Attachment 2- Project Specifications Lewis Valley Trail 22 Jan 2020.pdf
PDF 2 MB Posted
- Attached to
- Repair Lewis Valley Rd & Trl Federal contract opportunity
- Solicitation number
- FA301620R0041
About this file
This solicitation is for the repair of Lewis Valley Road and Lewis Valley Trail located on Joint Base San Antonio - Camp Bullis, Texas. The scope of work includes geotechnical borings and logs, topographic and construction surveying, development of professional engineer designed plans, a traffic control plan, demolition and disposal of existing pavement and base course, demolition of stormwater culverts and headwalls, construction of HDPE stormwater culverts and safety end treatments with reflectors, lime stabilization of subgrade, construction of a flexible base course and hot mix asphalt surface course. The Department of the Air Force Air Education and Training Command is listed as the agency. The response due date and award date are not provided.
View the file
Other files for this federal contract opportunity
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1033923 Repair Lewis Valley Trail
802D Civil Engineering Joint Base San Antonio
Request For Proposal
REPAIR LEWIS VALLEY TRAIL,
FAC. NO. 06880
JBSA-Camp Bullis, Texas
1033923 CYRB170018
CONTRACT: TBD
ATTACHMENT 2
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 31 19.00 44 PROJECT MEETING
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 29 OCCUPATIONAL SAFETY AND HEALTH
01 35 30 SAFETY, HEALTH AND EMERGENCY RESPONSE
01 35 35 ENVIRONMENTAL PROTECTION
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 20 CONTRACTOR QUALITY CONTROL
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 56 00.00 44 DUST CONTROL
01 71 23.16 CUTTING AND PATCHING
01 72 00.00 44 ALTERATIONS TO EXISTING FACILITIES
01 74 19.00 CONSTRUCTION WASTE MANAGEMENT
01 77 00.00 20 CONTRACT CLOSEOUT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 36.00 WARRANTY OF CONSTRUCTION
DIVISION 02 - EXISTING CONDITIONS
02 41 00 [DEMOLITION][ AND ][DECONSTRUCTION]
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 16.71 COLD MILLING ASPHALT PAVING
32 11 23 Graded Crushed BASE COURSES 32 11 29 Lime Stabilized Subgrade
32 12 13 BITUMINOUS TACK AND PRIME COATS
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 17 23 PAVEMENT MARKINGS
32 92 23 SODDING
DIVISION 33 - UTILITIES
33 40 00 STORM DRAINAGE UTILITIES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
**SUBMITTAL REGISTER**
SECTION 01 11 00 Page 3 Jan 22, 2020
SECTION
01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control approval.][for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.]Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
1. Traffic Control Plan; G, 2. Geotechnical Report; G,
3. Topographic Survey, G. 4. Engineering Drawings; G.
5. Existing Conditions photos, G. 6. Testing Schedule; G.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
This project begins at the intersection of Cowgill Rd and Lewis Valley Rd and proceeds north for approximately 28,196 linear feet to the project end at the intersection of Lewis Valley Trail and County Rd (Attachment 1).
The Contractor’s scope of project work includes:
a. Geotechnical borings and logs.
b. Topographic surveying and construction layout surveying.
c. Development of complete Professional Engineer designed construction plans.
d. Development and implementation of a Traffic Control Plan.
e. Demolition and disposal of existing 24-foot wide and 18-foot wide pavement and base course down to the top of the proposed lime stabilized subgrade, approximately 14-inches below top of existing pavement.
f. Demolition of 6 each, 24-inch storm water culverts and 12 headwalls.
g. Construction of 6 each, 24-inch HDPE storm water culverts and 12 TxDOT
Safety End Treatment (S.E.T.) with total of 12 pole mounted reflector, 2 at each S.E.T.
h. Construction of new Lime stabilization of 6-inches thick, 24-foot wide and 18-foot wide subgrade.
i. Construction of new 24-foot wide and 18 foot wide 6.0-inch thick flexible base course with TxDOT A2 base material.
SECTION 01 11 00 Page 4
j. Construction of new 24 foot wide and 18 foot wide TxDOT Type “C” hot mix asphaltic concrete surface course, 2.5-inches thick, constructed in one layer.
1.2.2. Work Plan Requirements
1.2.2.1. Surveying, Geotechnical, Design, and Traffic Control
Surveying: The Contractor shall provide a topographic survey of the entire length and width of the road out to approximately 2 feet past the proposed shoulders on each side. Contractor’s surveyor shall locate the centerline of the existing road and use that as a basis to provide construction staking to insure construction of pavement that has a uniform width and smooth transitions between horizontal curves and straight sections, smooth grades, and a 2% grade crown from the pavement center to pavement edge on each side of the road. Contractor shall provide and maintain all survey benchmarks/control points as needed to perform the work.
Project construction surveying work does not require the services of a Licensed Professional Surveyor.
