Attachment 5 - Submittal Register 3-10-20.XLS
XLS spreadsheet 172 KB Posted
- Attached to
- B238 Renovations Federal contract opportunity
- Solicitation number
- N4008520B2533
About this file
This document is a submittal register for the B-238 1st and 2nd Floor Renovations project. The project involves repairing and renovating spaces on the first and second floors of Building B-238, including demolishing and constructing a new break room, renovating a training room, cafeteria, locker room, and various work spaces. The submittal register lists 284 required submittals from the contractor organized by specification section. Submittals include shop drawings, product data, samples, test reports, manufacturer instructions, operation and maintenance manuals, and closeout documents covering areas such as preconstruction plans, demolition, hazardous materials abatement, structural, wood, architectural, plumbing, HVAC, electrical, fire protection, security, and communications systems. The period of performance for the project is 280 days from award. The solicitation was issued by the Naval Facilities Engineering Command for the Department of the Navy.
View the file
Other files for this federal contract opportunity
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal Register
| TITLE: | B-238 - 1st & 2nd Floor Renovations | SUBMITTAL REGISTER | ||||||||||||||||||
| JOB NAME: | B-238 Interior Renovations | |||||||||||||||||||
| LOCATION: | PNSY | |||||||||||||||||||
| CONTRACT NO: | TBD | |||||||||||||||||||
| CONTRACTOR: | ||||||||||||||||||||
| CONTRACTOR SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | ||||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |||
| Line | Activity # | Trans-mittal # | Specification Section | SD # | Submittal Description | Item Submitted | Paragraph # | Classification: GOVT or A/E Revwr | Submit | Approval Needed By | Material Needed By | Action Code | Date Of Action | Date FWD to APPR / Auth Date RCD From CONTR | Date FWD To Other Revwr | Date RCD From Other Revwr | Action Code | Date Of Action | Mailed To CONTR/ Date RCD From APPR Authority | Remarks |
| 1 | 01 14 00.00 22 | 01 | Preconstruction Submittals | List of Contact Personnel | 1.4.1 | G | ||||||||||||||
| 2 | 01 20 00.00 22 | 01 | Preconstruction Submittals | Schedule of Prices | 1.3 | G | ||||||||||||||
| 3 | 01 30 00.00 22 | 01 | Preconstruction Submittals | NAVFAC Red Zone Checklist | 1.6 | G | ||||||||||||||
| 4 | 01 30 00.00 22 | 01 | Preconstruction Submittals | NAVFAC PWD ME Follow-on Services List | 1.6 | G | ||||||||||||||
| 5 | 01 31 23.13 22 | 01 | Preconstruction Submittals | List of Contractor's Personnel | 1.4.2 | G | ||||||||||||||
| 6 | 01 32 16.00 20 | 01 | Preconstruction Submittals | Baseline Construction Schedule | 1.2 | G | ||||||||||||||
| 7 | 01 32 16.00 20 | 01 | Preconstruction Submittals | Baseline Design Schedule | 0 | G | ||||||||||||||
| 8 | 01 32 16.00 20 | 07 | Certificates | Monthly Updates | 1.4 | |||||||||||||||
| 9 | 01 33 00 | 01 | Preconstruction Submittals | Submittal Register | 1.7 | G | ||||||||||||||
| 10 | 01 35 26.00 22 | 01 | Preconstruction Submittals | Accident Prevention Plan (APP) | 1.7 | G | ||||||||||||||
| 11 | 01 35 26.00 22 | 06 | Test Reports | Monthly Exposure Reports | 1.4 | |||||||||||||||
| 12 | 01 35 26.00 22 | 06 | Test Reports | Notifications and Reports | 1.12 | |||||||||||||||
| 13 | 01 35 26.00 22 | 06 | Test Reports | Accident Reports | 1.12.2 | G | ||||||||||||||
| 14 | 01 35 26.00 22 | 06 | Test Reports | LHE Inspection Reports | 1.12.3 | |||||||||||||||
| 15 | 01 35 26.00 22 | 07 | Certificates | Crane Operators/Riggers | 1.6.1.5 | |||||||||||||||
| 16 | 01 35 26.00 22 | 07 | Certificates | Standard Lift Plan | 1.7.2.2 | G | ||||||||||||||
| 17 | 01 35 26.00 22 | 07 | Certificates | Critical Lift Plan | 1.7.2.3 | G | ||||||||||||||
| 18 | 01 35 26.00 22 | 07 | Certificates | Naval Architecture Analysis | 1.7.2.3 | G | ||||||||||||||
| 19 | 01 35 26.00 22 | 07 | Certificates | Activity Hazard Analysis (AHA) | 1.8 | |||||||||||||||
| 20 | 01 35 26.00 22 | 07 | Certificates | Confined Space Entry Permit | 1.9.1 | |||||||||||||||
| 21 | 01 35 26.00 22 | 07 | Certificates | Hot Work Permit | 1.9.1 | |||||||||||||||
| 22 | 01 35 26.00 22 | 07 | Certificates | Certificate of Compliance | 1.12.4 | |||||||||||||||
| 23 | 01 35 26.00 22 | 07 | Certificates | Barge Mounted Mobile Cranes | 1.7.2.3 | |||||||||||||||
| 24 | 01 35 26.00 22 | 07 | Certificates | License Certificates | 1.14 | |||||||||||||||
| 25 | 01 35 26.00 22 | 07 | Certificates | Radiography Operation Planning Work Sheet | 1.14.1 | G | ||||||||||||||
| 26 | 01 45 00.10 22 | 01 | Preconstruction Submittals | QC Plan | 1.6 | G | ||||||||||||||
| 27 | 01 50 00.00 22 | 01 | Preconstruction Submittals | Construction site plan | 1.4 | G | ||||||||||||||
| 28 | 01 50 00.00 22 | 01 | Preconstruction Submittals | Traffic control plan | 3.2.1 | G | ||||||||||||||
| 29 | 01 50 00.00 22 | 06 | Test Reports | Backflow Preventer Tests | 2.2.5 | G | ||||||||||||||
| 30 | 01 50 00.00 22 | 07 | Certificates | Backflow Tester | 1.5.1 | G | ||||||||||||||
| 31 | 01 50 00.00 22 | 07 | Certificates | Backflow Preventers | 1.5 | G | ||||||||||||||
| 32 | 01 57 19.00 22 | 01 | Preconstruction Submittals | Preconstruction Survey | 1.5.1 | G | ||||||||||||||
| 33 | 01 57 19.00 22 | 01 | Preconstruction Submittals | Solid Waste Management Plan | 3.4 | G | ||||||||||||||
| 34 | 01 57 19.00 22 | 01 | Preconstruction Submittals | Regulatory Notifications | 1.5.2 | G | ||||||||||||||
| 35 | 01 57 19.00 22 | 01 | Preconstruction Submittals | Environmental Management Plan (EMP) | 3.1 | G | ||||||||||||||
| 36 | 01 57 19.00 22 | 01 | Preconstruction Submittals | Dirt and Dust Control Plan | 3.14.1 | G | ||||||||||||||
| 37 | 01 57 19.00 22 | 01 | Preconstruction Submittals | Contractor Hazardous Material Inventory Log | 3.6 | G | ||||||||||||||
