Phase 4. Federal contract opportunity
Solicitation number
80KSC021R0023
Issued by
National Aeronautics and Space Administration Kennedy Space Center

About this file

This is a summary of an amendment to a federal solicitation and the related federal contract opportunity. The amendment provides answers to contractor questions regarding replacement of electrical equipment and installation of new substation switchgears, load break switches, and vacuum fault interrupters at various Kennedy Space Center locations. The work includes removal and replacement of two substations in Operations Support Building 1. The safety and reliability upgrade project has a period of performance of 730 calendar days and is anticipated to have an award amount between $1,000,000 to $5,000,000. It is a small business set-aside being conducted by the National Aeronautics and Space Administration Kennedy Space Center under solicitation number 80KSC021R0023. The proposal due date remains May 24, 2021.

View the file

Other files for this federal contract opportunity

Other files attached to Safety and Reliability Upgrade, KSC Institutional Power Systems, Phase 4., newest first.
File Type Posted
Amendment 05 signed.pdf PDF
Amendment 04 signed.pdf PDF
Amendment 03 signed.pdf PDF
Amendment 02 signed.pdf PDF
Amendment 01 signed.pdf PDF
80KSC021R0023 - RFP.pdf PDF
Section L Appendix 1 - KSC Form 28-889 Visitor Badge Request.pdf PDF
Section L Appendix 3 - Pre-Proposal Inquiry Form.xlsx XLSX spreadsheet
Attachment J-A Project Deliverables.pdf PDF
Attachment J-B KSC Project Specific Requirements.pdf PDF
Section L Appendix 2 - Acceptable Identity Guide.docx DOCX document
Section L Appendix 5 - Badging Request Form (Secure Area).docx DOCX document
Section L Appendix 4 - Past Performance Questionnaire.docx DOCX document
Attachment J-C Wage Determination FL20210001 Mod 3.pdf PDF
Attachment J-D Certification of Progress Payments.doc DOC document
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

80KSC021R0023, Amendment 06 (Continued) Page 2 of 3

14. The purpose of this amendment is to answer 10 Contractor questions. The proposal due date remains unchanged.

A. Answers to Contractor Questions.

1. Reference: Drawing 79K40870, Page E103, Note L. Where on the Bid Form do we list the quote for Bid Alternate specified in Note L? We assume that this is part of CLIN 0001 - Package 2 TASK 1.

Answer: Bid Alternate is not in the Scope of this project.

2. Reference: 80KSC021R0023, Section L.18(b)(2). We will not be using major subcontractors

(our subs will be less than 10% of contract value). Can we not submit Technical Experience Summaries and PPQs for the subcontractors?

Answer: You would not need to submit Technical Experience Summaries and PPQs for the subcontractors.

3. Reference: Drawing package 79K40869. Drawing E-001 Note 4 states to provide extra material 15kv cable, splices, elbows, etc. to be turned over to the government. This packages has 5 additive bid items. Which additive bid item shall we place the money for this material?

Or will the bid sheet be revised to add an additional bid additive for this material?

Answer: Place the bid items (extra materials) in Additive 1.

4. Reference: Drawing package 79K40869. For each #4/0 and #350 15kv cable there will be a minimum order quantity (MOQ) of 7500' to 10,000'. This packages has 5 additive bid items, some of which need very little cable. Which additive bid item shall we place the money for this material? Or will the bid sheet be revised to add an additional bid additive for this material?

Answer: Place the bid item (EPR 15KV cable) in Additive 1.

5. Reference: Drawing package 79K40870. E-002 shows a proposed sequence of construction and E-003 shows a bid alternate for the sequence of construction for the temporary power.

There is no bid alternate for Task 1 indicated on the bid form. Please advise.

Answer: Bid alternate (E-003) in not in the scope of this project.

6. Reference: Specification 79K40868 Section 33 77 19.00 40. Section 2.1 Equipment asks for visible break option. We can do this with the Non-Compact Trident however, we cannot provide the front/rear option. The configuration would be all front access. Will the 3" diameter circular viewing windows to verify Open/Close indicator position be sufficient?

80KSC021R0023, Amendment 06 (Continued) Page 3 of 3

This is what has been provided on all prior projects with solid dielectric type switchgear provided to NASA.

Answer: Yes.

7. Reference: RFP Section L.18 Project Execution Plan & Drawing package 79K40870. What is the anticipated award date that we should use in developing our schedule? There are specific work windows found in the sequences of work and this is needed to build the schedule.

Answer: June 2021 is the estimated award date. The work windows are not known at this time. It will be coordinate with facility manager and customers during the project.

8. Reference: Drawing package 79K40870. We are requesting the electrical as-builts drawings for the OSB-1 Facility.

Answer: Will be provided after contract award.

9. Reference: Drawing package 79K40870. Drawing E-603 shows cable 17C routing from

ATS-FPC to SWBD-1127A. Drawing E-105 cable schedule does not indicate a cable 17C.

Please advise.

Answer: Change Drawing E-603 to read 17A, and not 17C

10. Reference: Drawing package 79K40870. Drawing E-105 cable 17A shows (3) 4" RSC with

(9) #14 XHHW-2. Should the conduit size read 3/4"?

Answer: Yes, should read ¾” RSC.

B. The proposal due date remains May 24, 2021 at 2:00:00 PM EDT.

There are no other changes.

Amendment 05 unsigned
Amendment 06 Pages 2-3
topmostSubform[0]:
Page1[0]:
AmendmentNo[0]: 06
Code[0]:
Code[1]:
AccountingData[0]: N/A
A13[0]:
C13[0]:
D13[0]:
NameandTitleSigner[0]:
NameandTitleOfficer[0]: Anthony M. Caruvana
Description[0]: See attached.
FacilityCode[0]:
Code[2]:
IssuedBy[0]: NASA/John F. Kennedy Space Center

Mail Code OP-CS, Attn: Anthony Caruvana Kennedy Space Center, FL 32899

NameandAddress[0]:
AdministeredBy[0]: NASA/John F. Kennedy Space Center

Mail Code OP-CS, Attn: Anthony Caruvana Kennedy Space Center, FL 32899

ContractIDCode[0]:
ReqNumber[0]: N/A
AmendmentNo[1]: 80KSC021R0023
ModificationNo[0]:
ProjectNo[0]: 98966.4
Page[0]: 1
Pages[0]: 3
EffectiveDate[0]: See Block 16C
Dated9B[0]: 4/22/2021
Dated10B[0]:
CheckBox9[0]: Off
CheckBox10[0]: Off
CheckBox11[0]: 1
CheckBox13A[0]: Off
CheckBox13B[0]: Off
CheckBox13C[0]: Off
CheckBox13D[0]: Off
IsNot[0]: Off
Is[0]: Off
Extended[0]: Off
NotExtended[0]: 1
2021-05-20T08:19:36-0400
ANTHONY CARUVANA
DateSigned[0]:
DateSigned[1]: 5/20/2021