Attachment A. Projects List.pdf

PDF 460 KB Posted

Attached to
GRPS Environmental Consulting 2023 Bond Projects
Solicitation number
RFP-GRP-250000000186-2
Issued by
Kent County, Michigan

About this file

This document is an Attachment A. Projects List related to a Request for Proposal (RFP) issued by the Grand Rapids Public Schools for Environmental Consulting Services. The attachment provides a detailed list of 27 facility projects across 3 series, with information on the building name, address, square footage, number of floors, program budget, planned construction timeline, and summary of improvements for each project. The projects range from facility renovations, additions, and upgrades to full building replacements, with improvements focused on areas such as elevators, HVAC systems, lighting, technology, parking lots, and playgrounds. The projects are scheduled to take place from 2024 through 2031, with the majority occurring between 2024-2026 and 2028-2030.

The total program budget across all 27 projects is approximately $176 million. Funding sources and detailed pricing terms are not provided. The document indicates that additional locations may be identified in the future.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GRAND RAPIDS PUBLIC SCHOOLS

REQUEST FOR PROPOSAL (RFP) – ENVIRONMENTAL CONSULTING SERVICES

ATTACHMENT A - PROJECT LIST

OCTOBER 18, 2024

Series 1 Facility Address Bldg Sqft # Floors Program Budget

Programming Start

Completion Summary of Improvements

Sibley Elementary 943 Sibley Street NW 61,451 3 $2,600,000 Winter 2024 Summer 2024 Elevators, Finishes, HVAC Controls, & Lighting Inn. Central – Performing Arts 421 Fountain Street NE $2,500,000 Winter 2024 Summer 2024 Booth Relocation, Lighting, Rigging, Seating, & Technology Coit Creative Arts 617 Coit Avenue NE 63,316 2 $6,142,000 Winter 2024 Summer 2024 & 2025 Finishes, HVAC System Upgrade, Parking Lot, & Playground Sigsbee (New SE Career Path) 1250 Sigsbee Ave SE 39,423 1 $7,000,000 Spring 2024 Summer 2025 Finishes, HVAC System, Masonry Repair, Parking Lot, & Windows

Ottawa Hills High 2055 Rosewood Ave SE 313,913 3 $7,183,000 Spring 2024 Summer 2025 Separate MS/HS Entrance, Offices, etc.

Houseman Field 901 Fountain St NE $5,107,000 Spring 2024 Summer 2025 Track & Field, Locker Room Finishes, Scoreboard, & Site Lighting Ottawa Hills - Performing Arts 2055 Rosewood Ave SE $4,538,000 Summer 2024 Summer 2025 Curtains, Flooring, Lighting, Sound System, & Stages Cesar Chavez Elementary 703 Shamrock Street SW 57,252 3 $1,034,000 Summer 2024 Summer 2025 Envelope Repairs, HVAC Controls, Flooring, & Playground Updates

Dickinson 448 Dickinson Street SE 52,024 3 $1,551,000 Fall 2024 Summer 2025 Flooring, HVAC Controls, Lighting, & Secured Entrance Ken-O-Sha 1353 Van Auken Street SE 82,726 1 $21,099,000 Spring 2024 Summer 2026 Fully Renovate Building (Costs Exclude Aquatic Center) Union – Pool 1800 Tremont Blvd NW $2,501,000 Summer 2024 Fall 2025 Filtration System, Lockers, & Showers Riverside Middle School 265 Eleanor Street NE 93,203 2 $21,139,000 Spring 2024 Summer 2026 Building Addition & Fully Renovate Interior Alger Middle School 921 Alger Street SE 80,304 3 $6,424,000 Fall 2024 Summer 2026 Add Bathrooms in Classrooms (ECC), Finishes, & New Playground

Series 2 Facility Program Budget Programming

Start Completion Summary of Improvement

Kent Hills 1445 Emerald Avenue NE 56,038 1 $3,490,000 Summer 2026 Summer 2027 Bathroom Renovations, Finishes, & Lighting City High/Mid - Performing Arts 1720 Plainfield Avenue NE $3,939,000 Summer 2026 Summer 2027 Scope Being Developed Aberdeen (New Elementary) 928 Abeerdeen Street NE 45,483 2 $38,757,000 Spring 2024 Summer 2027 New School for 450 Scholars & Demo Existing Building Ottawa Hills – Pool 2055 Rosewood Ave SE $3,102,000 Fall 2026 Fall 2027 Deepen Pool, Electrical, Filtration System, Lighting, & Locker Rooms Harrison Park 1440 Davis Avenue NW 172,739 2 $11,641,000 Spring 2026 Summer 2028 Cafeteria Improvements, Finishes, HVAC System, Lighting, & Playground

Union High 1800 Tremont Blvd NW 264,800 3 $6,983,000 Fall 2026 Summer 2028 Separate MS/HS Entrance, Offices, etc.

Campus Elementary 710 Benjamin Ave SE 48,767 3 $10,982,000 Spring 2028 Spring 2030 Doors, Finishes, Lighting, Roofing, Windows, Partial Reconfiguration of

Interiors, & Separate ECC & Elementary

Series 3 Facility Program Budget Programming

Start Completion Summary of Improvement

City High/Mid – Pool 1720 Plainfield Avenue NE $1,833,000 Winter 2029 Fall 2029 Scope Being Developed Southwest Elementary 801 Oakland Ave NW 88,838 3 $18,323,000 Winter 2028 Summer 2030 Full Building Renovation Mulick Park 1761 Rosewood Avenue SE 45,703 2 $23,968,000 Summer 2028 Summer 2030 Building Addition, HVAC, Finishes, & Renovate to Be More Accessible

Burton - Performing Arts 2133 Buchanan Ave SE $475,000 Summer 2029 Summer 2030 Scope Being Developed Congress Elementary 940 Baldwin Street SE 33,664 3 $6,341,000 Fall 2029 Summer 2030 Add Elevator, Exterior Doors, Finishes, Lighting, Parking Lot, & Windows Union - Performing Arts 1800 Tremont Blvd NW $3,293,000 Summer 2029 Summer 2030 Scope Being Developed Innovation Central 421 Fountain Street NE 203,751 5 $7,490,000 Winter 2031 Summer 2031 Masonry Repair & Windows Ridgemoor Park 2555 Iverness Road SE 32,702 1 $10,965,000 Summer 2029 Summer 2031 Roof, Two Classroom Addition (K-8) w/ Gym & Cafeteria Burton Elementary 2133 Buchanan Ave SE 181,527 3 $658,000 Spring 2031 Summer 2031 Finishes & HVAC Controls Gerald R. Ford Academic Center 851 Madison Ave SE 76,994 3 $1,316,000 Spring 2031 Summer 2031 Lighting

NOTE: ADDITIONAL LOCATIONS MAY BE IDENTIFIED IN THE FUTURE

ATTACHMENT A. PROJECT LIST