| 38 | 01 57 19.00 22 | 01 | Preconstruction Submittals | Storm Water Management/Erosion and Sedimentation Control Plan | 3.2.1 | |||||||||||||||
| 39 | 01 74 19.00 22 | 01 | Preconstruction Submittals | Waste Management Plan | 1.3 | G | ||||||||||||||
| 40 | 01 74 19.00 22 | 11 | Closeout Submittals | Records | 1.4 | G | ||||||||||||||
| 41 | 01 78 00.00 22 | 03 | Product Data | As-Built Record of Equipment and Materials | 1.3.2 | G | ||||||||||||||
| 42 | 01 78 00.00 22 | 03 | Product Data | Warranty Management Plan | 1.7.1 | G | ||||||||||||||
| 43 | 01 78 00.00 22 | 03 | Product Data | Warranty Tags | 1.7.4 | G | ||||||||||||||
| 44 | 01 78 00.00 22 | 03 | Product Data | Final Cleaning | 0 | G | ||||||||||||||
| 45 | 01 78 00.00 22 | 03 | Product Data | Spare Parts Data | 1.4 | G | ||||||||||||||
| 46 | 01 78 00.00 22 | 08 | Manufacturer’s Instructions | Preventative Maintenance | 1.5 | G | ||||||||||||||
| 47 | 01 78 00.00 22 | 08 | Manufacturer’s Instructions | Condition Monitoring (Predictive Testing) | 1.5 | G | ||||||||||||||
| 48 | 01 78 00.00 22 | 08 | Manufacturer’s Instructions | Inspection | 1.5 | G | ||||||||||||||
| 49 | 01 78 00.00 22 | 08 | Manufacturer’s Instructions | Instructions | 1.7.1 | G | ||||||||||||||
| 50 | 01 78 00.00 22 | 10 | Operation and Maintenance Data | Operation and Maintenance Manuals | 1.9 | G | ||||||||||||||
| 51 | 01 78 00.00 22 | 11 | Closeout Submittals | Record Drawings | 1.3.1 | G | ||||||||||||||
| 52 | 01 78 00.00 22 | 11 | Closeout Submittals | Certification of EPA Designated Items | 1.6 | G | ||||||||||||||
| 53 | 01 78 00.00 22 | 11 | Closeout Submittals | Certification of EPA Designated Items | 1.6 | G | ||||||||||||||
| 54 | 01 78 00.00 22 | 11 | Closeout Submittals | Red Zone Documents | 1.3.6 | G | ||||||||||||||
| 55 | 01 78 23 | 10 | Operation and Maintenance Data | O&M Database | 0 | G | ||||||||||||||
| 56 | 01 78 23 | 10 | Operation and Maintenance Data | Training Plan | 3.1.1 | G | ||||||||||||||
| 57 | 01 78 23 | 10 | Operation and Maintenance Data | Training Outline | 3.1.3 | G | ||||||||||||||
| 58 | 01 78 23 | 10 | Operation and Maintenance Data | Training Content | 3.1.2 | G | ||||||||||||||
| 59 | 01 78 23 | 11 | Closeout Submittals | Training Video Recording | 3.1.4 | G | ||||||||||||||
| 60 | 01 78 23 | 11 | Closeout Submittals | Validation of Training Completion | 3.1.6 | G | ||||||||||||||
| 61 | 01 78 24.00 22 | 11 | Closeout Submittals | eOMSI, Progress Submittal | 1.4.1 | G | ||||||||||||||
| 62 | 01 78 24.00 22 | 11 | Closeout Submittals | eOMSI, Prefinal Submittal | 1.4.2 | G | ||||||||||||||
| 63 | 01 78 24.00 22 | 11 | Closeout Submittals | eOMSI, Final Submittal | 1.4.3 | G | ||||||||||||||
| 64 | 01 91 00.15 | 01 | Preconstruction Submittals | Commissioning Firm | 1.7 | G | ||||||||||||||
| 65 | 01 91 00.15 | 01 | Preconstruction Submittals | Lead Commissioning Specialist | 1.7.1 | G | ||||||||||||||
| 66 | 01 91 00.15 | 01 | Preconstruction Submittals | Technical Commissioning Specialists | 1.7.2 | G | ||||||||||||||
| 67 | 01 91 00.15 | 06 | Test Reports | Interim Construction Phase Commissioning Plan | 3.1.2.1 | G | ||||||||||||||
| 68 | 01 91 00.15 | 06 | Test Reports | Final Construction Phase Commissioning Plan | 3.1.2.2 | G | ||||||||||||||
| 69 | 01 91 00.15 | 06 | Test Reports | Pre-Functional Checklists | 3.1.4.2 | G | ||||||||||||||
| 70 | 01 91 00.15 | 06 | Test Reports | Issues Log | 1.8 | |||||||||||||||
| 71 | 01 91 00.15 | 06 | Test Reports | Commissioning Report | 3.2 | G | ||||||||||||||
| 72 | 01 91 00.15 | 07 | Certificates | Certificate of Readiness | 1.9 | G | ||||||||||||||
| 73 | 01 91 00.15 | 10 | Operation and Maintenance Data | Training Plan | 3.1.5 | G | ||||||||||||||
| 74 | 01 91 00.15 | 10 | Operation and Maintenance Data | Training Attendance Rosters | 3.1.5 | G | ||||||||||||||
| 75 | 01 91 00.15 | 10 | Operation and Maintenance Data | Systems Manual | 3.1.6 | G | ||||||||||||||
| 76 | 01 91 00.15 | 11 | Closeout Submittals | Final Commissioning Report | 3.2 | |||||||||||||||
| 77 | 02 41 00 | 01 | Preconstruction Submittals | Demolition Plan | 1.2.2 | G | ||||||||||||||
| 78 | 02 41 00 | 01 | Preconstruction Submittals | Existing Conditions | 1.9 | |||||||||||||||
| 79 | 02 41 00 | 07 | Certificates | Notification | 1.6 | G | ||||||||||||||
| 80 | 02 41 00 | 11 | Closeout Submittals | Receipts | 3.2.3 | |||||||||||||||
| 81 | 02 83 00 | 01 | Preconstruction Submittals | Competent Person | 1.5.1.1 | G | ||||||||||||||
| 82 | 02 83 00 | 01 | Preconstruction Submittals | Training Certification | 1.5.1.2 | G | ||||||||||||||
| 83 | 02 83 00 | 01 | Preconstruction Submittals | Occupational and Environmental Assessment Data Report | 1.5.2.3 | G | ||||||||||||||
| 84 | 02 83 00 | 01 | Preconstruction Submittals | Medical Examinations | 1.5.2.4 | G | ||||||||||||||
| 85 | 02 83 00 | 01 | Preconstruction Submittals | Lead, Cadmium, Chromium Waste Management Plan | 1.5.2.8 | G | ||||||||||||||
| 86 | 02 83 00 | 01 | Preconstruction Submittals | Licenses, Permits and Notifications | 1.5.4 | G | ||||||||||||||
| 87 | 02 83 00 | 01 | Preconstruction Submittals | Occupant Protection Plan | 1.5.5 | G | ||||||||||||||
| 88 | 02 83 00 | 01 | Preconstruction Submittals | Lead, Cadmium, Chromium Compliance Plan | 1.5.2.2 | G | ||||||||||||||
| 89 | 02 83 00 | 01 | Preconstruction Submittals | Written Evidence of TSD Approval | 3.5.2.1 | G | ||||||||||||||
| 90 | 02 83 00 | 03 | Product Data | Respirators | 1.6.1 | G | ||||||||||||||
| 91 | 02 83 00 | 03 | Product Data | Vacuum Filters | 1.6.4 | G | ||||||||||||||
| 92 | 02 83 00 | 03 | Product Data | Negative Air Pressure System | 1.6.7 | G | ||||||||||||||
| 93 | 02 83 00 | 03 | Product Data | Materials and Equipment | 2.1 | G | ||||||||||||||
| 94 | 02 83 00 | 03 | Product Data | Expendable Supplies | 2.1.1 | G | ||||||||||||||
| 95 | 02 83 00 | 06 | Test Reports | Sampling and Analysis | 1.3.3 | G | ||||||||||||||