Geotechnical: The proposed subgrade depth for the road shall be approximately 14-inches below the existing road surface and the 6 culverts may be as much as 48 inches below the road surface. The Contractor shall take at least 4 borings along the length of the project and provide logs that show subsurface conditions and depth to escarpment or very hard material that would make excavation to proposed subgrade unfeasible.
d. Design: The contractor shall develop construction plans for the repair of Lewis Valley Road. Specification are provided by the Government with this Summary of Work.
e. The Design Package, at a minimum, shall include: Cover Sheet, Overall Site Plan Sheet, Notes Sheets and Testing Schedule, Stormwater Pollution Prevention Plan (SWPPP), Plan and Profile Sheets, Roadway Striping Plan Sheet, and Details/Pavement Section Sheets. Hard copy submittal plans shall be printable in Tabloid size and shall be to scale.
f. Contractor shall field verify all required dimensions and information to produce the design documents. Contractor shall develop accurate electronic plans in AutoCAD 2010/2011 drawing format (.dwg) and PDF format.
g. The contractor shall submit for government review and approval, bound paper copies and electronic copies of 50%, 100%, and For Construction Design Package signed and sealed by a Texas State Licensed Professional Engineer. The Design Package shall consist of plans and specifications for the construction work required to repair Lewis Valley Road. Contractor shall submit a signed and sealed For Construction design package incorporating all corrections from 50% and 100% review. Mobilization and construction effort will only be allowed to begin upon: 1) the receipt of signed and sealed For Construction design package, 2) Lane closures and the Traffic Control Plan is approved by the 802 CE Squadron. All electronic copies shall be provided to the government in the native file format and PDF format.
h. h. Final As-Builts shall be signed, sealed, and each plan sheet stamped “As-Built”, by the designer of record. The Contractor shall provide an electronic copy and hard copy of the As-Built construction plans to the Govt. project manager.
SECTION 01 11 00 Page 5
Traffic Control Plan: The Contractor shall provide a professionally developed Traffic Control Plan for each phase of construction. The Traffic Control plan shall be drawn by a Traffic Engineer.
1.2.2.2. Traffic Signs and Barricades
The Contractor shall provide all temporary traffic signs and barricades necessary to reroute vehicle traffic.
1.2.2.3. Demolition
Contractor shall demolish approximately 150 linear feet of 24-inch concrete pipe and 6 concrete headwalls. Contractor shall demolish and dispose of approximately 9,800 cubic yards of old base and subgrade below the existing asphalt road.
Milling: The depth of milling of the existing pavement shall be deep enough to expose the base course. The Contractor shall store the millings on site and reuse them in the construction of the new road shoulders.
1.2.2.4. Civil/Site
1.2.2.4.1. Construction of Storm Water Pipes and S.E.T. Headwalls
Contractor shall construct six (6) storm water culverts. Each culvert pipe shall be made of High Density Polyethylene (HDPE), approximately 46 feet in length with water tight joints. Contractor shall construct a precast concrete TxDOT Safety End Treatment type headwall at each end of the pipe. The Contractor shall install 2-pole mounted yellow reflectors at each Safety End Treatment. (Attachment 2)
1.2.2.4.1. Construction of Lime Stabilized Subgrade
After Contractor has milled and removed the old pavement and demolished and removed the old base The Contractor shall lime stabilize 6-inches thickness of the subgrade with hydrated lime, 2% mix by weight. Lime shall be mixed and then allowed a 24 hour to 48 hour mellowing period. After mellowing the soil shall be remixed before it is compacted. The density of the compacted mixture shall be at least 90 percent of laboratory maximum density. See UFC 32-11-29 Lime Stabilization.
1.2.2.4.2. Construction of Flexible Base Course
Contractor shall construct a 24 foot wide, 6.0-inch thick flexible base course on top of the completed lime stabilized subgrade. Contractor shall place the TxDOT A2 base material over the lime stabilized subgrade and compact to 95% standard proctor.
1.2.2.4.3. Construction of TxDOT Type “C” Hot Mix Asphaltic Concrete Surface Course
Contractor shall construct the 24-foot wide, 2.5 inch thick Hot Mix Asphaltic Concrete Surface Course on top of the completed flexible base course. Because Camp Bullis is situated over the Aquifer prime coat shall not be applied to the Flexible Base.
The Contractor shall construct the surface course in one 2.5 inch lifts.
1.2.2.4.7. Yellow Raised Reflective Pavement Markers
Contractor shall install yellow raised reflective pavement markers along the centerline of the road spaced 40 feet apart. There will not be any pavement striping.
1.3 Environmental
Golden Cheeked Warbler Habitat- The Contractor shall not perform any road
SECTION 01 11 00 Page 6 construction next to the Golden Cheeked Warbler Habitat Area from March 1st to August 15th every year. The Golden Cheeked Warbler Habitat is shown on the SOW Attachment 1. It is next to the roadway and affects approximately 18,164 linear feet of roadway construction.
1.3.1 Contractor is responsible and liable to comply with all of JBSA-FSH Environmental Protection Section 01 35 35.
1.3.2 All waste chemicals, waste materials, and waste soils must be properly characterized, transported, and disposed of at a permitted Class 1 facility. Contact the JBSA-FSH Waste Program Manager at 671-5382 or 671-4844.
