This document is a set of electrical construction drawings for the MCC Breaker Maintenance project at Building 62, Second Floor, prepared by Bernhard TME for a federal facility located at 3900 UFTH Road, Jefferson Barracks, Missouri 63125.
The project involves the removal and replacement of existing motor control centers (MCCs) and related electrical distribution equipment. Specifically, the work includes: removing an existing Federal Pacific MCC and a Cutler Hammer MCC, with circuits to be re-fed to new distribution panels HDP-7 and HDP-A respectively; retaining a 600A GE MCC and existing Panel AA with protection during construction; and re-feeding Panel AA and other existing panels from new switchgear per a new one-line diagram. All existing electrical equipment must remain protected during construction unless otherwise noted. The contractor is required to coordinate power outages carefully with the facility owner, provide temporary power and generators as needed for circuits that cannot be disconnected for extended periods, and plan work during after-business hours and weekends to minimize operational disruption. All circuit reconnections must match existing wire sizes and trip settings as documented in panel schedules and elevations. The demolition floor plan (left side) shows current equipment locations, while the new floor plan (right side) illustrates the reconfigured layout following equipment relocation and installation of replacement panels.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MCC-7
MCC-A
MCC-4
REMOVE EXISTING
FEDERAL PACIFIC MCC
EXISTING 600A GE
MCC TO REMAIN AND
PROTECTED
2EXISTING TO REMAIN
AHU-1
TRANSFORMER
DISCONNECT
EXISTING PANEL
'AA' TO REMAIN
HDP-9
MDP-62
HDP-AHDP-7
HDP-9
MDP-62
NO. 18899
ARKANSAS
ENGINEER
PROFESSIONAL
REGISTERED
OFETA
S T
A L I H ON A R M A N
D
NARKA
SA S
No. 2790
CE
RT
IF
IC
ATE OF AUTHOR
IZAT
ION
Bernhard
TME, LLC
ISSUE DATE:
SHEET NUMBER:
PROJECT
NUMBER:
1 ALLIED DRIVE, BUILDING 2
SUITE 2600
LITTLE ROCK, AR 72202
Phone: (501) 666-6776
Fax: (501) 663-8888 tme@bernhardtme.com
SHEET TITLE:
ENGINEER SEAL
CORPORATE SEAL
100% CONSTRUCTION
DOCUMENTS
E1230
BUILDING 62 - SECOND FLOOR
PLANS - DEMOLITION & NEW
10-15-21
01-19-0062
M C
C B
R E
A K
E R
M A
IN
T
E N
A N
C E
J E
F F
E R
S O
N L
A B
O R
A T
O R
IE
S
N
C T
R R
O A
D J E
F F
E R
S O
N
A R
K A
N S
A S
1/8" = 1'-0"1
FLOOR PLAN - BUILDING 62 SECOND FLOOR - DEMOLITION
1/8" = 1'-0"2
FLOOR PLAN - BUILDING 62 SECOND FLOOR - NEW
DEMOLITION KEYED NOTES:
EXISTING CIRCUITS FED OUT OF THE CUTLER HAMMER MCC TO BE
RE-FED FROM NEW PANELBOARD HDP-A. REFER TO ELEVATIONS
AND NEW FLOOR PLAN. REMOVE MCC AFTER NEW PANEL IS
INSTALLED AND ALL CIRCUITS HAVE BEEN TRANSFERRED.
EXISTING CIRCUITS FED OUT OF THE FEDERAL PACIFIC MCC TO BE
RE-FED FROM NEW PANELBOARD HDP-7. REFER TO ELEVATIONS
AND NEW FLOOR PLAN. REMOVE MCC AFTER NEW PANEL IS
INSTALLED AND ALL CIRCUITS HAVE BEEN TRANSFERRED.
EXISTING PANEL TO REMAIN AND PROTECTED DURING
CONSTRUCTION. PANEL TO BE RE-FED FROM NEW SWITCHGEAR.
REFER TO NEW ONE-LINE DIAGRAM. PANEL IS LOCATED ON 3RD
FLOOR MECHANICAL ROOM(2ND FLOOR ROOF).
EXISTING PANEL TO REMAIN AND PROTECTED DURING
CONSTRUCTION. PANEL TO BE RE-FED FROM NEW SWITCHGEAR.
REFER TO NEW ONE-LINE DIAGRAM.
GENERAL NOTES:
UNLESS OTHERWISE NOTED, ALL ELECTRICAL EQUIPMENT TO
REMAIN AND PROTECTED DURING CONSTRUCTION.
COORDINATE ALL POWER OUTAGES VERY CAREFULLY WITH
OWNER PRIOR TO TURNING OFF POWER. CONTRACTOR TO
PROVIDE TEMPORARY POWER AND GENERATOR AS NEEDED FOR
EVERY CIRCUIT THAT CANNOT BE DISCONNECTED FOR A LONG
PERIOD OF TIME. COORDINATE WITH OWNER CLOSELY.