| 96 | 02 83 00 | 06 | Test Reports | Occupational and Environmental Assessment Data Report | 1.5.2.3 | G | ||||||||||||||
| 97 | 02 83 00 | 06 | Test Reports | Sampling Results | 1.5.2.3 | G | ||||||||||||||
| 98 | 02 83 00 | 06 | Test Reports | Pressure Differential Recordings For Local Exhaust System | 1.5.3 | G | ||||||||||||||
| 99 | 02 83 00 | 07 | Certificates | Testing Laboratory | 1.5.1.3 | G | ||||||||||||||
| 100 | 02 83 00 | 07 | Certificates | Third Party Consultant Qualifications | 1.5.1.4 | G | ||||||||||||||
| 101 | 02 83 00 | 07 | Certificates | Occupant Notification | 0 | G | ||||||||||||||
| 102 | 02 83 00 | 07 | Certificates | Notification of the Commencement of LBP Hazard Abatement | 0 | G | ||||||||||||||
| 103 | 02 83 00 | 07 | Certificates | Clearance Certification | 3.5.1.1 | G | ||||||||||||||
| 104 | 02 83 00 | 11 | Closeout Submittals | Hazardous Waste Manifest | 3.5.2.1 | G | ||||||||||||||
| 105 | 02 83 00 | 11 | Closeout Submittals | Turn-In Documents or Weight Tickets | 3.5.2.1 | G | ||||||||||||||
| 106 | 06 10 00 | 02 | Shop Drawings | Modifications of Structural Members | 1.8.2 | G | ||||||||||||||
| 107 | 06 10 00 | 02 | Shop Drawings | Nailing Strips | 2.1.1 | |||||||||||||||
| 108 | 06 10 00 | 03 | Product Data | Fiberboard Wall Sheathing | 0 | |||||||||||||||
| 109 | 06 10 00 | 03 | Product Data | Structural-use and OSB Panels | 1.4.3 | |||||||||||||||
| 110 | 06 10 00 | 03 | Product Data | Oriented Strand Board | 0 | |||||||||||||||
| 111 | 06 10 00 | 03 | Product Data | Adhesives | 2.3.4 | |||||||||||||||
| 112 | 06 10 00 | 05 | Design Data | Modifications of Structural Members | 1.8.2 | G | ||||||||||||||
| 113 | 06 10 00 | 06 | Test Reports | Preservative-treated | 1.4.4 | |||||||||||||||
| 114 | 06 20 00 | 02 | Shop Drawings | Detail Drawings Indicating All Wood Assemblies | 1.3 | G | ||||||||||||||
| 115 | 06 20 00 | 03 | Product Data | Wood Products | 2.1 | G | ||||||||||||||
| 116 | 06 20 00 | 03 | Product Data | Engineered | 0 | G | ||||||||||||||
| 117 | 06 20 00 | 03 | Product Data | Treated Wood Products | 1.4 | G | ||||||||||||||
| 118 | 06 20 00 | 03 | Product Data | Hardware and Accessories | 2.6 | G | ||||||||||||||
| 119 | 06 20 00 | 03 | Product Data | Recycled Content for MDF/Particleboard | 0 | S | ||||||||||||||
| 120 | 06 20 00 | 04 | Samples | Samples | 1.5 | G | ||||||||||||||
| 121 | 06 20 00 | 07 | Certificates | Certificates of Grade | 1.7.1.1 | G | ||||||||||||||
| 122 | 06 41 16.00 10 | 02 | Shop Drawings | Shop Drawings | 2.8 | |||||||||||||||
| 123 | 06 41 16.00 10 | 02 | Shop Drawings | Installation | 3.1 | |||||||||||||||
| 124 | 06 41 16.00 10 | 03 | Product Data | Wood Materials | 2.1 | |||||||||||||||
| 125 | 06 41 16.00 10 | 03 | Product Data | Finish Schedule | 2.8.1.3 | |||||||||||||||
| 126 | 06 41 16.00 10 | 03 | Product Data | Certification | 0 | |||||||||||||||
| 127 | 06 41 16.00 10 | 04 | Samples | Plastic Laminates | 2.3 | |||||||||||||||
| 128 | 06 41 16.00 10 | 04 | Samples | Cabinet Hardware | 0 | |||||||||||||||
| 129 | 06 41 16.00 10 | 07 | Certificates | Quality Assurance | 1.4 | |||||||||||||||
| 130 | 06 41 16.00 10 | 07 | Certificates | Laminate Clad Casework | 3.1 | |||||||||||||||
| 131 | 06 61 16 | 02 | Shop Drawings | Detail Drawings | 0 | G | ||||||||||||||
| 132 | 06 61 16 | 02 | Shop Drawings | Installation | 3.1 | G | ||||||||||||||
| 133 | 06 61 16 | 03 | Product Data | Solid Polymer Material | 2.1 | |||||||||||||||
| 134 | 06 61 16 | 03 | Product Data | Qualifications | 1.5.1 | |||||||||||||||
| 135 | 06 61 16 | 03 | Product Data | Fabrications | 2.3 | |||||||||||||||
| 136 | 06 61 16 | 03 | Product Data | Indoor air quality for solid surface seam and sealant products | 2.2.4 | |||||||||||||||
| 137 | 06 61 16 | 04 | Samples | Material | 2.1 | G | ||||||||||||||
| 138 | 06 61 16 | 04 | Samples | Counter and Vanity Tops | 2.3.4 | G | ||||||||||||||
| 139 | 06 61 16 | 06 | Test Reports | Solid Polymer Material | 2.1 | |||||||||||||||
| 140 | 06 61 16 | 07 | Certificates | Fabrications | 2.3 | |||||||||||||||
| 141 | 06 61 16 | 07 | Certificates | Qualifications | 1.5.1 | |||||||||||||||
| 142 | 06 61 16 | 07 | Certificates | Indoor Air Quality for solid surface fabrication products | 2.1 | |||||||||||||||
| 143 | 06 61 16 | 10 | Operation and Maintenance Data | Clean-up | 3.2 | |||||||||||||||
| 144 | 07 84 00 | 02 | Shop Drawings | Firestopping System | 2.1 | G | ||||||||||||||
| 145 | 07 84 00 | 03 | Product Data | Firestopping Materials | 2.2 | G | ||||||||||||||
| 146 | 07 84 00 | 06 | Test Reports | Inspection | 3.3 | G | ||||||||||||||
| 147 | 07 84 00 | 07 | Certificates | Inspector Qualifications | 1.5.2 | |||||||||||||||
| 148 | 07 84 00 | 07 | Certificates | Firestopping Materials | 2.2 | |||||||||||||||
| 149 | 07 84 00 | 07 | Certificates | Installer Qualifications | 1.5.1 | G | ||||||||||||||
| 150 | 07 92 00 | 03 | Product Data | Sealants | 2.1 | G | ||||||||||||||
| 151 | 07 92 00 | 03 | Product Data | Primers | 2.2 | G | ||||||||||||||
| 152 | 07 92 00 | 03 | Product Data | Bond Breakers | 2.3 | G | ||||||||||||||
| 153 | 07 92 00 | 03 | Product Data | Backstops | 2.4 | G | ||||||||||||||
| 154 | 07 92 00 | 03 | Product Data | Field Adhesion | 3.1 | G | ||||||||||||||
| 155 | 08 11 13 | 02 | Shop Drawings | Doors | 2.1 | G | ||||||||||||||
| 156 | 08 11 13 | 02 | Shop Drawings | Doors | 2.1 | G | ||||||||||||||
| 157 | 08 11 13 | 02 | Shop Drawings | Frames | 2.7 | G | ||||||||||||||
| 158 | 08 11 13 | 02 | Shop Drawings | Frames | 2.7 | G | ||||||||||||||
| 159 | 08 11 13 | 02 | Shop Drawings | Accessories | 2.5 | |||||||||||||||
| 160 | 08 11 13 | 03 | Product Data | Doors | 2.1 | G | ||||||||||||||
| 161 | 08 11 13 | 03 | Product Data | Frames | 2.7 | G | ||||||||||||||
| 162 | 08 11 13 | 03 | Product Data | Accessories | 2.5 | |||||||||||||||
| 163 | 08 71 00 | 02 | Shop Drawings | Manufacturer's Detail Drawings | 1.3 | G | ||||||||||||||
| 164 | 08 71 00 | 02 | Shop Drawings | Verification of Existing Conditions | 1.3 | G | ||||||||||||||
| 165 | 08 71 00 | 02 | Shop Drawings | Hardware Schedule | 1.5 | G | ||||||||||||||
| 166 | 08 71 00 | 02 | Shop Drawings | Keying System | 2.3.9 | G | ||||||||||||||
| 167 | 08 71 00 | 03 | Product Data | Hardware Items | 2.3 | G | ||||||||||||||
| 168 | 08 71 00 | 08 | Manufacturer’s Instructions | Installation | 3.1 | |||||||||||||||
| 169 | 08 71 00 | 10 | Operation and Maintenance Data | Hardware Schedule | 1.5 | G | ||||||||||||||
| 170 | 08 71 00 | 11 | Closeout Submittals | Key Bitting | 1.6.1 | |||||||||||||||
| 171 | 09 29 00 | 03 | Product Data | Cementitious Backer Units | 0 | |||||||||||||||
| 172 | 09 29 00 | 03 | Product Data | Accessories | 2.1.4 | |||||||||||||||
| 173 | 09 29 00 | 03 | Product Data | Gypsum Board | 2.1.1 | |||||||||||||||
| 174 | 09 29 00 | 07 | Certificates | Asbestos Free Materials | 2.1 | G | ||||||||||||||
| 175 | 09 29 00 | 07 | Certificates | Indoor Air Quality | 0 | |||||||||||||||
| 176 | 09 29 00 | 08 | Manufacturer’s Instructions | Safety Data Sheets | 2.1 | |||||||||||||||
| 177 | 09 29 00 | 10 | Operation and Maintenance Data | Manufacturer Maintenance Instructions | 2.1 | |||||||||||||||
| 178 | 09 51 00 | 02 | Shop Drawings | Approved Detail Drawings | 2.1 | G | ||||||||||||||
| 179 | 09 51 00 | 03 | Product Data | Acoustical Ceiling Systems | 0 | G | ||||||||||||||
| 180 | 09 51 00 | 04 | Samples | Acoustical Units | 2.2 | G | ||||||||||||||
| 181 | 09 51 00 | 04 | Samples | Acoustical Ceiling Tiles | 2.2.1.1 | G | ||||||||||||||
| 182 | 09 51 00 | 06 | Test Reports | Ceiling Attenuation Class and Test | 2.1.1 | G | ||||||||||||||
| 183 | 09 65 00 | 02 | Shop Drawings | Resilient Flooring and Accessories | 2.9 | G | ||||||||||||||
| 184 | 09 65 00 | 03 | Product Data | Resilient Flooring and Accessories | 2.9 | G | ||||||||||||||
| 185 | 09 65 00 | 03 | Product Data | Adhesives | 2.5 | |||||||||||||||
| 186 | 09 65 00 | 03 | Product Data | Vinyl Composition Tile | 0 | |||||||||||||||
| 187 | 09 65 00 | 03 | Product Data | Rubber Tile | 2.1 | |||||||||||||||
| 188 | 09 65 00 | 03 | Product Data | Wall Base | 2.3 | |||||||||||||||
| 189 | 09 65 00 | 03 | Product Data | Moulding | 2.4 | |||||||||||||||
| 190 | 09 65 00 | 04 | Samples | Resilient Flooring and Accessories | 2.9 | G | ||||||||||||||
| 191 | 09 65 00 | 06 | Test Reports | Moisture, Alkalinity and Bond Tests | 3.3 | G | ||||||||||||||
| 192 | 09 65 00 | 07 | Certificates | Indoor Air Quality for Adhesives | 2.5 | |||||||||||||||
| 193 | 09 65 00 | 08 | Manufacturer’s Instructions | Surface Preparation | 3.2 | G | ||||||||||||||
| 194 | 09 65 00 | 08 | Manufacturer’s Instructions | Installation | 3.1 | G | ||||||||||||||
| 195 | 09 65 00 | 10 | Operation and Maintenance Data | Resilient Flooring and Accessories | 2.9 | G | ||||||||||||||
| 196 | 09 68 00 | 03 | Product Data | Carpet | 2.1 | G | ||||||||||||||
| 197 | 09 68 00 | 03 | Product Data | Moldings | 2.4 | G | ||||||||||||||
| 198 | 09 68 00 | 04 | Samples | Carpet | 2.1 | G | ||||||||||||||
| 199 | 09 68 00 | 04 | Samples | Moldings | 2.4 | |||||||||||||||
| 200 | 09 68 00 | 06 | Test Reports | Moisture and Alkalinity Tests | 3.2 | G | ||||||||||||||
| 201 | 09 68 00 | 08 | Manufacturer’s Instructions | Surface Preparation | 3.1 | |||||||||||||||
| 202 | 09 68 00 | 10 | Operation and Maintenance Data | Cleaning and Protection | 3.5 | |||||||||||||||
| 203 | 09 68 00 | 11 | Closeout Submittals | Warranty | 1.6 | |||||||||||||||
| 204 | 09 90 00 | 02 | Shop Drawings | Piping Identification | 0 | |||||||||||||||
| 205 | 09 90 00 | 03 | Product Data | Sealant | 0 | |||||||||||||||
| 206 | 09 90 00 | 04 | Samples | Color | 1.10 | G | ||||||||||||||
| 207 | 09 90 00 | 07 | Certificates | Applicator's Qualifications | 1.3 | |||||||||||||||
| 208 | 09 90 00 | 07 | Certificates | Qualification Testing | 1.4.1.2 | G | ||||||||||||||
| 209 | 09 90 00 | 07 | Certificates | Indoor Air Quality for Paints and Primers | 2.1 | |||||||||||||||
| 210 | 09 90 00 | 08 | Manufacturer’s Instructions | Application Instructions | 0 | |||||||||||||||
| 211 | 09 90 00 | 08 | Manufacturer’s Instructions | Mixing | 3.6.2 | |||||||||||||||
| 212 | 09 90 00 | 08 | Manufacturer’s Instructions | Manufacturer's Safety Data Sheets | 1.7.2 | |||||||||||||||
| 213 | 10 22 19 | 02 | Shop Drawings | Installation | 3.3 | |||||||||||||||
| 214 | 10 22 19 | 03 | Product Data | Warranty | 1.7 | G | ||||||||||||||
| 215 | 10 22 19 | 03 | Product Data | Partition System | 2.2 | G | ||||||||||||||
| 216 | 10 22 19 | 03 | Product Data | Partition System | 2.2 | G | ||||||||||||||
| 217 | S.O.W. 1.8..4 | 02 | Shop Drawings | Steel Shop Drawings | 1.8..4 | G | ||||||||||||||
| 218 | S.O.W. 1.8..5 | 03 | Product Data | Epoxy Anchor Material Data | 1.8..5 | G | ||||||||||||||
| 219 | S.O.W. 1.8..6 | 03 | Product Data | Steel Coating System | 1.8..6 | G | ||||||||||||||
| 220 | S.O.W. 1.8..8 | 03 | Product Data | Non-Shrink Grout | 1.8..8 | G | ||||||||||||||
| 221 | 10 22 19 | 04 | Samples | Partition System Samples | 2.4 | G | ||||||||||||||
| 222 | 10 22 19 | 04 | Samples | Mock-Up | 2.2 | G | ||||||||||||||
| 223 | 10 22 19 | 07 | Certificates | Burning Characteristics | 2.1.1 | |||||||||||||||
| 224 | 10 22 19 | 07 | Certificates | Acoustical Performance | 2.1.2 | |||||||||||||||
| 225 | 10 22 19 | 07 | Certificates | Structural Performance | 2.1.3 | |||||||||||||||
| 226 | S.O.W. 1.8..7 | 07 | Certificates | Welder Certifications | 1.8..7 | G | ||||||||||||||
| 227 | 10 22 19 | 10 | Operation and Maintenance Data | Assembly Manuals | 2.3.1 | G | ||||||||||||||
| 228 | 10 22 19 | 10 | Operation and Maintenance Data | Maintenance Manuals | 3.5 | G | ||||||||||||||
| 229 | 12 59 00 | 02 | Shop Drawings | Detail Drawings | 1.4.4 | G | ||||||||||||||
| 230 | 12 59 00 | 03 | Product Data | Warranty | 1.6 | G | ||||||||||||||
| 231 | 12 59 00 | 03 | Product Data | Workstations | 2.3.1 | |||||||||||||||