SECTION 01 11 11 Contractor will make every practical effort to maximize nonhazardous solid waste (SW) and construction and demolition (C&D) diversion from landfills or incinerators through reuse, donation, recycling, QRPs, composting and mulching, or other waste diversion activities to optimize reduction in both the volume of solid waste disposed and overall cost of non-hazardous solid waste management. A minimum of 54% of debris should be diverted through recycling and/or reuse.
Any compostable materials generated should be composted, scrap materials eligible for recycling must be recycled, and any waste sent for disposal at the landfill must be report to CEIE, Alvin Brown, alvin.brown@us.af.mil.
1.3.2.2. Only JBSA Environmental can sign waste manifests.
The Environmental personnel authorized to sign waste manifests are:
Jesse Alvarez, Steve Diaz, Eldred George, Edward Vogel, David Fierros, Gerardo Pantoja, Robert Hernandez.
1.3.3 Any removed concrete should be recycled and diversion/landfill rate must be reported to CEIE.
1.3.4 Contractor must record disposal and recycling quantities and will provide report to CEIE Base Environmental.
1.3.5 Ensure Paint, wash water and/or any material/debris generated during this activity is not dumped onto ground or allowed to enter storm drain or pollute storm water runoff.
1.3.6 Provide a plan for removal and manifesting C&D, tracking and recycling of scrap metal/concrete. Contractor will provide a manifest and fund the disposal of any and all waste. Any questions email Hazardous Waste Program Manager, Noah Ramos, 210-671- 0331, noah.ramos@us.af.mil. 1.5.9. Contractor will minimize nuisance dust emissions.
mailto:alvin.brown@us.af.mil mailto:noah.ramos@us.af.mil
SECTION 01 11 00 Page 7
1.3.7 Artifacts. If during excavation or other construction
activities any previously unidentified or unanticipated resources are discovered or found, the Contractor shall immediately stop work and notify the Contracting Officer and 502 CES/CEIE per requirements of Section 01 35 35 Environmental Protection. Resources covered by this paragraph include: any human skeletal remains or burials; artifacts;
shell, bone charcoal, or other deposits; rocks or coral alignments, paving, walls, or other constructed features, and any indication of agricultural or human activities.
1.3.8 Prior to any work being performed, Contractor must submit a
List and the associated Safety Data Sheets of the proposed hazardous materials to be used during the project to the JBSA- Lackland Hazardous Materials Office; email Hazardous Material Program Manager, Steven Diaz, 210-295-0936, steven.a.diaz4.civ@mail.
1.3.9 All waste chemicals and materials must be managed in
accordance with the JBSA-Lackland Hazardous Waste Management Plan. Email Hazardous Waste Program Manager for guidance, Noah Ramos, 210-671-0331, noah.ramos@us.af.mil.
1.3.9.1. Contractor shall submit copies of the manifests for materials hauled off Base.
1.3.9.2. Contractor shall submit Safety Data Sheets (SDS) for Asphalt used for re-surfacing. Note: Contractor shall note use the ingredient Coal Tar in asphalting operations.
1.3.9.3. Contractor shall submit an estimate of how much asphalt will be used in the project.
1.3.10 Bexar County Air Permit. An Air Permit is not required.
1.3.11. Golden Cheeked Warbler Habitat- The Contractor shall not perform any road construction next to the Golden Cheeked Warbler Habitat Area from March 1st to August 15th every year.
1.4 Location
The work is located on Lewis Valley Road between Cowgill Rd and County Rd, Camp Bullis, TX.
1.5 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
Verify existing utility locations, within area of work.
