DATE 20 OCT 2022
PERFORMANCE WORK STATEMENT FOR
DFSP GUAM S-1 RME FUEL DISPOSAL
Background Information
Defense Fuel Support Point (DFSP) Guam currently operates 27 Belowground Field Constructed
Underground Storage Tanks (BFCUSTs), 21 Aboveground Storage Tanks (ASTs), and miles of pipeline across four main functional areas on Guam. The fuel terminal stores multiple types of Petroleum, Oil, and
Lubricant (POL) products to include, but not limited to Residual Marine Extract (RME), JP-5, JP-8, F-
76/diesel, and oily waste and sludge (slop).
Scope
This contract will cover government waste disposal activities (e.g. Hazardous Waste, Solid Waste, Used
Oil) on Guam.
Tasks
3.1 Prior to commencing any site work, Contractor shall coordinate an In-Brief Meeting with the
Contracting Officer’s Representative (COR), the Installation/Facility representative(s), and/or any other interested parties identified by the Contractor or Government. The Pre-Performance
Meeting shall occur via teleconference or in-person whichever is preferable to the Government.
This meeting shall be held to establish the responsibilities of each party, to discuss the schedule, and to ensure a mutual understanding of the scope.
3.2 The Contractor shall prepare a Work Plan (WP) outlining major work tasks, technical approach, project schedule, project management, Contractor's in-field staff, environmental protection, and the qualifications/responsibilities/names/contact information of oversight personnel. The WP shall demonstrate that the work will meet the requirements identified in this PWS, and applicable standards and guidance. No work shall start until the final Work Plan is accepted by the COR.
3.3 An Accidental Prevention Plan (APP) with Site Safety and Health Plan (SSHP) meeting all applicable 29 CFR 1910, Safety and Health Requirements Manual EM 385-1-1, local safety regulations, and other safety directives shall be prepared by the Contractor. No work shall start until the final APP is accepted by the COR.
3.4 Contractor shall remove and dispose of approximately 3,413 BBLs (143,346 gallons) of RME and sludge within Tank S-1. The contractor shall remove and dispose of RME and sludge leaving no more than 1/16 inch of content at the completion of removal work. Cleaning of tank is not required. Following the removal work, Contractor shall provide documentation certifying that the tank is empty.
Schedule
All tasks under this PWS must be completed with 180 days after award.
ACTIVITY TASK SCHEDULE (CALENDAR DAYS)
Task 3.1 Within 14 days of award
DATE 20 OCT 2022
Task 3.2, 3.3
Draft within 14 days of Task 3.1 completion
Government comments within 7 days receipt of draft
Final within 7 days of receiving Gov. comments
Task 3.4 Within 120 days of Task 3.2, 3.3 completion