| 232 | 12 59 00 | 03 | Product Data | Power and Communications | 2.12 | |||||||||||||||
| 233 | 12 59 00 | 03 | Product Data | Communications | 2.12.8 | |||||||||||||||
| 234 | 12 59 00 | 04 | Samples | Workstations | 2.3.1 | G | ||||||||||||||
| 235 | 12 59 00 | 04 | Samples | Mock-up | 2.3.3 | G | ||||||||||||||
| 236 | 12 59 00 | 04 | Samples | Samples | 2.3.2 | |||||||||||||||
| 237 | 12 59 00 | 06 | Test Reports | Selected Components | 2.3.5.1 | G | ||||||||||||||
| 238 | 12 59 00 | 06 | Test Reports | Panel Acoustics | 2.3.5.2 | G | ||||||||||||||
| 239 | 12 59 00 | 06 | Test Reports | Fire Safety | 1.4.2 | G | ||||||||||||||
| 240 | 12 59 00 | 06 | Test Reports | Electrical System | 1.4.3 | G | ||||||||||||||
| 241 | 12 59 00 | 07 | Certificates | Workstations | 2.3.1 | |||||||||||||||
| 242 | 12 59 00 | 10 | Operation and Maintenance Data | Assembly Manuals | 2.4.1 | G | ||||||||||||||
| 243 | 12 59 00 | 10 | Operation and Maintenance Data | Maintenance Manuals | 3.2 | G | ||||||||||||||
| 244 | 12 59 00 | 10 | Operation and Maintenance Data | Cleaning | 3.2 | G | ||||||||||||||
| 245 | 12 59 00 | 10 | Operation and Maintenance Data | Electrical System | 1.4.3 | G | ||||||||||||||
| 246 | 12 59 00 | 10 | Operation and Maintenance Data | Maintenance Agreements | 1.7 | |||||||||||||||
| 247 | 12 59 00 | 10 | Operation and Maintenance Data | Installation | 3.1 | G | ||||||||||||||
| 248 | 21 13 13.00 20 | 02 | Shop Drawings | Shop Drawings | 1.5.1 | G | ||||||||||||||
| 249 | 21 13 13.00 20 | 03 | Product Data | Pipe | 2.1.1 | G | ||||||||||||||
| 250 | 21 13 13.00 20 | 03 | Product Data | Fittings | 2.1.1 | G | ||||||||||||||
| 251 | 21 13 13.00 20 | 03 | Product Data | Sprinklers | 2.1.4 | G | ||||||||||||||
| 252 | 21 13 13.00 20 | 03 | Product Data | Pipe hangers and supports | 2.1.5 | G | ||||||||||||||
| 253 | 21 13 13.00 20 | 03 | Product Data | Mechanical couplings | 2.1.1 | G | ||||||||||||||
| 254 | 21 13 13.00 20 | 06 | Test Reports | request to schedule Preliminary Tests | 3.4 | G | ||||||||||||||
| 255 | 21 13 13.00 20 | 06 | Test Reports | Preliminary Test Report | 3.4 | G | ||||||||||||||
| 256 | 21 13 13.00 20 | 06 | Test Reports | request to schedule Final Acceptance Test | 3.4.1.1 | G | ||||||||||||||
| 257 | 21 13 13.00 20 | 06 | Test Reports | Final Acceptance Test Report | 3.4.1.1 | G | ||||||||||||||
| 258 | 21 13 13.00 20 | 07 | Certificates | Sprinkler System Installer | 1.5.1 | G | ||||||||||||||
| 259 | 21 13 13.00 20 | 10 | Operation and Maintenance Data | Operating and Maintenance Instructions | 0 | |||||||||||||||
| 260 | 21 13 13.00 20 | 11 | Closeout Submittals | As-built drawings | 3.4.1.1 | |||||||||||||||
| 261 | 21 13 13.00 20 | 11 | Closeout Submittals | On-site training | 0 | |||||||||||||||
| 262 | 22 00 00 | 03 | Product Data | Fixtures | 2.4 | |||||||||||||||
| 263 | 22 00 00 | 03 | Product Data | Drinking-Water Coolers | 2.4.2 | G | ||||||||||||||
| 264 | 22 00 00 | 03 | Product Data | Welding | 1.5.1 | |||||||||||||||
| 265 | 22 00 00 | 03 | Product Data | Kitchen Sinks | 2.4.1 | G | ||||||||||||||
| 266 | 22 00 00 | 06 | Test Reports | Tests, Flushing and Disinfection | 3.4 | |||||||||||||||
| 267 | 22 00 00 | 07 | Certificates | Materials and Equipment | 1.3 | |||||||||||||||
| 268 | 22 00 00 | 07 | Certificates | Bolts | 2.1.1 | |||||||||||||||
| 269 | 22 15 14.00 40 | 03 | Product Data | Aboveground Piping Materials | 2.1.1 | G | ||||||||||||||
| 270 | 22 15 14.00 40 | 03 | Product Data | Supporting Elements | 2.2.2 | G | ||||||||||||||
| 271 | 22 15 14.00 40 | 03 | Product Data | Miscellaneous Materials | 2.2.1 | G | ||||||||||||||
| 272 | 22 15 14.00 40 | 06 | Test Reports | Piping System Test Report | 3.2.1.4 | |||||||||||||||
| 273 | 22 15 14.00 40 | 07 | Certificates | Aboveground Piping Materials | 2.1.1 | |||||||||||||||
| 274 | 22 15 14.00 40 | 07 | Certificates | Supporting Elements | 2.2.2 | |||||||||||||||
| 275 | 23 00 00 | 02 | Shop Drawings | Detail Drawings | 1.4.4 | G | ||||||||||||||
| 276 | 23 00 00 | 03 | Product Data | Manual Balancing Dampers | 2.9.4 | G | ||||||||||||||
| 277 | 23 00 00 | 03 | Product Data | Centrifugal Fans | 2.10.1.1 | |||||||||||||||
| 278 | 23 00 00 | 03 | Product Data | In-Line Centrifugal Fans | 2.10.1.2 | |||||||||||||||
| 279 | 23 00 00 | 03 | Product Data | Air Handling Units | 2.11 | G | ||||||||||||||
| 280 | 23 00 00 | 03 | Product Data | Room Fan-Coil Units | 2.12.1 | G | ||||||||||||||
| 281 | 23 00 00 | 03 | Product Data | Energy Recovery Devices | 2.13 | G | ||||||||||||||
| 282 | 23 00 00 | 03 | Product Data | Diffusers | 2.9.9.1 | G | ||||||||||||||
| 283 | 23 00 00 | 03 | Product Data | Registers And Grilles | 2.9.9.2 | G | ||||||||||||||
| 284 | 23 00 00 | 03 | Product Data | Metallic Flexible Duct | 2.9.1.1 | G | ||||||||||||||
| 285 | 23 00 00 | 03 | Product Data | Ductwork | 0 | G | ||||||||||||||
| 286 | 23 00 00 | 06 | Test Reports | Performance Tests | 3.12 | G | ||||||||||||||
| 287 | 23 00 00 | 06 | Test Reports | Damper Acceptance Test | 3.10 | G | ||||||||||||||
| 288 | 23 00 00 | 07 | Certificates | Ozone Depleting Substances Technician Certification | 1.4.3 | |||||||||||||||
| 289 | 23 00 00 | 08 | Manufacturer’s Instructions | Manufacturer's Installation Instructions | 3.2 | |||||||||||||||
| 290 | 23 00 00 | 08 | Manufacturer’s Instructions | Operation and Maintenance Training | 3.14.2 | |||||||||||||||
| 291 | 23 00 00 | 10 | Operation and Maintenance Data | Centrifugal Fans | 2.10.1.1 | G | ||||||||||||||
| 292 | 23 00 00 | 10 | Operation and Maintenance Data | In-Line Centrifugal Fans | 2.10.1.2 | G | ||||||||||||||
| 293 | 23 00 00 | 10 | Operation and Maintenance Data | Air Handling Units | 2.11 | G | ||||||||||||||
| 294 | 23 00 00 | 10 | Operation and Maintenance Data | Room Fan-Coil Units | 2.12.1 | G | ||||||||||||||
| 295 | 23 00 00 | 10 | Operation and Maintenance Data | Energy Recovery Devices | 2.13 | G | ||||||||||||||