mailto:noah.ramos@us.af.mil
SECTION 01 11 00 Page 8
1.6 PERIOD OF PERFORMANCE
60 Calendar Days for Geotechnical, Surveying, Engineering Design and, Traffic Control Plan. 60 Calendar Days for JBSA to review and advertise Traffic Control Plan. 45 Calendar Days for milling, demolition and disposal of existing base course and subgrade. 30 Calendar days for demo of existing Stormwater Pipes and Headwalls. 30 calendar Days for construction of new Stormwater pipes and Safety End treatments. 45 Calendar days for Lime Stabilization, 45 calendar days for new Flexible Base construction, 30 Calendar days for new Surface Course Construction, 5 Calendar Days for raised reflective pavement markers. 10 Calendars for Project Closeout, 360 Calendar Days Total.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
-- End of Section --
ATTACHMENT 1
CYRB170018 Repair Lewis Valley Trail Sheet 1 of 1
STA 0+00 Begin Golden Cheeked Warbler Habitat at Lewis Valley Trail and Cowgill Rd Intersection. Begin 24-foot wide pavement
STA 90+82
End Golden Cheeked Warbler Habitat at Lewis Valley Trail and Trail Intersection
NO CONSTRUCTION AUTHORIZED
FROM MARCH 1 TO AUGUST 15
Between STA 0+00 and STA 90+82
MIAMI RD
LITTLE BIGHORN RD
ATTACHMENT 2 STA 90+82 to STA 191+14 CYRB170018 Repair Lewis Valley Trail
STA 90+82 Begin construction at Lewis Valley Trail and Trail Intersection
STA 191+14 End Construction Lewis Valley Trail and Oppenheimer Rd Intersection
CONSTRUCTION IS AUTHORIZED AT
ANY TIME Between STA 90+82 and STA
191+14 LEWIS VALLEY TRAIL
MIAMI RD
LITTLE BIGHORN RD
NO CONSTRUCTION AUTHORIZED
FROM MARCH 1 TO AUGUST 15
In RED AREA
NO CONSTRUCTION AUTHORIZED
FROM MARCH 1 TO AUGUST 15
IN RED AREA
STA 133+44 Begin 18-ft wide pavement at Trail Junction
TRAIL
ATTACHMENT 3
CYRB170018 Repair Lewis Valley Trail
STA 281+96 End Construction Lewis Valley Trail and County Rd Intersection End 18-foot wide pavement
NO CONSTRUCTION AUTHORIZED
FROM MARCH 1 TO AUGUST 15
Between STA 191+14 and STA 281+96
STA 191+14 Begin Construction Lewis Valley Trail and Oppenheimer Rd Intersection
LUNDY’S LANE
Replace Culvert Pipe And Headwall
SOW Attachment 2
DESCRIPTION RATE QUANTITY
SOILS
Standard Proctor - Trench Backfill Per Material Source 1
Standard Proctor - Subgrade Per Street 1
Densities 0 Trench Backfill Per 200 LF Trench 6-1 per trnch
Densities - Street Per 325 Square Yard 200
Densities - Driveways Per 2 Driveways N/A
FLEXIBLE BASE
Sieve Analysis Per 3,000 cubic yards 4
Atterburg Limits Per 3,000 cubic yards 4
Modified Proctor Per 3,000 cubic yards 4
L.A. Abrasion Per 3,000 cubic yards 4
CBR(Standard) Per Material Source 1
Densities of Compacted Base (Street/Pavement Repair) Per 325 square yards 200
Densities of Compacted Base (Curb & Gutter) Per 200 LF Curb & Gutter N/A
Wet Ball Mill Test Per Material Source 1
Triaxial Test Per Material Source 1
HOT MIX ASPHALTIC CONCRETE (HMAC)
Extraction Sieve Analysis Per 500 Tons or Day 18
Lab Density and Stability Per 500 Tons or Day 18
Theoretical Density (Rice Method) Per 500 Tons or Day 18
Temperature - During Laydown Continuous As Needed
Thickness - In Place (Core) Per 1,000 LF Street 28
%Theoretical Density - In Place (Core) Per 1,000 LF Street 28
CONCRETE (UNCONFINED COMPRESSION 7, 14, 28 DAYS)
Pavement 1 per 500 LF Street N/A
Curb and Gutter Per 500 LF Curb&Gutter N/A
Sidewaks and Curb Ramps Per 4,000 SF N/A
Driveways Per 2,500 SF N/A
Curb, Post, and Grate Inlets and Manhole Risers Per 6 each N/A
Headwalls Per Each N/A
Storm Sewer / San Sewer / Water Manholes (Cast-In-Place Per 2 Each N/A
Rip Rap, Aprons, Safety End Treatment (S.E.T.) Per 4,000 SF 12 N/A
Manhole Base/Footing Per 10 Each
CYRB170018 Repair Lewis Valley Trail ATTACHMENT 03E / TESTING SCHEDULE
1.1 REFERENCES
SECTION 01 14 00
WORK RESTRICTIONS
11/15
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. AIR FORCE (USAF)
AFI 40-201 (Incorporating Change 1, 17 December 2015) Radioactive Materials (RAM) Management
AFI 48-148 (20 NOVEMBER 2014) Ionizing Radiation Protection
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals list of Contract Personnel; G
Installation Access
1.3 SPECIAL SCHEDULING REQUIREMENTS
All medical and mission critical areas will remain in operation during the entire construction period. The contractor shall conduct his operations so as to cause the least possible interference with normal operations of the activity.
Permission to interrupt any Activity roads, railroads, and/or utility service must be requested in writing a minimum of 30 calendar days prior to the desired date of interruption.
1.4 CONTRACTOR ACCESS AND USE OF PREMISES
1.4.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and cleared for such entry. Mark all Contractor equipment for identification
Jan 14, 2020 SECTION 01 14 00 Page 1
SECTION 01 14 00 Page 2
1.4.1.1 Installation Access
Non DOD persons (Contractors, vendors, etc.) requiring entry to JBSA installation [Lackland] [Randolph] [Fort Sam Houston] [Camp Bullis] shall be sponsored by an authorized DBIDS registered DOD ID card holder.
Sponsors must notify the Security Forces Visitor Control Center for the installation that access is required no later than 10 days prior to the requested entry date. Sponsors or Authorizing Official must request the permit in writing or via email from a .mil address to the Visitor Control Center. An Application for the Installation Access Credential form (see Appendix D) will be submitted by the Sponsor or Official to the Pass and Registration Office. Contractor and vendor companies requiring access to Joint Base San Antonio shall provide the credential information for their employees to the sponsor in order to process the access.
