This document provides two federal wage determinations applicable to the solicitation for construction of a multipurpose facility at Bombay Hook National Wildlife Refuge in Delaware. The wage determinations outline prevailing wage rates for various construction crafts such as carpenters, electricians, laborers, operators and welders according to the Davis-Bacon Act. The related federal contract opportunity seeks offers for all work to complete the multipurpose facility including a visitor center, administrative offices, parking area and site improvements. A firm fixed price award is contemplated from this solicitation evaluated based on key personnel, past performance, technical approach and price. Site visits for the pre-proposal are scheduled on July 29th and August 4th 2021 at the project address. The soliciting agency is the U.S. Fish and Wildlife Service Region 2 for this construction project.

View the file

Other files for this federal contract opportunity

Other files attached to CONSTRUCT MULTIPURPOSE FACILITY, BOMBAY HOOK NWR, DE, newest first.
File Type Posted
Amend_3_Attach_1_Solicitation_140F0221R0018_updated_Attachment_4_Quote_Schedule_August_31_2021_0003.pdf PDF
Sol_140F0221R0018_Amd_0003.pdf PDF
Amend_3_Attach_2_Solicitation_140F0221R0018_Questions_and_Answers_to_date_August_31_2021_0003.pdf PDF
Amend_2_Attach_2_Solicitation_140F0221R0018_Questions_and_Answers_to_date_August_25__2021_0002.pdf PDF
Sol_140F0221R0018_Amd_0002.pdf PDF
Amend_2_Attach_1_Solicitation_140F0221R0018_updated_Attachment_4_Quote_Schedule_August_25_2021_0002.pdf PDF
Sol_140F0221R0018_Amd_0001.pdf PDF
Amend_1_Attach_3_Site_Visit_Sign_in_sheets_info_0001.pdf PDF
Amend_1_Attach_1_Solicitation_140F0221R0018_updated_Clauses_Provisions_August_16_2021_0001.pdf PDF
Amend_1_Attach_2_Solicitation_140F0221R0018_Questions_and_Answers_to_date_August_12__2021_0001.pdf PDF
Attachment_5__PAST_AND_PRESENT_PERFORMANCE_SURVEY.pdf PDF
Sol_140F0221R0018.pdf PDF
Attachment_1B_100pct_Roadway_Specifications.pdf PDF
Attachment_1C_Bombay_Hook_Waste_Water_Permit_245166.pdf PDF
Attachment_1A_Bombay_Hook_New_MPF_Specifications.pdf PDF
Attachment_4_Quote_Schedule.pdf PDF
Attachment_2B_100pct_Roadway_Drawings.pdf PDF
Attachment_2A_Bombay_Hook_New_MPF_Drawings.pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 1 of 18 "General Decision Number: DE20210007 06/11/2021

Superseded General Decision Number: DE20200007

State: Delaware

Construction Type: Building

County: Kent County in Delaware.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.95 for calendar year 2021 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January

1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.95 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year

2021. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the

Davis-Bacon Related Acts, including those set forth at 29 CFR

5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 2 of 18

Modification Number Publication Date

0 01/01/2021

1 01/15/2021

2 04/02/2021

3 05/14/2021

4 06/11/2021

BOIL0013-009 01/01/2016

Rates Fringes

BOILERMAKER......................$ 42.26 37.02

BRDE0001-001 05/01/2019

BRICKLAYER

Brick Refractory/Brick

Placement Worker............$ 35.00 24.57

Bricklayer..................$ 33.37 24.57

CARP0173-009 05/01/2020

CARPENTER (Includes

Acoustical Ceiling

Installation, Drywall

Hanging, Form Work, Metal

Stud Installation, Scaffold

Building, Excludes

Masonry/Brick, and Excludes

Soft Floor Layer)................$ 32.97 23.84

* CARP0251-008 05/01/2021

ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 3 of 18

SOFT FLOOR LAYER.................$ 33.08 23.46

CARP1906-003 07/01/2015

MILLWRIGHT.......................$ 36.05 30.63

ELEC0313-002 06/01/2020

ELECTRICIAN (Includes Low

Voltage Wiring and

Installation of Alarms, HVAC/Temperature Controls and

Sound and Communication

Systems).........................$ 41.75 32.51

ELEV0005-003 01/01/2018

ELEVATOR MECHANIC................$ 55.76 32.645+A&B

FOOTNOTES FOR ELEVATOR MECHANICS:

A. PAID VACATION: Employer contributes 8% of basic hourly rate for 5 years or more of service or 6% for 6 months to 5 years of service.

B. Eight Paid Holidays (provided employee has worked 5 consecutive days before and the working day after the holiday): New Years's Day; Memorial Day; Independence Day;

Labor Day; Veteran's Day; Thanksgiving Day and the Friday after Thanksgiving Day, and Christmas Day.

ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 4 of 18

ENGI0542-003 05/01/2020

POWER EQUIPMENT OPERATOR

(Forklift).......................$ 42.16 28.80+A

FOOTNOTE: A. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas

Day, and Election Day (provided the employee works the scheduled work day following the holiday.)