| 296 | 23 05 15 | 01 | Preconstruction Submittals | Material, Equipment, and Fixture Lists | 1.2 | G | ||||||||||||||
| 297 | 23 05 15 | 02 | Shop Drawings | Record Drawings | 1.2 | G | ||||||||||||||
| 298 | 23 05 15 | 02 | Shop Drawings | Coordination Drawings | 1.2 | G | ||||||||||||||
| 299 | 23 05 15 | 02 | Shop Drawings | Fabrication Drawings | 1.2 | G | ||||||||||||||
| 300 | 23 05 15 | 02 | Shop Drawings | Installation Drawings | 3.1 | |||||||||||||||
| 301 | 23 05 15 | 03 | Product Data | Pipe and Fittings | 2.1 | G | ||||||||||||||
| 302 | 23 05 15 | 03 | Product Data | Piping Specialties | 2.2 | G | ||||||||||||||
| 303 | 23 05 15 | 03 | Product Data | Valves | 2.3 | G | ||||||||||||||
| 304 | 23 05 15 | 03 | Product Data | Miscellaneous Materials | 2.4 | G | ||||||||||||||
| 305 | 23 05 15 | 03 | Product Data | Supporting Elements | 2.5 | G | ||||||||||||||
| 306 | 23 05 15 | 06 | Test Reports | Hydrostatic Tests | 3.1 | G | ||||||||||||||
| 307 | 23 05 15 | 06 | Test Reports | Valve-Operating Tests | 3.1 | G | ||||||||||||||
| 308 | 23 05 15 | 06 | Test Reports | System Operation Tests | 3.1 | G | ||||||||||||||
| 309 | 23 05 15 | 10 | Operation and Maintenance Data | Operation and Maintenance Manuals | 3.9 | G | ||||||||||||||
| 310 | 23 05 93 | 01 | Preconstruction Submittals | Records of Existing Conditions | 1.3.3 | G | ||||||||||||||
| 311 | 23 05 93 | 01 | Preconstruction Submittals | Independent TAB Agency and Personnel Qualifications | 1.5.1 | G | ||||||||||||||
| 312 | 23 05 93 | 01 | Preconstruction Submittals | TAB Design Review Report | 1.5.3.2 | G | ||||||||||||||
| 313 | 23 05 93 | 02 | Shop Drawings | TAB Schematic Drawings and Report Forms | 1.3.3 | G | ||||||||||||||
| 314 | 23 05 93 | 03 | Product Data | Equipment and Performance Data | 1.3 | G | ||||||||||||||
| 315 | 23 05 93 | 03 | Product Data | TAB Related HVAC Submittals | 1.5.1.3 | G | ||||||||||||||
| 316 | 23 05 93 | 06 | Test Reports | Completed Pre-Final DALT Report | 3.3.5 | G | ||||||||||||||
| 317 | 23 05 93 | 06 | Test Reports | Certified Final DALT Report | 3.3.8 | G | ||||||||||||||
| 318 | 23 05 93 | 06 | Test Reports | Prerequisite HVAC Work Checkout List | 1.5.3.3 | G | ||||||||||||||
| 319 | 23 05 93 | 06 | Test Reports | Prerequisite HVAC Work Checkout List | 1.5.3.3 | G | ||||||||||||||
| 320 | 23 05 93 | 06 | Test Reports | Prerequisite HVAC Work Checkout List | 1.5.3.3 | G | ||||||||||||||
| 321 | 23 05 93 | 06 | Test Reports | Proportional Balancing | 3.4.6.1 | G | ||||||||||||||
| 322 | 23 05 93 | 06 | Test Reports | Proportional Balancing | 3.7 | G | ||||||||||||||
| 323 | 23 05 93 | 06 | Test Reports | Season 1 | 3.4.6.2 | G | ||||||||||||||
| 324 | 23 05 93 | 06 | Test Reports | Season 1 | 3.7 | G | ||||||||||||||
| 325 | 23 05 93 | 06 | Test Reports | Season 2 | 3.4.6.2 | G | ||||||||||||||
| 326 | 23 05 93 | 06 | Test Reports | Season 2 | 3.7 | G | ||||||||||||||
| 327 | 23 05 93 | 07 | Certificates | Independent TAB Agency and Personnel Qualifications | 1.5.1 | G | ||||||||||||||
| 328 | 23 05 93 | 07 | Certificates | DALT and TAB Submittal and Work Schedule | 1.5.3.2 | G | ||||||||||||||
| 329 | 23 05 93 | 07 | Certificates | TAB Pre-Field Engineering Report | 1.5.3.3 | G | ||||||||||||||
| 330 | 23 05 93 | 07 | Certificates | Instrument Calibration Certificates | 1.5.5 | G | ||||||||||||||
| 331 | 23 05 93 | 07 | Certificates | DALT and TAB Procedures Summary | 3.7 | G | ||||||||||||||
| 332 | 23 05 93 | 07 | Certificates | Completed Pre-Final DALT Work Checklist | 3.7 | G | ||||||||||||||
| 333 | 23 05 93 | 07 | Certificates | Advance Notice of Pre-Final DALT Field Work | 3.3.2 | G | ||||||||||||||
| 334 | 23 05 93 | 07 | Certificates | Proportional Balancing | 3.4.6.1 | G | ||||||||||||||
| 335 | 23 05 93 | 07 | Certificates | Proportional Balancing | 3.7 | G | ||||||||||||||
| 336 | 23 05 93 | 07 | Certificates | Season 1 | 3.4.6.2 | G | ||||||||||||||
| 337 | 23 05 93 | 07 | Certificates | Season 1 | 3.7 | G | ||||||||||||||
| 338 | 23 05 93 | 07 | Certificates | Season 2 | 3.4.6.2 | G | ||||||||||||||
| 339 | 23 05 93 | 07 | Certificates | Season 2 | 3.7 | G | ||||||||||||||
| 340 | 23 07 00 | 02 | Shop Drawings | MICA Plates | 3.2.2.4 | G | ||||||||||||||
| 341 | 23 07 00 | 02 | Shop Drawings | Pipe Insulation Systems | 2.3 | |||||||||||||||
| 342 | 23 07 00 | 02 | Shop Drawings | Pipe Insulation Systems | 3.2 | |||||||||||||||
| 343 | 23 07 00 | 02 | Shop Drawings | Duct Insulation Systems | 3.3 | |||||||||||||||
| 344 | 23 07 00 | 02 | Shop Drawings | Equipment Insulation Systems | 3.4 | |||||||||||||||
| 345 | 23 07 00 | 03 | Product Data | Pipe Insulation Systems | 2.3 | G | ||||||||||||||
| 346 | 23 07 00 | 03 | Product Data | Pipe Insulation Systems | 3.2 | G | ||||||||||||||
| 347 | 23 07 00 | 03 | Product Data | Duct Insulation Systems | 3.3 | G | ||||||||||||||
| 348 | 23 07 00 | 03 | Product Data | Equipment Insulation Systems | 3.4 | G | ||||||||||||||
| 349 | 23 07 00 | 04 | Samples | Thermal Insulation | 2.2.1.3 | G | ||||||||||||||
| 350 | 23 07 00 | 04 | Samples | Display Samples | 3.1.1 | G | ||||||||||||||
| 351 | 23 07 00 | 08 | Manufacturer’s Instructions | Pipe Insulation Systems | 2.3 | G | ||||||||||||||
| 352 | 23 07 00 | 08 | Manufacturer’s Instructions | Pipe Insulation Systems | 3.2 | G | ||||||||||||||
| 353 | 23 07 00 | 08 | Manufacturer’s Instructions | Duct Insulation Systems | 3.3 | G | ||||||||||||||
| 354 | 23 07 00 | 08 | Manufacturer’s Instructions | Equipment Insulation Systems | 3.4 | G | ||||||||||||||
| 355 | 23 09 00 | 02 | Shop Drawings | DDC Contractor Design Drawings | 3.2 | G | ||||||||||||||
| 356 | 23 09 00 | 02 | Shop Drawings | Draft As-Built Drawings | 3.2 | G | ||||||||||||||
| 357 | 23 09 00 | 02 | Shop Drawings | Final As-Built Drawings | 3.2 | G | ||||||||||||||
| 358 | 23 09 00 | 03 | Product Data | Programming Software | 1.8.3 | G | ||||||||||||||
| 359 | 23 09 00 | 03 | Product Data | Controller Application Programs | 1.8.4 | G | ||||||||||||||