All construction contractor employees shall have:
a. One form of picture identification
b. Provide personal (full name, date of birth, home address, and driver license number) and vehicle information.
The following is also required for passes 60 days or longer:
a. A memo from the construction company on company letterhead stating the reason for entry, contract number, project start and end date, and the location at JBSA of where the jobsite is located.
1.4.1.2 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.4.1.3 Government Housing Areas
a. Haul routes to and from constructions sites cannot go through the housing, residential areas.
b. When working inside a housing area, working hours are limited to 0800 (8 am) to 1600 (4 pm) unless otherwise approved by the Contracting Officer.
1.4.2 Emergency Response Requirement
Contractors reporting an emergency should provide the 9-1-1 dispatcher with the following information:
SECTION 01 14 00 Page 3
a. Building number, address or general location
b. Name
c. Phone number
d. Emergency information (cause of fire, explosion, natural gas leak, injuries, etc.)
e. Please, do not hang up the phone until directed by the 9-1-1 dispatcher.
IMPORTANT: If calling 9-1-1 from a mobile phone on any JBSA location you will be directed to the local 9-1-1 dispatcher. Advise the local dispatcher of your location (JBSA-Fort Sam Houston, JBSA-Lackland or JBSA-Randolph).
Immediately the local dispatcher will transfer the 9-1-1 phone call to a JBSA emergency dispatcher.
1.4.3 Radioactive Materials and Equipment (Use and Storage)
a. Non-Air Force agencies, including contractors, who intend to use, or store, radiation sources on Joint Base San Antonio, Fort Sam Houston and Camp Bullis must obtain proper authorization in accordance with the above references AFI 40-201 and AFI 48-148. Non-Air Force agencies will not use radiation sources on referenced locations without an approved Department of the Air Force Radiation Permit. Such equipment typically includes equipment for Soil Density Testing, Lead-Based Paint Analysis (X-Ray fluorescent analyzer), etc.
b. Non-Army agencies (including civilian contractors) require an Air Force
Radiation Permit(s) (AFRP) to use or possess ionizing radiation sources on an Air Force installation. For the purpose of this paragraph, ionizing radiation source means any source that, if held or owned by an Air Force organization, would require a specific NRC license or Air Force radiation authorization - ARA.
c. The non-Air Force applicant will apply by letter with supporting documentation through the Installation Radiation Safety Officer (RSO).
Submit the letter so that the installation representative receives the application at least thirty (30) days before the requested start date of the permit.
d. The Air Force radiation permit (AFRP) application will specify start and stop dates for the AFRP and describe for what purposes the applicant needs the AFRP. See the document in Appendix A for AFRP requirements and instructions to apply for a permit. The following information shall be submitted to the RSO for the AFRP request.
1) Brief Description of Proposed Activities
2) The applicant possesses a valid U.S. Nuclear Regulatory Commission
(NRC) Form 347 material license that allows the applicant to use the source as specified in the AFRP application.
3) The applicant possesses a valid Agreement State or Radioactive
Material License (Texas Department of Health, Bureau of Radiation Control) license that allows the applicant to use radioactive material (RAM) as specified in the AFRP application and the applicant has filed NRC Form 241, Report of Proposed Activities in Non-Agreement States, with the NRC in accordance with 10 CFR
150.20. A copy of the NRC Rom 241, must accompany the TRC Form 12-1. An AFRP issued under this circumstance will be valid for no more than 180 days in any calendar year.
SECTION 01 14 00 Page 4
4) Project Local Point of Contact: Name, Address, and Phone.
5) Company Radiation Safety Officer: Name, Address, and Phone.
6) Copy of Contractual Clause of the Air Force/Army Contract describing work to be performed and inclusive dates (from the contract)
7) Provide log of actual equipment usage to the JBSA-FSH RSO.
8) Leak test documentation for the equipment with the radioactive source(s).
9) Site map defining area where radioactive materials/equipment is to be used.
10) Radiation Safety Program to include standard operating procedures
(SOP), training program and designation of Radiation Protection/Safety Officer.
11) Written confirmation that the JBSA-FSH RSO can conduct periodic assessments and has authority to suspend contractor operations believed to be unsafe.
12) For naturally occurring or accelerator produce radioactive material (NORM/NARM) and machine-produced ionizing radiation sources, the applicant has an appropriate State authorization that allows the applicant to use the source as specified in the AFRP application or has in place a radiation safety program that complies with Air Force requirements.
e. All AFRPs will require applicants to remove all permitted sources from Air Force property by the end of the work day. (Ft. Sam Houston policy, no radiation producing equipment will be stored on Ft. Sam Houston and Camp Bullis property overnight).
f. Disposal of radioactive material (RAM) by non-Air Force agencies on Air
Force property is strictly prohibited. 3.2.3 Review, Approval/Disapproval. Review of the permit request and subsequent approval/disapproval requires approximately 30 days.
g. Submission of Application. Submit three copies of the application with the required supporting documentation to 502nd Air Base Wing Safety Office, Safety Point of Contact:
JBSA Installation Radiation Protection Officer (RSO) Mr. Ken Talley 59th Medical Wing/SGPB 59 MDW Office Telephone No: 210.671-7061 E-mail: kenneth.talley@us.af.mil
1.4.4 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 14 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract mailto:kenneth.talley@us.af.mil
SECTION 01 14 00 Page 5 number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours...
1.4.5 Permits and Requests
All permit requests must include at minimum the following:
a. Site Map (8" x 11" or 8" x 14") 5 complete copies
b. 100% Construction Drawings 5 complete copies
c. Project Name and Number
d. Contractor & Subcontractor Name
e. Brief Description of Work - Identify all buildings and/or facilities possibly affected.
f. Desired Date for Work to Begin
g. Estimated Duration of Work
h. 14 Day Advance Notice minimum, unless otherwise noted.
i. Contractor's Representative Contact Information
1.4.5.1 Digging Permits / Utility Locate
a. Digging permits must be obtained prior to prior to any digging, drilling or any excavation work.
b. Digging permit /utility locates are available by submitting the completed US Air Force Form 103 located in Appendix A to the 502 CES Construction Manager.
c. Contractor to allow (14) calendar days for Government review of digging permit requests. A digging permit for a specified area of excavation expires 30 days after the issue date; the contractor shall re-apply for a new permit to perform excavation in the area if the excavation was not started within the 30-day period.
d. Permits will identify all underground utilities within 5 feet of the designated area. Contractor shall be responsible for all repairs, costs, and damages due to excavating without permit or damaging an identified utility.
1.4.5.2 Utility Outage Permit
a. Contractor shall complete and submit a written request 14 days in advance of the requested utility outage to CES Utility Manager through the 502 CES Construction Manager. The request shall include the utility service to be affected, proposed date, proposed time, and outage duration. Form 103 included in Appendix A can also be used for the request.
b. Contractor shall be responsible to coordinate with CPS Energy about any energy or gas outage request. This coordination is separate than the government coordination.
SECTION 01 14 00 Page 6
c. Provide CES Construction Manager a copy of the written Utility Outage request.
d. After submitting the request to the government, the contractor shall receive approval from the government prior to schedule a utility outage.
1.4.5.3 Hot Work Permits
Under no circumstances shall hot work operations start without a hot work permit.
All welding and cutting operations shall be performed in accordance with National Fire Protection Association NFPA Standard 5lB Fire Prevention during Welding, Cutting, and Other Hot Work. Contact the site specific JBSA fire department to request an AF Form 592 USAF Welding, Cutting and Brazing Permit. Ensure a copy of the AF Form 592 is located on site. Phone numbers are:
JBSA-Ft Sam Houston Fire Prevention
(210) 221-2727
JBSA-Lackland Fire Prevention (210) 671-2921
JBSA-Randolph Fire Prevention
(210)
652-6915
Permits expire in 30 days. If work will extend beyond 30 day period the contractor shall contact JBSA Fire and Emergency Services to re-issue a new permit.
1.4.5.4 Road Closure Approval Requests
a. Road closings will not be permitted without approval. To get approval for a proposed road closure contractor shall submit a traffic control plan to the 502 CES Construction manager prior to anticipated need for closure
b. The Contractor traffic control plan will include each section of road that will be worked on or impacted as a result of this contract. The traffic control plan shall be in accordance with "Traffic Controls for Street and Highway Construction and Maintenance Operations" of the latest edition of the "Texas Manual on Uniform Traffic Control Devices."
c. Contractor will provide traffic control signs and barricades for all street widening and extensions. At least one lane of traffic must be maintained at all times.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
SECTION 01 30 00 Page 1
1.1 SUBMITTALS
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
08/15 submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section 01 33
00 SUBMITTAL PROCEDURES:
View Location Map; G
Progress and Completion Pictures; G
1.2 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.3 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start and at completion of the Contract. Digital photographs, .jpeg, shall be provided to the Contracting Officer for unrestricted use by the Government.
1.4 MINIMUM INSURANCE REQUIREMENTS
Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage:
Comprehensive general liability: $500,000 per occurrence
b. Automobile liability: $200,000 per person, $500,000 per occurrence for bodily injury, $20,000 per occurrence for property damage
c. Workmen's compensation as required by Federal and State workers' compensation and occupational disease laws.
d. Employer's liability coverage of $100,000, except in States where workers compensation may not be written by private carriers,
e. Others as required by Texas law.
1.5 CONTRACTOR SPECIAL REQUIREMENTS
Accomplish all contract requirements of Section assigned to the directly with a first tier subcontractor.
SECTION 01 30 00 Page 2
1.6 SUPERVISION
1.6.1 Minimum Communication Requirements
Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.
The Project Manager in this context shall mean the individual with the responsibility for the overall management of the project and the Project Superintendent shall mean the individual with the responsibility for quality and production. Both the Project Manager and Project Superintendent are subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders shall be made the subject of claim for extension of time for excess costs or damages by the Contractor.
