ATTACHMENT C COSMOS Schedule.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- ARPA-H Comprehensive Organ System Modeling in Outer Space (COSMOS) Innovative Solutions Opening
- Solicitation number
- ARPA-H-SOL-26-165
About this file
This is a project schedule for the ARPA-H COSMOS (Comprehensive Organ System Modeling in Outer Space) Initiative spanning four fiscal years from FY27 through FY30 (calendar years 2027-2030). The schedule outlines a phased approach consisting of Phase I activities (Development & Testing, Pre-launch Integration and Hardware Validation) and Phase II activities (Launch Phase, Showcase, Model development/Scale Up/Integration Testing, and subsequent launches). The program is organized into 42 months divided into 15 program quarters, with key milestones including Design Lock for the Twin Study Morphological Platform System (MPS) and Commercial Space Platform (CSP) housing specifications, Hardware Validation Launch (HVL), four launch events (L1 through L4), and multiple data analysis periods. Critical governance events include Scientific Review Meetings (SRM) scheduled throughout the program. The schedule incorporates countdown timelines to launch events, with the initial launch occurring at Month 18-19 from program start, followed by additional launches at Months 24, 30, and 36, supporting the program's objective to study tissue aging acceleration in microgravity across multiple organ systems and age brackets to validate cost-effectiveness for autonomous drug screening in Low Earth Orbit.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ARPA-H-SOL-26-165_COSMOS_QA_Set_2_2026-09-25.pdf | ||
| ARPA-H-SOL-26-165_COSMOS_ISO_Amendment 02.pdf | ||
| ARPA-H-SOL-26-165_COSMOS_QA_Set_1_2026-09-21.pdf | ||
| ARPA-H-SOL-26-165_COSMOS_ISO_Amendment 01.pdf | ||
| ATTACHMENT A.1_Technical & Management Proposal Model (VOL I).docx | DOCX document | |
| ATTACHMENT B_COSMOS Eligibility and Conformance Certification Sheet.docx | DOCX document | |
| ATTACHMENT A.3_COSMOS Milestone and Payment Table.xlsx | XLSX spreadsheet | |
| ARPA-H-SOL-26-165_COSMOS_ISO.docx | DOCX document | |
| Attachment E_COSMOS Administrative and National Policy Requirements.docx | DOCX document | |
| Attachment D_COSMOS Cost Proposal Template.xlsx | XLSX spreadsheet | |
| ATTACHMENT A.2_Task Description Document Model.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COSMOS Program Schedule
| FYQuarter | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 | ||||||||||||||||||||||||||||
| Fiscal Year | FY27 | FY28 | FY29 | FY30 | ||||||||||||||||||||||||||||||||||||||
| Calendar Year | 2027 | 2028 | 2029 | 2030 | ||||||||||||||||||||||||||||||||||||||
| Program Year | Year 1 | Year 2 | Year 3 | Year 4 | ||||||||||||||||||||||||||||||||||||||
| Program quarter | PQ1 | PQ2 | PQ3 | PQ3 | PQ4 | PQ4 | PQ5 | PQ5 | PQ6 | PQ6 | PQ7 | PQ7 | PQ8 | PQ8 | PQ9 | PQ9 | PQ10 | PQ10 | PQ11 | PQ11 | PQ12 | PQ12 | PQ13 | PQ13 | PQ14 | PQ14 | PQ15 | |||||||||||||||
| Phase | Phase I | Phase II | ||||||||||||||||||||||||||||||||||||||||
| Month | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | 42 |
| Month | jan | feb | mar | apr | may | jun | jul | aug | sep | oct | nov | dec | jan | feb | mar | apr | may | jun | jul | aug | sep | oct | nov | dec | jan | feb | mar | apr | may | jun | jul | aug | sep | oct | nov | dec | jan | feb | mar | apr | may | jun |
| Program Activities | Development & Testing | Pre launch integration and hardware validation | Launch Phase | Showcase | MPS Model development, Scale Up, and Integration Testing | Showcase | ||||||||||||||||||||||||||||||||||||
| Launches | MPS Design Lock | HVL | L1 | L2 | L3 | L4 | ||||||||||||||||||||||||||||||||||||
| CSP design lock | Data Analysis | Data Analysis | Data Analysis | |||||||||||||||||||||||||||||||||||||||
| Months to Launch 1 | 18 | 17 | 16 | 15 | 14 | 13 | 12 | 11 | 10 | 9 | 8 | 7 | 6 | 5 | 4 | 3 | 2 | 1 | 0 | 11 | 10 | 9 | 8 | 7 | 6 | 5 | 4 | 3 | 2 | 1 | 0 | |||||||||||
| All-Program Meetings | SRM | SRM | SRM | SRM | ||||||||||||||||||||||||||||||||||||||
| Design Lock = Design specifications for Twin Study MPS are finalized; CSP housing Design specifications are finalized | ||||||||||||||||||||||||||||||||||||||||||
| SRM = Scientific Review Meeting | ||||||||||||||||||||||||||||||||||||||||||
| HVL = Hardware Validation Launch |