| 360 | 23 09 00 | 03 | Product Data | Configuration Software | 1.8.1 | G | ||||||||||||||
| 361 | 23 09 00 | 03 | Product Data | Controller Configuration Settings | 1.8.2 | G | ||||||||||||||
| 362 | 23 09 00 | 03 | Product Data | Manufacturer's Product Data | 2.2 | G | ||||||||||||||
| 363 | 23 09 00 | 03 | Product Data | Niagara Framework Supervisory Gateway Backups | 1.8.5 | G | ||||||||||||||
| 364 | 23 09 00 | 03 | Product Data | Niagara Framework Engineering Tool | 1.8.6 | G | ||||||||||||||
| 365 | 23 09 00 | 05 | Design Data | Boiler Or Chiller Plant Gateway Request | 1.9 | |||||||||||||||
| 366 | 23 09 00 | 06 | Test Reports | Start-Up Testing Report | 3.4.2 | G | ||||||||||||||
| 367 | 23 09 00 | 06 | Test Reports | PVT Procedures | 3.5.1 | G | ||||||||||||||
| 368 | 23 09 00 | 06 | Test Reports | PVT Report | 3.5.3 | G | ||||||||||||||
| 369 | 23 09 00 | 06 | Test Reports | Pre-Construction Quality Control (QC) Checklist | 1.10.1 | G | ||||||||||||||
| 370 | 23 09 00 | 06 | Test Reports | Post-Construction Quality Control (QC) Checklist | 1.10.2 | G | ||||||||||||||
| 371 | 23 09 00 | 10 | Operation and Maintenance Data | Operation and Maintenance (O&M) Instructions | 3.6 | G | ||||||||||||||
| 372 | 23 09 00 | 10 | Operation and Maintenance Data | Training Documentation | 3.7.1 | G | ||||||||||||||
| 373 | 23 09 00 | 11 | Closeout Submittals | Enclosure Keys | 2.5 | G | ||||||||||||||
| 374 | 23 09 00 | 11 | Closeout Submittals | Password Summary Report | 3.1.6.1 | G | ||||||||||||||
| 375 | 23 09 00 | 11 | Closeout Submittals | Closeout Quality Control (QC) Checklist | 1.10.3 | G | ||||||||||||||
| 376 | 23 21 13.00 20 | 02 | Shop Drawings | Hot water heating system; | 1.3.1 | |||||||||||||||
| 377 | 23 21 13.00 20 | 03 | Product Data | Hot Water Heating Pipe | 2.1.1 | G | ||||||||||||||
| 378 | 23 21 13.00 20 | 03 | Product Data | Finned Tube Radiators | 2.2.1 | G | ||||||||||||||
| 379 | 23 21 13.00 20 | 06 | Test Reports | Hydrostatic test of piping system | 3.3.1 | |||||||||||||||
| 380 | 23 21 13.00 20 | 07 | Certificates | Welding procedures | 1.5.2.1 | |||||||||||||||
| 381 | 23 21 13.00 20 | 07 | Certificates | Welder's qualifications | 1.5.2.2 | |||||||||||||||
| 382 | 23 21 13.00 20 | 10 | Operation and Maintenance Data | Finned tube radiators | 2.2.1 | G | ||||||||||||||
| 383 | 23 25 00 | 03 | Product Data | Glycol | 0 | G | ||||||||||||||
| 384 | 25 10 10 | 02 | Shop Drawings | UMCS Contractor Design Drawings | 3.3.1 | |||||||||||||||
| 385 | 25 10 10 | 02 | Shop Drawings | Draft As-Built Drawings | 3.3.2 | |||||||||||||||
| 386 | 25 10 10 | 02 | Shop Drawings | Final As-Built Drawings | 3.3.2 | |||||||||||||||
| 387 | 25 10 10 | 03 | Product Data | Product Data Sheets | 2.1.5 | |||||||||||||||
| 388 | 25 10 10 | 03 | Product Data | Enclosure Keys | 2.3.1 | |||||||||||||||
| 389 | 25 10 10 | 06 | Test Reports | Pre-Construction QC Checklist | 1.6 | |||||||||||||||
| 390 | 25 10 10 | 06 | Test Reports | Post-Construction QC Checklist | 1.6 | |||||||||||||||
| 391 | 25 10 10 | 06 | Test Reports | Factory Test Procedures | 3.1 | |||||||||||||||
| 392 | 25 10 10 | 06 | Test Reports | Factory Test Report | 3.1 | |||||||||||||||
| 393 | 25 10 10 | 06 | Test Reports | Existing Conditions Report | 3.2 | |||||||||||||||
| 394 | 25 10 10 | 06 | Test Reports | Start-Up and Start-Up Testing Report | 3.7 | G | ||||||||||||||
| 395 | 25 10 10 | 06 | Test Reports | PVT Phase I Procedures | 3.8.1 | |||||||||||||||
| 396 | 25 10 10 | 06 | Test Reports | PVT Phase I Report | 3.8.2 | G | ||||||||||||||
| 397 | 25 10 10 | 06 | Test Reports | PVT Phase II Report | 3.8.3 | G | ||||||||||||||
| 398 | 25 10 10 | 10 | Operation and Maintenance Data | Operation and Maintenance (O&M) Instructions | 1.7 | |||||||||||||||
| 399 | 25 10 10 | 10 | Operation and Maintenance Data | Preventive Maintenance Work Plan | 3.9.7.1 | |||||||||||||||
| 400 | 25 10 10 | 10 | Operation and Maintenance Data | Basic Training Documentation | 3.10.1 | |||||||||||||||
| 401 | 25 10 10 | 10 | Operation and Maintenance Data | Advanced Training Documentation | 3.10.1 | |||||||||||||||
| 402 | 25 10 10 | 10 | Operation and Maintenance Data | Refresher Training Documentation | 3.10.1 | |||||||||||||||
| 403 | 25 10 10 | 11 | Closeout Submittals | Closeout QC Checklist | 1.6 | |||||||||||||||
| 404 | 26 20 00 | 02 | Shop Drawings | Panelboards | 2.12 | G | ||||||||||||||
| 405 | 26 20 00 | 02 | Shop Drawings | Transformers | 2.13 | G | ||||||||||||||
| 406 | 26 20 00 | 02 | Shop Drawings | Cable Trays | 0 | G | ||||||||||||||
| 407 | 26 20 00 | 02 | Shop Drawings | Coordination drawings | 0 | G | ||||||||||||||
| 408 | 26 20 00 | 02 | Shop Drawings | Wireways | 2.21 | G | ||||||||||||||
| 409 | 26 20 00 | 02 | Shop Drawings | Marking strips | 3.1.6.1 | G | ||||||||||||||
| 410 | 26 20 00 | 02 | Shop Drawings | Field fabricated nameplates | 0 | G | ||||||||||||||
| 411 | 26 20 00 | 03 | Product Data | Receptacles | 2.11 | G | ||||||||||||||
| 412 | 26 20 00 | 03 | Product Data | Circuit breakers | 2.12.3 | G | ||||||||||||||
| 413 | 26 20 00 | 03 | Product Data | Switches | 2.9 | G | ||||||||||||||
| 414 | 26 20 00 | 03 | Product Data | Transformers | 2.13 | G | ||||||||||||||
| 415 | 26 20 00 | 03 | Product Data | Grounding Busbar | 0 | G | ||||||||||||||
| 416 | 26 20 00 | 06 | Test Reports | 600-volt wiring test | 3.5.2 | G | ||||||||||||||
| 417 | 26 20 00 | 06 | Test Reports | Grounding system test plan and results | 0 | G | ||||||||||||||
| 418 | 26 20 00 | 06 | Test Reports | Transformer tests | 3.5.3 | G | ||||||||||||||
| 419 | 26 20 00 | 06 | Test Reports | Ground-fault receptacle test | 3.5.4 | G | ||||||||||||||
| 420 | 26 20 00 | 07 | Certificates | Fuses | 2.10 | G | ||||||||||||||
| 421 | 26 20 00 | 09 | Manufacturer’s Field Reports | Transformer factory tests | 2.23.1 | |||||||||||||||
| 422 | 26 20 00 | 10 | Operation and Maintenance Data | Electrical Systems | 0 | G | ||||||||||||||
