This document includes an attachment for a past and present performance survey and details of a solicitation to construct a multipurpose facility at Bombay Hook National Wildlife Refuge in Delaware. The solicitation involves providing all labor, equipment, and materials to complete a parking area, visitor center, administrative offices, and associated site improvements and utility upgrades on a firm-fixed-price basis. Offerors must submit information on relevant past performance, bonding, personnel, and a price proposal in accordance with the instructions and evaluation criteria provided. A pre-proposal site visit is scheduled for July 29th and August 4th, 2021 at the project address. The solicitation was issued by the U.S. Fish and Wildlife Service Region 2 for the Department of the Interior.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 5 140F0221R0018 page 1 of 4

PAST AND PRESENT PERFORMANCE SURVEY

Your Company Name:

Street Address:

City, State and ZIP Code:

1. GENERAL BUSINESS INFORMATION

Date Firm Organized/Established:

Company President: Vice President:

Dun & Bradstreet Number: __

Is company a ; Partnership [ ] Separate entity [ ] Division [ ] N/A [ ]

2. CONTRACT BONDING INFORMATION

Name of your bonding company intended to use:

Mailing Address:

City, State (including ZIP Code):

Point of Contact: Telephone No.: ( )

3. CONTRACTS/SUBCONTRACTS COMPLETED OR IN PROGRESS

Complete and submit the information requested on page 2-3 below on prime contracts or subcontracts completed or in progress. Government contracts are preferred; but, if you have not performed Government contracts, indicate any other contracts completed or in progress.

ATTACHMENT 5 140F0221R0018 page 2 of 4

a. First Contract:

Contracting Agency or Company:

Point of Contact: Telephone Number:

Contract Number: Contract/Subcontract Amount: $

Project Title and Location:

General Scope of Construction Project:

Your Role (Prime [ ], Joint Venture [ ], or Subcontractor [ ]) and the work your firm performed:

Describe any Work You Subcontracted to Others:

Total Amount of Subcontract(s): $

Period of Performance: days

Scheduled Completion Date:

Actual Completion Date: Percentage of Work Completed: %

Were You Terminated?

Were You Assessed Liquidated Damages?

(If the answer to either Question is “Yes”, Explain:

Did you use a Quality Control Plan? _________ Did you use a Safety Plan?_______________

Quality Control or Safety Problems encountered (if any):

How were the problems resolved?

ATTACHMENT 5 140F0221R0018 page 3 of 4

b. Second Contract:

Contracting Agency or Company:

Point of Contact: Telephone Number:

Contract Number: Contract/Subcontract Amount: $

Project Title and Location:

General Scope of Construction Project:

Your Role (Prime [ ], Joint Venture [ ], or Subcontractor [ ]) and the work your firm performed:

Describe any Work You Subcontracted to Others:

Total Amount of Subcontract(s): $

Period of Performance: days

Scheduled Completion Date:

Actual Completion Date: Percentage of Work Completed: %

Were You Terminated?

Were You Assessed Liquidated Damages?

(If the answer to either Question is “Yes”, Explain:

Did you use a Quality Control Plan? _________ Did you use a Safety Plan?_______________

Quality Control or Safety Problems encountered (if any):

How were the problems resolved?

ATTACHMENT 5 140F0221R0018 page 4 of 4

4. Certification of Past and Present Performance Information:

Type or Print Information

Name of Survey Preparer_______________________________

Title__________________________________________

Signature______________________________________

Date__________________________________________

PAST AND PRESENT PERFORMANCE SURVEY
1. GENERAL BUSINESS INFORMATION
2. CONTRACT BONDING INFORMATION
3. CONTRACTS/SUBCONTRACTS COMPLETED OR IN PROGRESS