Approval of Project Manager and on-site Project Superintendent is required prior to start of construction. Provide resumes for the proposed Project Manager and on-site Project Superintendent describing their experience with references and qualifications to the Contracting Officer for approval. The Contracting Officer reserves the right to interview the proposed Project Manager and on-site Project Superintendent at any time in order to verify the submitted qualifications.
1.7 PRECONSTRUCTION CONFERENCE
After award of the TO contracts but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work shall also attend.
1.8 PARTNERING
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key
SECTION 01 30 00 Page 3
Personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.
The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.
1.9 AVAILABILITY OF CADD DRAWING FILES
After award and upon request, the electronic "Computer-Aided Drafting and Design (CADD)" drawing files will only be made available to the Contractor for use in preparation of construction data related to the referenced contract subject to the following terms and conditions.
Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic CADD drawing files are not construction documents.
Differences may exist between the CADD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CADD files, nor does it make representation to the compatibility of these files with the Contractors hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The Contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.
If the Contractor uses, duplicates and/or modifies these electronic CADD files for use in producing construction drawings and data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.
1.10 ELECTRONIC MAIL (E-MAIL) ADDRESS
The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the
SECTION 01 30 00 Page 4
Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc. Multiple email address will not be allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.
Not Used
SECTION 131 19.00 44 Page 1
SECTION 01 31 19.00 44
PROJECT MEETING
11/15
1.1 PRECONSTRUCTION CONFERENCE
Approximately three weeks after award of the contract and prior to the start of any construction work an authorized representative of the Contracting Officer will schedule and conduct a preconstruction conference.
The Contractor's Project Manager, Superintendent, and Quality Control Manager will attend this meeting. The Contractor is encouraged to have an officer of his company and representation from his sub-contractors at this conference. This conference will be held at the location specified by the Contracting Officer's authorized representative. Minutes of the meeting will be prepared by the Government and signed by both the Contractor and the Contracting Officer. The minutes shall become a part of the contract file.
1.1.1 Start of Construction Work
If the Contractor has submitted the Accident Prevention (Safety) Plan, Quality Control Plan, Environmental Protection Plan for review prior to this meeting, these may be accepted in to or accepted with comments at the conference. Construction work will not proceed until after this meeting has been held, the plans noted above have been accepted, and the Notice to Proceed has been received and acknowledged by the Contractor.
1.2 OTHER MEETINGS
Construction Quality Control meetings and conferences are specified in Section 01 45 00.00 20 QUALITY CONTROL. Other meetings are specified in various Division 1 and technical sections.
PART 2 PRODUCTS NOT USED
PART 3 EXECUTION NOT USED
] -- End of Section --
SECTION 132 19.00 44 Page 1
1.1 Qualifications
SECTION 01 32 01.00 10
PROJECT SCHEDULE
02/15
The Contractor shall designate an authorized representative who shall be responsible for the preparation of all required project schedule reports.
1.2 SUBMITTALS
Government approval is required for submittals with a "GA" designation;
submittals having a "FIO" designation are for information only. When used, a designation following the "GA" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 30 00 SUBMITTAL PROCEDURES:
Project Schedule CPM; GA
PART 2 NOT USED
3.1 GENERAL REQUIREMENTS
A Project Schedule as described below shall be prepared. The scheduling of construction shall be the responsibility of the Contractor. Contractor management personnel shall actively participate in its development.
Subcontractors and suppliers, subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. The approved Project Schedule shall be used to measure the progress of the work, to aid in evaluating time extensions, and to provide the basis of all progress payments.
3.2 BASIS FOR PAYMENT
The schedule shall be the basis for measuring Contractor progress. Lack of an approved schedule or scheduling personnel will result in an inability of the Contracting Officer to evaluate Contractor's progress for the purposes of payment. Failure of the Contractor to provide all information, as specified below, shall result in the disapproval of the entire Project Schedule submission and the inability of the Contracting Officer to evaluate Contractor progress for payment purposes. In the case where Project Schedule revisions have been directed by the Contracting Officer and those revisions have not been included in the Project Schedule, the Contracting Officer may hold retainage up to the maximum allowed by Contract, each payment period, until revisions to the Project Schedule have been made.
SECTION 01 32 01.00 10 Page 2
3.3 Project Schedule
The computer software system utilized by the Contractor to produce the Project Schedule shall be capable of providing all requirements of this specification. Failure of the Contractor to meet the requirements of this specification shall result in the disapproval of the schedule. Manual methods used to produce any required information shall require approval by the Contracting Officer.
3.3.1 AF IMT 3064
Use of the AF IMT 3064 will be the normal requirement for contractor construction schedules for most of the task orders issued under this contract and shall include the required items, submittals, level of detail and contract requirements listed below for critical path method activities (Work Elements), in this paragraph C. through F and as detailed in the Instructions to Contractors on the reverse side of the AF IMT 3064, Form..