| 423 | 26 51 00 | 02 | Shop Drawings | Luminaire Drawings | 1.5.1 | G | ||||||||||||||
| 424 | 26 51 00 | 02 | Shop Drawings | Occupancy/Vacancy Sensor Coverage Layout | 1.5.2 | G | ||||||||||||||
| 425 | 26 51 00 | 03 | Product Data | Luminaires | 2.2 | G | ||||||||||||||
| 426 | 26 51 00 | 03 | Product Data | Light Sources | 2.4 | G | ||||||||||||||
| 427 | 26 51 00 | 03 | Product Data | Drivers, Ballasts and Generators | 2.3 | G | ||||||||||||||
| 428 | 26 51 00 | 03 | Product Data | LED Luminaire Warranty | 1.6.1 | G | ||||||||||||||
| 429 | 26 51 00 | 03 | Product Data | Luminaire Design Data | 1.5.4 | G | ||||||||||||||
| 430 | 26 51 00 | 03 | Product Data | Vacancy Sensors | 2.5.3.2 | G | ||||||||||||||
| 431 | 26 51 00 | 03 | Product Data | Dimming Controllers (Dimmers) | 2.5.2 | G | ||||||||||||||
| 432 | 26 51 00 | 03 | Product Data | Lighting Contactor | 2.5.4 | G | ||||||||||||||
| 433 | 26 51 00 | 03 | Product Data | Timeswitch | 2.5.5 | G | ||||||||||||||
| 434 | 26 51 00 | 03 | Product Data | Power Hook Luminaire Hangers | 2.8 | G | ||||||||||||||
| 435 | 26 51 00 | 03 | Product Data | Exit Signs | 2.6.1 | G | ||||||||||||||
| 436 | 26 51 00 | 03 | Product Data | Emergency Lighting Unit (EBU) | 2.6.2 | G | ||||||||||||||
| 437 | 26 51 00 | 03 | Product Data | LED Emergency Drivers | 2.6.3 | G | ||||||||||||||
| 438 | 26 51 00 | 03 | Product Data | Fluorescent Emergency Ballasts | 2.6.4 | G | ||||||||||||||
| 439 | 26 51 00 | 03 | Product Data | Occupancy Sensors | 2.5.3.1 | G | ||||||||||||||
| 440 | 26 51 00 | 03 | Product Data | Ambient Light Level Sensor | 3.1.8 | G | ||||||||||||||
| 441 | 26 51 00 | 03 | Product Data | Bi-Level HID Controller | 2.5.6 | G | ||||||||||||||
| 442 | 26 51 00 | 03 | Product Data | Lighting Control Panel | 2.5.7 | G | ||||||||||||||
| 443 | 26 51 00 | 06 | Test Reports | LED Luminaire - IES LM-79 Test Report | 1.5.5 | G | ||||||||||||||
| 444 | 26 51 00 | 06 | Test Reports | LED Light Source - IES LM-80 Test Report | 1.5.6 | G | ||||||||||||||
| 445 | 26 51 00 | 06 | Test Reports | LED Light Source - IES TM-21 Test Report | 1.5.7 | G | ||||||||||||||
| 446 | 26 51 00 | 06 | Test Reports | Occupancy/Vacancy Sensor Verification Tests | 1.5.8 | G | ||||||||||||||
| 447 | 26 51 00 | 06 | Test Reports | Energy Efficiency | 1.5.11.3 | G | ||||||||||||||
| 448 | 26 51 00 | 07 | Certificates | Luminaire Useful Life Certificate | 1.6.1.1 | G | ||||||||||||||
| 449 | 26 51 00 | 07 | Certificates | LED Driver and Dimming Switch Compatibility Certificate | 1.5.3 | G | ||||||||||||||
| 450 | 26 52 00.00 40 | 02 | Shop Drawings | Central Emergency Lighting Systems | 2.2.3 | G | ||||||||||||||
| 451 | 26 52 00.00 40 | 03 | Product Data | Material, Equipment, and Fixture Lists | 1.2.1 | G | ||||||||||||||
| 452 | 26 52 00.00 40 | 03 | Product Data | Sample Warranty | 1.2.1 | G | ||||||||||||||
| 453 | 26 52 00.00 40 | 03 | Product Data | Emergency Lighting Egress Units | 2.2.1 | G | ||||||||||||||
| 454 | 26 52 00.00 40 | 03 | Product Data | Emergency Fluorescent Lighting | 2.2.2 | G | ||||||||||||||
| 455 | 26 52 00.00 40 | 03 | Product Data | Central Emergency Lighting Systems | 2.2.3 | G | ||||||||||||||
| 456 | 26 52 00.00 40 | 03 | Product Data | Accessories | 2.2.3.4 | G | ||||||||||||||
| 457 | 26 52 00.00 40 | 06 | Test Reports | System Operational Tests | 3.2 | G | ||||||||||||||
| 458 | 26 52 00.00 40 | 07 | Certificates | Certificates of Conformance | 1.2.1 | |||||||||||||||
| 459 | 26 52 00.00 40 | 11 | Closeout Submittals | Warranty | 3.3 | |||||||||||||||
| 460 | 26 53 00.00 40 | 01 | Preconstruction Submittals | Material, Equipment, and Fixture Lists | 1.2.1 | G | ||||||||||||||
| 461 | 26 53 00.00 40 | 02 | Shop Drawings | Exit Lighting Units | 1.2.1 | G | ||||||||||||||
| 462 | 26 53 00.00 40 | 02 | Shop Drawings | Exit Lighting Units Outline Drawings | 1.2.1 | G | ||||||||||||||
| 463 | 26 53 00.00 40 | 03 | Product Data | Exit Lighting Units | 1.2.1 | G | ||||||||||||||
| 464 | 26 53 00.00 40 | 03 | Product Data | Contemporary Fixtures | 1.2.1 | G | ||||||||||||||
| 465 | 26 53 00.00 40 | 03 | Product Data | Accessories | 1.2.1 | G | ||||||||||||||
| 466 | 26 53 00.00 40 | 06 | Test Reports | Operational Tests | 3.2.1 | G | ||||||||||||||
| 467 | 26 53 00.00 40 | 07 | Certificates | Energy Efficiencies | 1.2.1 | G | ||||||||||||||
| 468 | 28 31 74.00 20 | 02 | Shop Drawings | System floor plans | 1.6.4.1 | G | ||||||||||||||
| 469 | 28 31 74.00 20 | 02 | Shop Drawings | System wiring diagrams | 1.6.4.2 | G | ||||||||||||||
| 470 | 28 31 74.00 20 | 02 | Shop Drawings | Conductor wire marker schedule | 3.1 | G | ||||||||||||||
| 471 | 28 31 74.00 20 | 03 | Product Data | Storage batteries | 2.1.3.1 | G | ||||||||||||||
| 472 | 28 31 74.00 20 | 03 | Product Data | Alarm horns | 2.2.1.1 | G | ||||||||||||||
| 473 | 28 31 74.00 20 | 03 | Product Data | Visible appliances | 2.2.1.2 | G | ||||||||||||||
| 474 | 28 31 74.00 20 | 03 | Product Data | Wiring | 2.2.5 | G | ||||||||||||||
| 475 | 28 31 74.00 20 | 03 | Product Data | Conduit | 2.2.2 | |||||||||||||||
| 476 | 28 31 74.00 20 | 03 | Product Data | Outlet boxes | 2.2.3 | |||||||||||||||
| 477 | 28 31 74.00 20 | 03 | Product Data | Fittings for conduit and outlet boxes | 2.2.4 | |||||||||||||||
| 478 | 28 31 74.00 20 | 05 | Design Data | Power calculations | 1.4.1.1 | G | ||||||||||||||
| 479 | 28 31 74.00 20 | 06 | Test Reports | Preliminary testing | 3.2.1 | G | ||||||||||||||
| 480 | 28 31 74.00 20 | 06 | Test Reports | Final acceptance testing | 3.2.2 | G | ||||||||||||||
| 481 | 28 31 74.00 20 | 07 | Certificates | Qualifications of installer | 1.6.1 | G | ||||||||||||||
| 482 | 28 31 74.00 20 | 07 | Certificates | Qualifications of system technician | 1.6.3 | G | ||||||||||||||
| 483 | 28 31 74.00 20 | 10 | Operation and Maintenance Data | Fire alarm system | 2.1.1 | G | ||||||||||||||
| 484 | 28 31 74.00 20 | 11 | Closeout Submittals | System as-built drawings | 1.6.4.3 | G |