CONTRACTOR TO PLAN FOR WORKING AFTER BUSINESS HOURS
AND WEEKENDS.
1.
2.
KEYED NOTES:
1 RE-CONNECT EXISTING CIRCUITS THAT WERE FED FROM MCC-A TO
NEW DISTRIBUTION PANEL. MATCH EXISTING WIRE SIZE AND TRIP
SETTINGS. REFER TO PANEL SCHEDULES AND ELEVATIONS FOR
MORE DETAILS.
RE-CONNECT EXISTING CIRCUITS THAT WERE FED FROM MCC-7 TO
NEW DISTRIBUTION PANEL. MATCH EXISTING WIRE SIZE AND TRIP
SETTINGS. REFER TO PANEL SCHEDULES AND ELEVATIONS FOR
MORE DETAILS.
RE-FEED PANEL FROM NEW SWITCHGEAR. REFER NO NEW ONE-
LINE DIAGRAM.
MARK DATE DESCRIPTION
| Sheets |
| E001 - GENERAL NOTES, LEGEND, AND BUILDING GROUPING/ADDITIVE ALTERNATES - ELECTRICAL |
| E002 - DETAILS - ELECTRICAL |
| E003 - DETAILS - STRUCTURAL |
| E101 - SITE PLAN - ELECTRICAL |
| E201 - BUILDING 5B - FLOOR PLAN & ONE-LINE DIAGRAM - DEMOLITION |
| E202 - BUILDING 5B - FLOOR PLAN & ONE-LINE DIAGRAM - NEW |
| E203 - BUILDING 5B - ELEVATIONS, SCHEDULES AND NOTES |
| E301 - BUILDING 9 - ELECTRICAL DEMOLITION |
| E302 - BUILDING 9 - ELECTRICAL NEW |
| E303 - BUILDING 9 - ONE-LINE DIAGRAM |
| E401 - BUILDING 11 - FLOOR PLANS & ONE-LINE DIAGRAMS - DEMOLITION AND NEW |
| E402 - BUILDING 11 - ELEVATIONS, SCHEDULES AND NOTES |
| E501 - BUILDING 12 - FLOOR PLANS & ONE-LINE DIAGRAMS - DEMOLITION AND NEW |
| E502 - BUILDING 12 - ELEVATIONS, SCHEDULES AND NOTES |
| E601 - BUILDING 26 - FLOOR PLAN & ONE-LINE DIAGRAM |
| E602 - BUILDING 26 - ELEVATIONS AND NOTES |
| E701 - BUILDING 44 - FLOOR PLANS & ONE-LINE DIAGRAMS - DEMOLITION AND NEW |
| E702 - BUILDING 44 - ELEVATIONS, SCHEDULES AND NOTES |
| E801 - BUILDING 51 - FLOOR PLANS & ONE-LINE DIAGRAMS - DEMOLITION AND NEW |
| E802 - BUILDING 51 - ELEVATIONS, SCHEDULES AND NOTES |
| E901 - BUILDING 52 - FLOOR PLANS & ONE-LINE DIAGRAMS - DEMOLITION AND NEW |
| E902 - BUILDING 52 - ELEVATIONS, SCHEDULES AND NOTES |
| E1010 - BUILDING 53A - FLOOR PLAN & ONE-LINE DIAGRAM - DEMOLITION |
| E1020 - BUILDING 53A - FLOOR PLAN & ONE-LINE DIAGRAM - NEW |
| E1030 - BUILDING 53A - ELEVATIONS, SCHEDULES AND NOTES |
| E1040 - BUILDING 53A - ELEVATIONS AND NOTES |
| E1110 - BUILDING 60 - FLOOR PLANS & ONE-LINE DIAGRAMS - DEMOLITION AND NEW |
| E1120 - BUILDING 60 - ELEVATIONS, SCHEDULES AND NOTES |
| E1210 - BUILDING 62 - FIRST & BASEMENT FLOOR PLANS & ONE-LINE DIAGRAM - DEMOLITION |
| E1220 - BUILDING 62 - FIRST & BASEMENT FLOOR PLANS & ONE-LINE DIAGRAM - NEW |
| E1230 - BUILDING 62 - SECOND FLOOR PLANS - DEMOLITION & NEW |
| E1240 - BUILDING 62 - ELEVATIONS, SCHEDULES AND NOTES |
| E1250 - BUILDING 62 - ELEVATIONS, SCHEDULES AND NOTES |
| E1310 - BUILDING 85 - FLOOR PLANS & ONE-LINE DIAGRAMS - DEMOLITION AND NEW |
| E1320 - BUILDING 85 - ELEVATIONS, SCHEDULES AND NOTES |
| G100 - COVER SHEET |
| M501 - BUILDING 12 - MECHANICAL FLOOR PLAN |
File details come from the government source that posted it. Updated .