3.3.2 Use of the Critical Path Method
The Critical Path Method (CPM) of network calculation shall be used to generate the Project Schedule. The Contractor shall provide the Project Schedule in the Precedence Diagram Method (PDM).
3.3.3 Level of Detail Required
The Project Schedule shall include an appropriate level of detail. Failure to develop or update the Project Schedule or provide data to the Contracting Officer at the appropriate level of detail, as specified by the Contracting Officer, shall result in the disapproval of the schedule. The Contracting Officer will use, but is not limited to the following conditions to determine the appropriate level of detail to be used in the Project Schedule:
a. Activity Durations: Contractor submissions shall follow the direction of the Contracting Officer regarding reasonable activity durations.
Reasonable durations are those that allow the progress of activities to be accurately determined between payment periods (usually less than 2 percent of all non-procurement activities' Original Durations are greater than 20 days).
b. Procurement Activities: Tasks related to the procurement of long lead materials or equipment shall be included as separate activities in the project schedule. Long lead materials and equipment are those materials that have a procurement cycle of over 90 days. Examples of procurement process activities include, but are not limited to: submittals, approvals, procurement, fabrication, and delivery.
c. Critical Activities: The following activities shall be listed as separate line activities on the Contractor's project schedule:
i. Pre-final inspection.
ii. Correction of punch list from pre-final inspection.
iii. Final inspection.
iv. Construction phasing.
d. Government Activities: Government and other agency activities that
SECTION 01 32 01.00 10 Page 3 could impact progress shall be shown. These activities include, but are not limited to: approvals, approvals, design reviews, environmental permit approvals by State regulators, inspections, and Notice to Proceed (NTP) for phasing requirements.
e. Responsibility: All activities shall be identified in the project schedule by the party responsible to perform the work. Responsibility includes, but is not limited to, the subcontracting firm, contractor work force, or government agency performing a given task. Activities shall not belong to more than one responsible party. The responsible party for each activity shall be identified by the Responsibility Code.
a. Work Areas: All activities shall be identified in the project schedule by the work area in which the activity occurs. Activities shall not be allowed to cover more than one work area. The work area of each activity shall be identified by the Work Area Code.
b. Modification or Claim Number: Any activity that is added or changed by contract modification or used to justify claimed time shall be identified by a mod or claim code that changed the activity. Activities shall not belong to more than one modification or claim item. The modification or claim number of each activity shall be identified by the Mod or Claim Number.
Whenever possible, changes shall be added to the schedule by adding new activities. Existing activities shall not normally be changed to reflect modifications.
c. Feature of Work: All activities shall be identified in the project schedule according to the feature of work to which the activity belongs. Feature of work refers, but is not limited to, a work breakdown structure for the project. The feature of work for each activity shall be identified by the Feature of Work Code.
f. Scheduled Project Completion: The schedule interval shall extend from NTP to the Contract completion date.
a. Project Start Date: The schedule shall start no earlier than the date on which the NTP was acknowledged. The Contractor shall include as the first activity in the project schedule an activity called "Start Project". The "Start Project" activity shall have an "ES" constraint date equal to the date that the NTP was acknowledged, and a zero day duration.
b. Constraint of Last Activity: Completion of the last activity in the schedule shall be constrained by the contract completion date. Calculation on project updates shall be such that if the early finish of the last activity falls after the contract completion date, then the float calculation shall reflect a negative float on the critical path. The Contractor shall include as the last activity in the project schedule an activity called "End Project". The "End Project" activity shall have an "LF" constraint date equal to the completion date for the project, and a zero day duration.
c. Early Project Completion: In the event the project schedule shows completion of the project prior to the contract completion date, the Contractor shall identify those activities that are
SECTION 01 32 01.00 10 Page 4 accelerated and/or those activities that are scheduled in parallel to support the Contractor's "early" completion. Contractor shall specifically address each of the activities noted in the narrative report at every project schedule update period to assist the Contracting Officer in evaluating the Contractor's ability to actually complete prior to the Contract period.
g. Interim Completion Dates: Contractually specified interim completion dates shall also be constrained to show negative float if the early finish date of the last activity in that phase falls after the interim completion date.
d. Start Phase: The Contractor shall include as the first activity for a project phase an activity called "Start Phase X" where "X" refers to the phase of work. The "Start Phase X" activity shall have an "ES" constraint date equal to the date on which the NTP was acknowledged, and a zero day duration.
e. End Phase: The Contractor shall include as the last activity in a project phase an activity called "End Phase X" where "X" refers to the phase of work. The "End Phase X" activity shall have an "LF" constraint date equal to the completion date for the project, and a zero day duration.
f. Phase X: The Contractor shall include a hammock type activity for each project phase called "Phase X" where "X" refers to the phase of work. The "Phase X" activity shall be logically tied to the earliest and latest activities in the phase.
h. Default Progress Data Disallowed: Actual Start and Finish dates shall not be automatically updated by default mechanisms that may be included in CPM scheduling software systems. Actual Start and Finish dates on the CPM schedule shall match those dates provided from Contractor Quality Control Reports.