IRON0451-003 07/01/2020

IRONWORKER (Ornamental and

Reinforcing).....................$ 39.10 31.35

The following holidays shall be observed, and when work is performed thereon it shall be paid for at twice the base wage rate: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.

LABO0199-005 05/01/2020

LABORER

Backfiller, Common or

General, Jack Hammer, Mason Tender - Brick, Pipelayer, Scaffold

Builder (Brick and

ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 5 of 18 Masonry), Tamper (Hand

Held).......................$ 25.95 22.50

Mason Tender -

Cement/Concrete.............$ 26.20 22.50

PAIN0252-002 05/01/2020

GLAZIER..........................$ 44.92 30.55

PLAS0008-006 05/01/2019

PLASTERER (Fireproofer)..........$ 37.72 30.54

PLAS0592-009 05/01/2020

CEMENT MASON/CONCRETE FINISHER...$ 32.74 27.83

PLUM0074-002 07/01/2019

PIPEFITTER (Includes HVAC

Pipe Installation and

Excludes Industrial Work)........$ 53.18 34.99

FOOTNOTE A: PAID HOLIDAYS: New Year's Day, Memorial

Day,Independence Day, Thanksgiving Day,Labor Day, Christmas

Day, and General Election Day.

PLUM0074-003 07/01/2019

ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 6 of 18

PIPEFITTER (INDUSTRIAL)..........$ 53.18 34.99

FOOTNOTE A: PAID HOLIDAYS: New Year's Day, Memorial

Day,Independence Day, Thanksgiving Day,Labor Day, Christmas

Day, and General Election Day.

SFDE0669-002 04/01/2021

SPRINKLER FITTER (Fire

Sprinklers)......................$ 39.36 25.42

SHEE0019-021 07/01/2020

SHEET METAL WORKER (Includes

HVAC Duct Installation)..........$ 33.63 40.60

SUDE2014-004 01/20/2016

IRONWORKER, STRUCTURAL...........$ 37.42 15.04

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 47.71 8.41

OPERATOR: Bulldozer.............$ 25.89 0.00

OPERATOR: Crane.................$ 31.59 16.83

PAINTER (Brush and Roller).......$ 40.57 0.94

ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 7 of 18

PLUMBER..........................$ 45.40 16.23

ROOFER (Installation of Metal

Roofs Only)......................$ 39.09 30.77

ROOFER, Excludes Installation of Metal Roofs...................$ 27.98 27.90

TILE FINISHER....................$ 35.40 4.31

TILE SETTER......................$ 57.98 1.11

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the

Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after

ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 8 of 18 award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate

(weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or

""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 9 of 18 Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010

08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 10 of 18

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour

Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the

Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the

Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations

Wage and Hour Division

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator

(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator

U.S. Department of Labor

ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 11 of 18

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative

Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION"

ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 12 of 18

"General Decision Number: DE20210010 06/11/2021

Superseded General Decision Number: DE20200010

State: Delaware

Construction Type: Heavy

County: Kent County in Delaware.

HEAVY CONSTRUCTION PROJECTS

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.95 for calendar year 2021 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January

1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.95 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year

2021. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the

Davis-Bacon Related Acts, including those set forth at 29 CFR

5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 13 of 18

Modification Number Publication Date

0 01/01/2021

1 01/15/2021

2 04/02/2021

3 06/11/2021

* CARP0173-010 05/01/2021

CARPENTER (Includes Form Work)...$ 33.65 24.21

ELEC0126-003 06/01/2020

LINE CONSTRUCTION (Lineman)......$ 46.32 31.25%+11.75

ENGI0542-008 05/01/2020

POWER EQUIPMENT OPERATOR

(Backhoe/Excavator/Trackhoe, Crane, Forklift, and Scraper)....$ 42.16 28.80+A

FOOTNOTE: A. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas

Day, and Election Day (provided the employee works the scheduled work day following the holiday.)

LABO0199-007 05/01/2020

LABORER

ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 14 of 18 Backfiller, Pipelayer, and

Tamper (Hand Held)..........$ 26.20 22.50

Trencher Hand Guided........$ 25.95 22.50

SUDE2014-007 01/20/2016

CEMENT MASON/CONCRETE FINISHER...$ 25.78 0.58

ELECTRICIAN......................$ 34.96 23.87

LABORER: Common or General......$ 19.09 0.00

OPERATOR: Bulldozer.............$ 28.12 7.56

OPERATOR: Loader................$ 25.55 7.56

TRUCK DRIVER: Dump Truck........$ 22.60 7.56

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the

Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons

ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 15 of 18 resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate

(weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or

""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 16 of 18 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010

08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 17 of 18 A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour

Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the

Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the

Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations

Wage and Hour Division

U.S. Department of Labor

ATTACH 3, Construct Multipurpose Building Bombay Hook NWR, DE page 18 of 18 2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator

(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative

Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION"