Attachment 12 -UFC_1_200_01.pdf
PDF 3 MB Posted
- Attached to
- Repair Dorm B4323 Federal contract opportunity
- Solicitation number
- FA4608-21-R-0004
About this file
This solicitation is for repair work on dormitory building 4323 at Barksdale Air Force Base in Louisiana. The contractor will remove and replace interior finishes in dorm rooms, including wall coverings, flooring, paint, ceilings, and doors. A site visit will be held on November 13, 2020, with an RSVP required by November 5. The period of performance is negotiable but listed as 336 calendar days. The estimated price range for the project is $5-10 million. This is a woman-owned small business set-aside. Responses are due by the date listed in the solicitation.
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UFC 1-200-01
8 October 2019
Change 1, 1 Oct 2020
UNIFIED FACILITIES CRITERIA (UFC)
APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED
DOD BUILDING CODE
FA4608-21-R-0004
Attachment 12
Pg 1 of 77
Change 1, 1 Oct 2020
UNIFIED FACILITIES CRITERIA (UFC)
DOD BUILDING CODE
Any copyrighted material included in this UFC is identified at its point of use.
Use of the copyrighted material apart from this UFC must have the permission of the copyright holder.
Indicate the preparing activity beside the Service responsible for preparing the document.
U.S. ARMY CORPS OF ENGINEERS
NAVAL FACILITIES ENGINEERING COMMAND (Preparing Activity)
AIR FORCE CIVIL ENGINEER CENTER
Record of Changes (changes are indicated by \1\ ... /1/)
Change No. Date Location 1 1-5.1, 1-5.2, 1-5.3 revised terms; 1-6.2 clarified use of
IRC; 1-6.3.1.1 corrections to core UFC list: delete 3-310- 04, 3-540-02, 3-230-03; add 3-301-02, 3-190-06; 2-16 update reference; 4-14 revised fifth bullet; Appendix C References: various updates.
This UFC supersedes UFC 1-200-01, dated 20 June 2016, with Change 2, dated 01 Nov 2018.
FA4608-21-R-0004
Pg 2 of 77
FOREWORD
The Unified Facilities Criteria (UFC) system is prescribed by MIL-STD 3007G and provides planning, design, construction, sustainment, restoration, and modernization criteria, and applies to the Military Departments, the Defense Agencies, and the DoD Field Activities in accordance with USD (AT&L) Memorandum dated 29 May 2002. UFC will be used for all DoD projects and work for other customers where appropriate. All construction outside of the United States is also governed by Status of Forces Agreements (SOFA), Host Nation Funded Construction Agreements (HNFA), and in some instances, Bilateral Infrastructure Agreements (BIA).
Therefore, the acquisition team must ensure compliance with the most stringent of the UFC, the SOFA, the HNFA, and the BIA, as applicable.
UFC are living documents and will be periodically reviewed, updated, and made available to users as part of the Services’ responsibility for providing technical criteria for military construction. Headquarters, U.S. Army Corps of Engineers (HQUSACE), Naval Facilities Engineering Command (NAVFAC), and Air Force Civil Engineer Center (AFCEC) are responsible for administration of the UFC system. Defense agencies should contact the preparing service for document interpretation and improvements. Technical content of UFC is the responsibility of the cognizant DoD working group. Recommended changes with supporting rationale may be sent to the respective DoD working group by submitting a Criteria Change Request (CCR) via the Internet site listed below.
UFC are effective upon issuance and are distributed only in electronic media from the following source:
• Whole Building Design Guide web site http://www.wbdg.org/ffc/dod.
Refer to UFC 1-200-01, DoD Building Code, for implementation of new issuances on projects.
AUTHORIZED BY:
GEORGE O. LEA JR P.E. CCM
FCMAA NAC
R. DAVID CURFMAN, P.E.
Chief Engineer
Chief Military Engineering Branch Engineering and Construction Division
Naval Facilities Engineering Command
U.S. Army Corps of Engineers
NANCY J. BALKUS, PE, SES
Deputy Director of Civil Engineers DCS Logistics, Engineering & Force Protection (HAF/A4C) HQ United States Air Force
MICHAEL McANDREW Deputy Assistant Secretary of Defense (Facilities Management) Office of the Assistant Secretary of Defense (Sustainment)
FA4608-21-R-0004
Attachment 12
Pg 3 of 77 http://www.wbdg.org/pdfs/ufc_implementation.pdf http://www.wbdg.org/ffc/dod
UNIFIED FACILITIES CRITERIA (UFC)
REVISION SUMMARY SHEET
Document: UFC 1-200-01, DoD BUILDING CODE
Superseding: UFC 1-200-01, DoD BUILDING CODE (GENERAL BUILDING REQUIREMENTS), dated 20 June 2016, with Change 2, dated 01 Nov 2018
Description: This update to UFC 1-200-01 represents the Tri-Services effort to bring uniformity to the military use of non-government model building codes. Technical representatives of each of the \1\three/1/ Services developed requirements in this document to implement the use of the 2018 IBC and 2018 IEBC consistent with the scope of current military requirements and procedures. This revision of UFC 1-200-01 contains modifications in the following areas:
• DoD criteria guidance approved as late as 1 September 2019 has been cited.
Reasons for Document:
• This document replaces 2015 IBC with the use of 2018 IBC revised and replaced in 2018 by the ICC.
• This document replaces 2015 IEBC with the use of 2018 IEBC revised and replaced in 2018 by the ICC.
Impact:
• This document reduces interpretation and ambiguity that could lead to design and construction conflicts.
• Costs of DoD facilities are not expected to increase as a result of this revision.
Unification Issues:
• There are no unification issues.
FA4608-21-R-0004
Pg 4 of 77 i
TABLE OF CONTENTS
INTRODUCTION
1-1 BACKGROUND
1-2 PURPOSE AND SCOPE
1-3 APPLICABILITY
1-3.1 Implementation, Administration, and Enforcement
1-3.2 Levels of Construction
1-3.3 Waivers and Exemptions
1-3.4 UFC Hierarchy
1-3.5 Facilities in Support of Military Operations
1-4 OVERARCHING CRITERIA OR REGULATORY REQUIREMENTS
1-4.1 Vending Facilities for the Blind
1-4.2 Nursing and Lactation Rooms
1-5 UFC AUTHORITIES
1-5.1 Engineering Senior Executive Panel
1-5.2 Component Technical Representative
1-5.3 Building Official / Authority Having Jurisdiction
1-6 GENERAL BUILDING REQUIREMENTS
1-6.1 Building Codes
1-6.2 Referenced Codes and Substitutions
1-6.3 Other Criteria
1-7 CYBERSECURITY
1-8 NON-GOVERNMENT STANDARD MODIFICATIONS
1-9 GLOSSARY
1-10 REFERENCES
MODIFICATIONS TO IBC
2-1 CHAPTER 1 – SCOPE AND ADMINISTRATION [SUPPLEMENT]
2-1.1 Section 101 – GENERAL
2-1.2 Section 102 – APPLICABILITY
2-1.3 Section 103 – DEPARTMENT OF BUILDING SAFETY [Deletion]
2-1.4 Section 104 – DUTIES AND POWERS OF BUILDING OFFICIAL
2-1.5 Section 105 – PERMITS [Deletion]
FA4608-21-R-0004
Pg 5 of 77 ii
2-1.6 Section 106 – FLOOR AND ROOF DESIGN LOADS [Deletion]
2-1.7 Section 107 – SUBMITTAL DOCUMENTS [Deletion]
2-1.8 Section 108 – TEMPORARY STRUCTURES AND USES [Deletion]. . 15
2-1.9 Section 109 – FEES [Deletion]
2-1.10 Section 111 – CERTIFICATE OF OCCUPANCY [Deletion]
2-1.11 Section 113 – BOARD OF APPEALS [Deletion]
2-1.12 Section 114 – VIOLATIONS [Deletion]
2-1.13 Section 115 – STOP WORK ORDER [Deletion]
2-1.14 Section 116 – UNSAFE STRUCTURES AND EQUIPMENT [Deletion]
2-2 CHAPTER 2 – DEFINITIONS [SUPPLEMENT]
2-3 CHAPTER 3 – USE AND OCCUPANCY CLASSIFICATION
[SUPPLEMENT]
2-4 CHAPTER 4 – SPECIAL DETAILED REQUIREMENTS BASED ON
USE AND OCCUPANCY [SUPPLEMENT]
2-5 CHAPTER 5 – GENERAL BUILDING HEIGHTS AND AREAS
[SUPPLEMENT]
2-5.1 Section 506 – BUILDING AREA
2-6 CHAPTER 6 – TYPES OF CONSTRUCTION [SUPPLEMENT]
2-7 CHAPTER 7 – FIRE AND SMOKE PROTECTION FEATURES
[SUPPLEMENT]
2-8 CHAPTER 8 – INTERIOR FINISHES [REPLACEMENT]
2-9 CHAPTER 9 – FIRE PROTECTION SYSTEMS [REPLACEMENT]
2-10 CHAPTER 10 – MEANS OF EGRESS [REPLACEMENT]
2-11 CHAPTER 11 – ACCESSIBILITY [REPLACEMENT]
2-12 CHAPTER 12 – INTERIOR ENVIRONMENT [SUPPLEMENT]
2-12.1 Section 1203 – TEMPERATURE CONTROL
2-12.2 Section 1206 – SOUND TRANSMISSION
2-12.3 Section 1207 – INTERIOR SPACE DIMENSIONS
2-13 CHAPTER 13 – ENERGY EFFICIENCY [REPLACEMENT]
2-14 CHAPTER 14 – EXTERIOR WALLS [SUPPLEMENT]
2-14.1 Section 1402 – PERFORMANCE REQUIREMENTS
2-14.2 Section 1406 – METAL COMPOSITE MATERIALS (MCM)
2-15 CHAPTER 15 – ROOF ASSEMBLIES AND ROOFTOP
STRUCTURES [SUPPLEMENT]
FA4608-21-R-0004
Pg 6 of 77 iii
2-16 CHAPTER 16 – STRUCTURAL DESIGN [SUPPLEMENT]
2-16.1 Section 1604 – GENERAL DESIGN REQUIREMENTS
2-16.2 Section 1612 – FLOOD LOADS [Supplement]
2-17 CHAPTER 17 – SPECIAL INSPECTIONS AND TESTS
[SUPPLEMENT]
2-17.1 Section 1701 – GENERAL
2-17.2 Section 1704 – SPECIAL INSPECTIONS AND TESTS, CONTRACTOR RESPONSIBILITY AND STRUCTURAL
OBSERVATION
2-18 CHAPTER 18 – SOILS AND FOUNDATIONS [SUPPLEMENT]
2-18.1 Section 1804 – EXCAVATION, GRADING, AND FILL
2-19 CHAPTER 19 – CONCRETE [SUPPLEMENT]
2-20 CHAPTER 20 – ALUMINUM [SUPPLEMENT]
2-21 CHAPTER 21 – MASONRY [SUPPLEMENT]
2-22 CHAPTER 22 – STEEL [SUPPLEMENT]
2-23 CHAPTER 23 – WOOD [SUPPLEMENT]
2-23.1 Section 2301.4 Composite Wood [Addition]
2-23.2 Section 2303 – MINIMUM STANDARDS AND QUALITY
2-24 CHAPTER 24 – GLASS AND GLAZING [SUPPLEMENT]
2-25 CHAPTER 25 – GYPSUM BOARD, GYPSUM PANEL PRODUCTS,
AND PLASTER
2-26 CHAPTER 26 – PLASTIC [SUPPLEMENT]
2-26.1 Section 2603 – FOAM PLASTIC INSULATION
2-27 CHAPTER 27 – ELECTRICAL [SUPPLEMENT]
2-28 CHAPTER 28 – MECHANICAL SYSTEMS [SUPPLEMENT]
2-29 CHAPTER 29 – PLUMBING SYSTEMS [SUPPLEMENT]
2-30 CHAPTER 30 – ELEVATORS AND CONVEYING SYSTEMS
[SUPPLEMENT]
2-31 CHAPTER 31 – SPECIAL CONSTRUCTION
2-32 CHAPTER 32 – ENCROACHMENTS INTO THE PUBLIC RIGHT-OF-
WAY
2-33 CHAPTER 33 – SAFEGUARDS DURING CONSTRUCTION
[SUPPLEMENT]
2-34 CHAPTER 34 – RESERVED [DELETION]
2-35 CHAPTER 35 – REFERENCED STANDARDS [SUPPLEMENT]
FA4608-21-R-0004
Pg 7 of 77 iv
2-36 APPENDICES [DELETION]
MODIFICATIONS TO IEBC
3-1 CHAPTER 1 – SCOPE AND ADMINISTRATION
3-1.1 Section 101 – GENERAL
3-1.2 Section 102 – APPLICABILITY
3-1.3 Section 103 – DEPARTMENT OF BUILDING SAFETY [Deletion]
3-1.4 Section 104 – DUTIES AND POWERS OF CODE OFFICIAL [Deletion]
3-1.5 Section 105 – PERMITS [Deletion]
3-1.6 Section 106 – CONSTRUCTION DOCUMENTS [Deletion]
3-1.7 Section 107 – TEMPORARY STRUCTURES AND USES [Deletion]. . 25
3-1.8 Section 108 – FEES [Deletion]
3-1.9 Section 110 – CERTIFICATE OF OCCUPANCY [Deletion]
3-1.10 Section 112 – BOARD OF APPEALS [Deletion]
3-1.11 Section 113 – VIOLATIONS [Deletion]
3-1.12 Section 114 – STOP WORK ORDER [Deletion]
3-1.13 Section 115 – UNSAFE BUILDINGS AND EQUIPMENT [Deletion]
3-1.14 Section 116 – EMERGENCY MEASURES [Deletion]
3-1.15 Section 117 – DEMOLITION [Deletion]
3-2 CHAPTER 2 – DEFINITIONS [SUPPLEMENT]
3-3 CHAPTER 3 – PROVISIONS FOR ALL COMPLIANCE METHODS
[SUPPLEMENT]
3-4 CHAPTER 4 – REPAIRS [SUPPLEMENT]
3-4.1 Section 401 – GENERAL
3-5 CHAPTER 5 – PRESCRIPTIVE COMPLIANCE METHOD
[SUPPLEMENT]
3-5.1 Section 502 – ADDITIONS
3-5.2 Section 503 – ALTERATIONS
3-5.3 Section 507 – HISTORIC BUILDINGS
3-6 CHAPTER 6 – CLASSIFICATION OF WORK [SUPPLEMENT]
3-7 CHAPTER 7 – ALTERATIONS – LEVEL 1 [SUPPLEMENT]
3-7.1 Section 701 – GENERAL
3-8 CHAPTER 8 – ALTERATIONS – LEVEL 2 [SUPPLEMENT]
3-9 CHAPTER 9 – ALTERATIONS – LEVEL 3 [SUPPLEMENT]
FA4608-21-R-0004
Pg 8 of 77 v
3-10 CHAPTER 10 – CHANGE OF OCCUPANCY [SUPPLEMENT]
3-11 CHAPTER 11 – ADDITIONS [SUPPLEMENT]
3-12 CHAPTER 12 – HISTORIC BUILDINGS [SUPPLEMENT]
3-12.1 Section 1201 – GENERAL
3-13 CHAPTER 13 – PERFORMANCE COMPLIANCE METHODS
[SUPPLEMENT]
3-13.1 Section 1301 – GENERAL
3-13.2 Section 1301 – GENERAL
3-14 CHAPTER 14 – RELOCATED OR MOVED BUILDINGS
[SUPPLEMENT]
3-15 CHAPTER 15 – CONSTRUCTION SAFEGUARDS [SUPPLEMENT]
3-16 CHAPTER 16 – REFERENCED STANDARDS [SUPPLEMENT]
3-17 APPENDICES [DELETION]
3-18 RESOURCES [DELETION]
CORROSION PREVENTION AND CONTROL
4-1 GENERAL
4-1.1 Definition of Corrosion
4-1.2 Identification of Project Environmental Severity Classification
4-1.3 Corrosion Prone Locations
4-1.4 Requirements for Corrosion Prone Locations
4-1.5 Design Geometries
4-1.6 Environmental Severity Factors
4-1.7 System, Component, and Material Design Requirements
APPENDIX A ESC FOR DOD LOCATIONS
APPENDIX B GLOSSARY
B-1 ACRONYMS
B-2 DEFINITION OF TERMS
APPENDIX C REFERENCES
TABLES
Table 1-1 Policy Related to Physical Security
ESC for United States, Its Territories and Possessions
ESC for Outside United States, Its Territories and Possessions
FA4608-21-R-0004
Pg 9 of 77 vi
This Page Intentionally Left Blank
Pg 10 of 77
INTRODUCTION
1-1 BACKGROUND.
Unified Facilities Criteria (UFC) provide common requirements across DoD for safety, sustainability, durability, and functionality for DoD facilities. UFC incorporate a combination of consensus building codes, DoD-defined technical and user requirements, and applicable statutory and regulatory requirements.
1-2 PURPOSE AND SCOPE
UFC 1-200-01 represents the foundational document of the UFC program in providing general building requirements and overarching criteria, establishing the use of consensus building codes and standards, establishing criteria implementation rules and protocols (including core UFC), and identifying unique military criteria. In accordance with the authority in MIL-STD-3007G, UFC are prepared by DoD committees called Discipline Working Group (DWG), and are published by the Military Services under the authority of the Engineering Senior Executive Panel (ESEP), comprised of the following:
• Deputy Assistant Secretary of Defense (Facilities Management) Office of the Assistant Secretary of Defense (Sustainment)
• Chief, Engineering and Construction Division, Headquarters United States Army Corps of Engineers (HQ USACE)
• Chief Engineer, Naval Facilities Engineering Command (NAVFAC)
• Department of the Air Force, Deputy Director of Civil Engineers DCS Logistics, Engineering & Force Protection
1-3 APPLICABILITY.
This UFC applies to the planning, design, construction, sustainment, restoration, and modernization of DoD-owned facilities. It is applicable to all methods of project delivery and levels of construction as defined below. For facilities supporting military operations see Paragraph 1-3.5.
1-3.1 Implementation, Administration, and Enforcement.
UFC are effective upon issuance for projects as follows:
• Design-Bid-Build projects that have not proceeded beyond 35% design completion.
• Design-Build projects that have not proceeded beyond date of Request for Proposal (RFP) issuance. When an RFP is issued in multiple phases or steps use the date of the last phase of the RFP issuance.
FA4608-21-R-0004
Pg 11 of 77
• Projects that have a delay, either planned or unintentional, of more than 18 months between design completion and the solicitation of offers for construction must be re-evaluated to determine if any design revision is necessary due to changes in criteria (including codes and standards) or site infrastructure (for example, water supply for fixed fire suppression systems, water for hose stream allowances, or fire department vehicle access). Note: The evaluation must also include retroactive requirements that have been included in the new editions of the criteria.
1-3.2 Levels of Construction
1-3.2.1 Permanent Construction.
Buildings and facilities designed and constructed to serve a life expectancy of more than 25 years.
1-3.2.2 Semi-permanent Construction.
Buildings and facilities designed and constructed to serve a life expectancy of more than 5 years, but less than 25 years. This construction level is typically only used for support of military operations. Expediency of construction and material availability may be a factor. Facilities are intended to have a more enduring presence with operational characteristics and functional performance similar to permanent construction.
Maintainability of finishes and systems must be commensurate with facility life expectancy and available maintenance capabilities. A moderate level of energy and water efficiency must be considered.
1-3.2.3 Temporary Construction.
Buildings and facilities designed and constructed to serve a life expectancy of five years or less using low cost construction. Temporary construction typically cannot be economically converted to a higher level of construction. Temporary facilities have limited flexibility for conversion and re-use.
1-3.3 Waivers and Exemptions.
A waiver provides authority to deviate from a criteria requirement for a specific period, typically 12 months. An exemption provides authority to deviate from a requirement indefinitely. Refer to MIL-STD-3007 for the waiver and exemption request and approval process. When additional coordination for waivers or exemptions is required due to a regulatory or functional authority, the affected criteria document will include additional information.
1-3.4 UFC Hierarchy.
UFC 1-200-01 is the overarching document for buildings and facilities used by DoD.
UFC 1-200-01 directs the use of the International Building Code® (IBC), the International Existing Building Code® (IEBC), Core UFC, other UFC as applicable to the
FA4608-21-R-0004
Pg 12 of 77 building, facility, structure, or system, and Facility Criteria (FC) as they pertain to the applicable DoD Component.
1-3.4.1 UFC 3- Series.
The UFC 3- Series and FC 3- Series (simply referred to as UFC 3- Series) provide discipline specific criteria requirements for the various engineering disciplines.
• If conflict occurs between a UFC 3- Series and UFC 3-600-01, the requirements of UFC 3-600-01 take precedence.
• If conflict occurs between two UFC within the UFC 3- Series, the requirements of the UFC that is more detailed pertaining to that specific building, facility, structure, or system take precedence.
1-3.4.2 UFC 4- Series.
The UFC 4- Series and FC 4- Series (simply referred to as UFC 4- Series) provide requirements for multi-disciplinary and facility-specific design.
• If conflict occurs between a UFC 4- Series facility type UFC and UFC 3- 600-01, the requirements of UFC 4- Series facility type UFC take precedence.
• If conflict occurs between two UFC within the UFC 4- Series, the requirements of the UFC that is more detailed pertaining to that specific building, facility, structure, or system take precedence.
• If conflict occurs between a UFC 4- Series and a UFC 3- Series, the requirements of the UFC 4- Series take precedence.
1-3.5 Facilities in Support of Military Operations.
The following UFC are intended for use outside of the United States and its territories and possessions. In addition, Joint Publication (JP) 3-0, Joint Operations, provides typical examples of military operations where uses of these UFC are appropriate.
1-3.5.1 UFC 1-201-01.
Use UFC 1-201-01 for design of non-permanent facilities constructed for use by DoD personnel in support of military operations.
1-3.5.2 UFC 1-201-02.
Use UFC 1-201-02 to assess existing facilities for life safety and habitability for use by DoD personnel in support of military operations.
1-3.5.3 UFC 1-202-01.
Use UFC 1-202-01 for design of host nation facilities that support military operations.
FA4608-21-R-0004
Pg 13 of 77
1-4 OVERARCHING CRITERIA OR REGULATORY REQUIREMENTS.
Design and Construction must comply with Public Laws (P.L.), Executive Orders (E.O.), Code of Federal Regulations (CFR), Department of Defense Instructions (DoDI), Department of Defense Manuals (DoDM), and Department of Defense Directives (DoDD) or other higher authority documents as applicable.
1-4.1 Vending Facilities for the Blind.
Verify with the using activity the requirement to provide blind-operated vending facilities in compliance with the Randolph-Sheppard Act and DoDI 1125.03. This requirement generally applies in buildings that are over 15,000 square feet (1,400 square meters) that will contain over 100 employees, but may also apply in other situations at the discretion of the using activity.
1-4.2 Nursing and Lactation Rooms.
Military installations and DoD facilities should provide a private space for nursing mothers as required by the Office of the Undersecretary of Defense (OUSD) Memorandum, Department-Wide Policy for Nursing and Lactation Rooms. Use the Office of Personnel Management (OPM) Guide for Establishing a Federal Nursing Mother’s Program to implement best practices for creating a successful nursing mother’s program, consistent with the demand of the workplace and the needs of the mission. This space may not be a bathroom, and must be shielded from view and free from intrusion of others. A nursing mother’s space must be functional, with a private space with a place to sit and a flat surface, other than the floor, to place the breast pump and other supplies. Although there are no size or permanency requirements, this space must provide access to electricity for the use of a breast pump, as well as good lighting, a comfortable temperature, and proper ventilation; and be near a source of hot and cold running water. In addition, comply with any command-specific policy applicable to this requirement or applicable to the establishment of a working mothers program within the facility.
1-5 UFC AUTHORITIES.
1-5.1 ESEP.
\1\ The ESEP represents the senior technical facilities engineering leadership within each Military Department as identified in paragraph 1-2 and exercises exclusive authority to issue UFC and FC, and to approve waivers and exemptions thereof.
1-5.2 Component Technical Representative (CTR).
The CTR represents the project sponsor or customers and exercises authority to establish project requirements on behalf of the user or facility owner in the following cases:
FA4608-21-R-0004
Pg 14 of 77
• When the Building Official / Authority Having Jurisdiction (BO/AHJ) has identified more than one option satisfies criteria and allows user preference, such as for different system choices that offer varying levels of performance, durability, compatibility, compatibility with other systems, esthetics, or the like. This authority would not apply where in conflict with requirements for installation-wide networks, architectural standards, or similar standards established by the installation or Component with jurisdiction of the installation.
• When the BO/AHJ has identified an approved equivalent standard that satisfies the intent of criteria (see Chapter 2, paragraph 104.11), such as a material or component meeting a host-nation standard in a foreign location.
• When the BO/AHJ has identified a design option is not specifically addressed in criteria.
1-5.3 Building Official / Authority Having Jurisdiction (BO/AHJ).
The terms “Building Official” or BO and “Authority Having Jurisdiction” or AHJ used in the UFC or FC criteria, reference codes, and standards are synonymous. The BO/AHJ represents the DoD design and construction agent responsible for accomplishing the project, and exercises authority to interpret and apply criteria to work in progress, evaluate compliance with criteria, and accept finished work that is in compliance. This authority does not include approval of waivers or exemptions to criteria. /1/
1-6 GENERAL BUILDING REQUIREMENTS.
1-6.1 Building Codes.
Use 2018 IBC and 2018 IEBC as follows:
• Use IBC, including all published errata, as the building code for DoD, except as modified by this UFC, other UFC, and FC. Where a paragraph in any chapter of IBC references a paragraph in a different chapter, the referenced chapter shall be modified as described in CHAPTER 2.
• Use IEBC, including all published errata, except as modified by this UFC, other UFC, and FC. Where a paragraph in any chapter of IEBC references a paragraph in a different chapter, the referenced chapter shall be modified as described in CHAPTER 3.
1-6.2 Referenced Codes and Substitutions.
Treat references in the DoD Building Code (see Paragraph 2-1.1) and the DoD Existing Building Code (see Paragraph 3-1.1) to other codes as follows:
• References to the International Fuel Gas Code® (IFGC) are references to NFPA 54 (ANSI Z223.1) and NFPA 58.
FA4608-21-R-0004
Pg 15 of 77
• References to the International Mechanical Code® (IMC) are references to UFC 3-410-01, which cites IMC.
• References to the International Plumbing Code® (IPC) are references to UFC 3-420-01, which cites IPC.
• Dismiss references to the International Property Maintenance Code® (IPMC), as IPMC is not adopted.
• References to the International Fire Code® (IFC) are references to UFC 3- 600-01, which cites NFPA 1.
• References to the International Energy Conservation Code® (IECC) are references to UFC 1-200-02, which cites ASHRAE 90.1 and
ASHRAE189.1.
• References to NFPA 70, National Electrical Code® (NEC) are references to UFC 3-501-01, which cites NFPA 70.
• References to the International Residential Code® (IRC) are references to \1\the IRC. See also UFC 3-600-01. /1/
1-6.3 Other Criteria.
In addition to IBC as modified in CHAPTER 2, and IEBC as modified in CHAPTER 3, comply with the following criteria.
1-6.3.1 UFC.
Comply with the UFC (latest version, refer to Paragraph 1-3.1) as noted herein.
1-6.3.1.1 Core UFC.
Core UFC are criteria that provide requirements for the majority of traditional building systems that are prevalent on DoD facility construction projects. Core UFC also identify additional criteria such as Antiterrorism, High Performance, and Sustainable Building requirements mandated by law and policy. Comply with the Core UFC listed here, and other UFC identified in APPENDIX C as they are applicable.
• 1-200-02, High Performance and Sustainable Building Requirements
• 3-101-01, Architecture
• 3-110-03, Roofing
• 3-120-10, Interior Design \1\
• 3-190-06, Protective Coatings and Paint /1/
• 3-201-01, Civil Engineering
• 3-201-02, Landscape Architecture
• 3-210-10, Low Impact Development
FA4608-21-R-0004
Pg 16 of 77
• 3-220-01, Geotechnical Engineering
• 3-230-01, Water Storage and Distribution \1\ /1/
• 3-240-01, Wastewater Collection
• 3-301-01, Structural Engineering \1\ /1/
• 3-401-01, Mechanical Engineering
• 3-410-01, Heating, Ventilating and Air Conditioning
• 3-420-01, Plumbing Systems
• 3-490-06, Elevators
• 3-501-01, Electrical Engineering
• 3-520-01, Interior Electrical Systems
• 3-530-01, Interior and Exterior Lighting Systems and Controls \1\ /1/
• 3-550-01, Exterior Electrical Power Distribution
• 3-560-01, Electrical Safety, O&M
• 3-580-01, Telecommunications Building Cabling Systems Planning and Design
• 3-600-01, Fire Protection Engineering for Facilities
• 4-010-01, DoD Minimum Antiterrorism Standards for Buildings
• 4-010-06, Cybersecurity of Facility-Related Control Systems
• 4-021-01, Design and O&M: Mass Notification Systems 1-6.3.1.2 Other UFC.
In addition to the “Core UFC”, comply with other UFC as applicable to the system, structure, or facility type defined in the scope of the construction project.
1-6.3.2 FC.
The designation "FC" is for criteria that are not applicable to all DoD Components. For example: FC 4-721-10N "Navy and Marine Corps Unaccompanied Housing" has a final "N" designation because it is used by the Navy, including its Component, the U.S.
Marine Corps. FC are applicable only to the DOD Component in the title and are intended for use with unified technical requirements published in UFC. Comply with the FC for the designated facility type and the DoD Component.
1-6.3.3 Specification Requirements.
Use Unified Facilities Guide Specifications (UFGS) for all projects, including Design- Build submittals, and in accordance with UFC 1-300-02. Download, use, and edit the most current UFGS database available from the Whole Building Design Guide website
FA4608-21-R-0004
Pg 17 of 77 at http://www.wbdg.org/ccb/browse_cat.php?c=3. Modify and edit the UFGS as necessary to suit the work required by the specific project, including editing for metric or inch-pound and to reflect the latest proven technology, materials, and methods for the project. Follow Order of Precedence requirements for each Government Design Agent on use of Regional, Agency, Unified, and Other guide specifications. Other guide specifications may be used as a basis for information when not available in the UFGS.
Provide these specifications in UFGS format and modified to meet the requirements of
UFC 1-300-02.
1-6.3.4 Other Military Criteria.
Military criteria other than those listed in this UFC may be applicable to specific types of structures, building systems, or building occupancies. Such structures, systems, or buildings must meet the additional requirements of applicable military criteria.
1-6.3.4.1 Explosive Safety.
This document does not contain requirements for explosives safety. Facilities that involve DoD Ammunition and Explosives (AE) storage, handling, maintenance, manufacture or disposal, as well as facilities within the explosives safety quantity distance (ESQD) arcs of AE facilities, must comply with the requirements found in DoDM 6055.09, as well as implementing Service criteria found in DA PAM 385-64 (Army), NAVSEA OP 5 (Navy and Marine Corps), and AFMAN 91-201 (Air Force). DoD facilities exposed to potential explosion effects from AE belonging to other nations are also required to meet DoD and Service explosives safety criteria.
Closely coordinate the planning and design of new facilities, and occupation, repair, alteration, and restoration of existing AE-related facilities, or other facilities within ESQD arcs with knowledgeable explosives safety professionals in theater, or with the Services’ Explosives Safety Centers. Coordinate as early as possible in the planning and design process to avoid issues or problems and to ensure compliance.
Facility construction or use within ESQD arcs requires review for compliance with explosives safety criteria, and must have either an approved explosives safety site plan or an approved explosives safety deviation. Refer to the DoD Service documents mentioned above for further applicable guidance.
1-6.3.4.2 Facility Systems Safety.
Safety is an important component of maintaining and operating DoD facilities. Consider safety during design. Incorporate a hazards review into the regular design review process to ensure systems safety has been considered at the earliest phases of project development to reduce and mitigate unintentional maintenance and operational hazards. Army projects will incorporate the safety engineering practices delineated under the Facilities Systems Safety (FASS) program as prescribed under AR PAM 385- 16, System Safety Management Guide, to the extent practicable and feasible. Air Force projects will incorporate the safety engineering practices delineated in AFMAN 91-203, Air Force Consolidated Occupational Safety Instruction, to the extent practicable and
FA4608-21-R-0004
Attachment 12
Pg 18 of 77 http://www.wbdg.org/ccb/browse_cat.php?c=3 feasible. For Navy the Designer of Record must follow the concepts from the most current ANSI/ASSP Z590.3, Prevention through Design: Guidelines for Addressing Occupational Hazards and Risks in Design and Redesign Processes. All DoD facilities must comply with DoDI 6055.01 and applicable Occupational Safety and Health Administration (OSHA) safety and health standards.
1-6.3.4.3 Antiterrorism.
Antiterrorism is defined as defensive measures used to reduce the vulnerability of individuals and property to terrorist acts. UFC 4-010-01 sets the minimum requirements for DoD buildings, and the Geographic Combatant Commander Antiterrorism Construction Standards address unique requirements specific to their area of responsibility. Refer to UFC 4-010-01 and the Geographic Combatant Commander Antiterrorism Construction Standards for the minimum antiterrorism requirements.
1-6.3.4.4 Physical Security.
Physical security is defined as that part of security concerned with physical measures designed and placed to safeguard personnel; to prevent unauthorized access to installations, equipment, material and documents, and to safeguard them against espionage, sabotage, damage, and theft. Many buildings require some level of physical security. When required, integrate physical measures into the site, building, room, or area as applicable. DoD requirements for physical security related to specific assets are documented in DoD publications, directives, manuals, and instructions. The Services have related documents that implement the DoD policy for the Services. The main DoD documents that contain the physical security requirements for the protection of specific DoD assets are shown in Table 1-1. This does not include the policy documents associated with the protection of nuclear and chemical assets.
Table 1-1 Policy Related to Physical Security
Asset Policy and Documents
Classified Information DoDM 5200.01, Volume 3, DoD Information Security Program:
Protection of Classified Information;
https://www.esd.whs.mil/DD/DoD-Issuances/
Sensitive Compartmented Information (SCI)
DoDM 5105.21-Volume 1, Sensitive Compartmented Information (SCI) Administrative Security Manual: Administration of Information and Information Systems Security;
https://www.esd.whs.mil/DD/DoD-Issuances/
DoDM 5105.21-Volume 2, Sensitive Compartmented Information (SCI) Administrative Security Manual: Administration of Physical Security, Visitor Control, and Technical Security;
https://www.esd.whs.mil/DD/DoD-Issuances/
UFC 4-010-05, Sensitive Compartmented Information Facilities Planning, Design, and Construction;
FA4608-21-R-0004
Attachment 12
Pg 19 of 77 https://www.esd.whs.mil/DD/DoD-Issuances/ https://www.esd.whs.mil/DD/DoD-Issuances/
Asset Policy and Documents https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-010- 05/
Special Access Program (SAP) Information
DoDM 5205.07, Volume 3, DoD Special Access Program (SAP) Security Manual: Physical Security;
https://www.esd.whs.mil/DD/DoD-Issuances/
Arms, Ammunition, and Explosives
DoDM 5100.76-M, Physical Security of Sensitive Conventional Arms, Ammunition, and Explosives (AA&E);
https://www.esd.whs.mil/DD/DoD-Issuances/
Weapons Systems and Platforms
DoD 5200.08-R, Physical Security Program;
https://www.esd.whs.mil/DD/DoD-Issuances/
Bulk Petroleum Products
Communications Systems
Controlled Inventory Items
1-6.3.4.5 Corrosion Prevention and Control Requirements.
Use the requirements in CHAPTER 4 in conjunction with other UFC requirements to design for durability and provide for a comprehensive corrosion prevention and control strategy.
1-7 CYBERSECURITY.
Plan, design, acquire, execute, and maintain all control systems (including systems separate from a utility monitoring and control system) in accordance with UFC 4-010-06 and as required by individual Service Implementation Policy. Implement cybersecurity requirements to mitigate vulnerabilities to all DoD real property facility-related control systems to a level that is acceptable to the System Owner and Authorizing Official.
UFC 4-010-06 provides requirements for integrating cybersecurity into the design and construction of control systems.
1-8 NON-GOVERNMENT STANDARD MODIFICATIONS.
CHAPTER 2 modifies IBC and is organized by the chapter of IBC that each section modifies. CHAPTER 3 modifies IEBC and is organized by the chapter of IEBC that each section modifies. The modifications are one of four actions, according to the following legend:
FA4608-21-R-0004
Attachment 12
Pg 20 of 77 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-010-05/ https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-010-05/ https://www.esd.whs.mil/DD/DoD-Issuances/
• [Addition] – Add new section, including new section number, not shown in IBC or IEBC.
• [Deletion] – Delete referenced IBC or IEBC section.
• [Replacement] – Delete referenced IBC or IEBC section or noted portion and replace it with the narrative shown.
• [Supplement] – Add narrative shown as a supplement to the narrative shown in the referenced section of IBC or IEBC.
The section modifiers are identified at the end of the paragraph title. Limited commentary has been added in the chapters. Section designations for such commentary are preceded by a “[C]”, and the commentary narrative is shaded.
1-9 GLOSSARY.
APPENDIX B contains acronyms, abbreviations, and terms.
1-10 REFERENCES.
APPENDIX C contains a list of references used in this document. Unless otherwise specified, use the most recent edition of the referenced publication.
Pg 21 of 77
Pg 22 of 77
MODIFICATIONS TO IBC
2-1 CHAPTER 1 – SCOPE AND ADMINISTRATION [SUPPLEMENT].
Use IBC Chapter 1 except as modified below.
2-1.1 Section 101 – GENERAL.
101.1 Title [Replacement]
These regulations shall be known as the DoD Building Code, hereinafter referred to as “this code.”
101.4 Referenced codes [Supplement]
Refer to Paragraph 1-6.2 for referenced codes.
2-1.2 Section 102 – APPLICABILITY.
102.1 General [Replacement]
Where there is a conflict between a general requirement and a specific requirement, the specific requirement shall be applicable. Where, in any specific case, different sections of this code specify different materials, methods of construction or other requirements, the most restrictive shall govern. Refer to Paragraph 1-3.4 for hierarchy of UFC.
102.2 Other Laws [Replacement]
The provisions of this code shall not be deemed to nullify any provisions of local, state, or federal law. In overseas locations the SOFA, HNFA, and in some instances, BIA may govern requirements.
102.4 Referenced codes and standards [Supplement]
Refer to Paragraph 1-6.2 and Paragraph 1-6.3 for referenced codes and criteria.
2-1.3 Section 103 – DEPARTMENT OF BUILDING SAFETY [Deletion].
2-1.4 Section 104 – DUTIES AND POWERS OF BUILDING OFFICIAL.
104.1 General [Replacement]
The Building Official/AHJ is a person authorized and directed to enforce the provisions of this code, UFC, or FC. They have the authority to render interpretations of this code, UFC, or FC and to clarify the application of the provisions. Such interpretations will be in compliance with the intent and purpose of this code, UFC, or FC and will not have the effect of waiving or exempting requirements specifically provided for in this code, UFC, or FC. For waiver and exemption process and authority refer to Section 104.10 Waivers and exemptions.
FA4608-21-R-0004
Pg 23 of 77
104.10 Waivers and exemptions [Replacement]
Where there are practical difficulties involved in carrying out the provisions of this code, UFC, or FC; the Building Official/AHJ shall first find that special individual case or reason makes the strict letter of this code, UFC, or FC impractical resulting in noncompliance with requirements or an increased risk to: health, accessibility, life and fire safety, structural requirements, or operational requirements. Such cases will be treated as a waiver or exemption. Waivers and exemptions to specific UFC or FC requirements are approved by the Service’s Chief Engineer, Engineering Senior Executive Panel signature authority for the Service. Refer to MIL-STD 3007 for waivers and exemption definitions and for specific requirements for approval.
104.11 Alternative materials, design and methods of construction and equipment [Replacement]
The provisions of this code, UFC, or FC are not intended to prevent the installation of any material or to prohibit any design or method of construction not specifically prescribed by this code, provided that any such alternative has been approved. An alternative material, design, or method of construction may be approved where the Building Official/AHJ finds that the proposed design is satisfactory and complies with the intent of the provisions of this code, UFC, or FC, and that the material, method, or work offered is, for the purpose intended, not less than the equivalent of that prescribed in this code, UFC, or FC in quality, strength, effectiveness, fire resistance, durability, and safety. When the alternative material, design, or method of construction is not approved, the Building Official/AHJ will respond in writing, stating the reasons why the alternative was not approved.
104.11.1 Research reports [Replacement]
Supporting data, where necessary to assist in the approval of materials or assemblies not specifically provided for in this code, UFC, or FC, shall consist of valid research reports from approved sources.
[C] 104.10 Waivers and exemptions [Supplement]
Avoid requests for waivers and exemptions if possible. A criteria- or code-compliant engineering solution for the facility should be the objective versus a waiver or exemption request. UFC and FC requirements are intended to address code-compliant facility requirements; life, health and safety requirements; property loss prevention; lowest lifecycle cost; and facility operational requirements. For issues dealing with life, health, and safety, cost is not a valid reason to grant a waiver or exemption. Waiving or exempting requirements typically results in increased risk to safety or property loss, increased operational risk, or poor return on investment.
FA4608-21-R-0004
Pg 24 of 77
104.11.2 Tests [Replacement]
Whenever there is insufficient evidence of compliance with the provisions of this code, or evidence that a material or method does not conform to the requirements of this code, or in order to substantiate claims for alternative materials or methods, the Building Official/AHJ shall have the authority to require tests as evidence of compliance to be made without expense to the government. Test methods shall be as specified in this code, UFC, or FC or by other recognized test standards. In the absence of recognized and accepted test methods, the Building Official/AHJ shall approve the testing procedures. Tests shall be performed by an approved agency. Reports of such tests shall be retained by the Building Official/AHJ.
104.11.3 Overseas locations [Addition]
In overseas locations where the SOFA, HNFA, OEBGD, or BIA may govern requirements, the Building Official/AHJ will review the situation and determine what, if any, measures are appropriate to take to compensate for measures not allowed by the host nation or that present practical difficulties involved in carrying out the provisions.
Measures taken must not lessen quality, strength, effectiveness, fire resistance, durability, and safety. In these instances, formal exemptions are not required. The details of action granting alternative materials, design and methods of construction and equipment will be recorded and entered in the project document files by the Building Official/AHJ. Note that alternative materials, design and methods of construction and equipment must not be misconstrued as a waiver or exemption. Waivers and exemptions are addressed in 104.10.
2-1.5 Section 105 – PERMITS [Deletion].
2-1.6 Section 106 – FLOOR AND ROOF DESIGN LOADS [Deletion].
2-1.7 Section 107 – SUBMITTAL DOCUMENTS [Deletion].
2-1.8 Section 108 – TEMPORARY STRUCTURES AND USES [Deletion].
2-1.9 Section 109 – FEES [Deletion].
2-1.10 Section 111 – CERTIFICATE OF OCCUPANCY [Deletion].
2-1.11 Section 113 – BOARD OF APPEALS [Deletion].
2-1.12 Section 114 – VIOLATIONS [Deletion].
2-1.13 Section 115 – STOP WORK ORDER [Deletion].
2-1.14 Section 116 – UNSAFE STRUCTURES AND EQUIPMENT [Deletion].
2-2 CHAPTER 2 – DEFINITIONS [SUPPLEMENT].
FA4608-21-R-0004
Pg 25 of 77
Use IBC Chapter 2 except as modified by APPENDIX B.
2-3 CHAPTER 3 – USE AND OCCUPANCY CLASSIFICATION
[SUPPLEMENT].
Use IBC Chapter 3 except as modified by UFC 3-600-01.
2-4 CHAPTER 4 – SPECIAL DETAILED REQUIREMENTS BASED ON USE
AND OCCUPANCY [SUPPLEMENT].
Use IBC Chapter 4 only as specifically referenced by UFC 3-600-01.
2-5 CHAPTER 5 – GENERAL BUILDING HEIGHTS AND AREAS
Use IBC Chapter 5 except as modified below and by UFC 3-600-01.
2-5.1 Section 506 – BUILDING AREA
2-5.1.1 Table 506.2 – Allowable Area Factor in Square Feet.
Table 506.2: Cell at I-3, S1, Type IIA [Replacement]
60,000.
Table 506.2: Cell at I-4, S1, Type IA [Replacement]
242,000.
2-6 CHAPTER 6 – TYPES OF CONSTRUCTION [SUPPLEMENT].
Use IBC Chapter 6 except as modified by UFC 3-600-01.
[C] CHAPTER 2 – DEFINITIONS [SUPPLEMENT]
Definitions in IBC Chapter 2 apply to terms used in the model code and are not intended to replace definitions and terms in military and other referenced documents.
It is essential that the code defined meaning be known to understand the intent and correctly interpret the code.
[C] CHAPTER 5 – GENERAL BUILDING HEIGHTS AND AREAS [SUPPLEMENT]
UFC 3-600-01 gives direction concerning the requirements for fire-rated partitions.
Note that the building area for funding and planning purposes is calculated differently than the method defined in IBC Chapter 5 for code compliance calculation.
FA4608-21-R-0004
Pg 26 of 77
2-7 CHAPTER 7 – FIRE AND SMOKE PROTECTION FEATURES
Use IBC Chapter 7 except as modified by UFC 3-600-01.
2-8 CHAPTER 8 – INTERIOR FINISHES [REPLACEMENT].
Use UFC 3-600-01 and UFC 3-120-10.
2-9 CHAPTER 9 – FIRE PROTECTION SYSTEMS [REPLACEMENT].
Use UFC 3-600-01.
2-10 CHAPTER 10 – MEANS OF EGRESS [REPLACEMENT].
Use UFC 3-600-01. Use IBC Chapter 10 when specifically referenced by US Access Board, Architectural Barriers Act (ABA) Standards and as referenced by UFC 3-600-01.
2-11 CHAPTER 11 – ACCESSIBILITY [REPLACEMENT].
Use the ABA Standards and the special provisions of the DoD Deputy Secretary of Defense Memorandum, Subject: Access for People with Disabilities, October 31, 2008.
2-12 CHAPTER 12 – INTERIOR ENVIRONMENT [SUPPLEMENT].
Use IBC Chapter 12 except as modified below.
[C] CHAPTER 7 – FIRE AND SMOKE PROTECTION FEATURES [SUPPLEMENT]
UFC 3-600-01 gives direction concerning the requirements for fire-rated partitions.
[C] CHAPTER 10 – MEANS OF EGRESS [REPLACEMENT]
UFC 3-600-01 references IBC Chapter 10 for requirements for stair to roof access.
Where the ABA Standards reference the previous versions of IBC, the applicable requirements of the 2018 IBC are acceptable.
[C] CHAPTER 11 – ACCESSIBILITY [REPLACEMENT]
Refer to APPENDIX C for a link to the ABA Standards and the DoD policy memorandum.
FA4608-21-R-0004
Pg 27 of 77
2-12.1 Section 1203 – TEMPERATURE CONTROL.
1203.1 Equipment and systems [Replacement]
Use the applicable UFC and individual military service standards for temperature control criteria.
1203.1 Equipment and systems, Exceptions [Deletion]
2-12.2 Section 1206 – SOUND TRANSMISSION.
1206.2 Airborne sound [Replacement]
Use UFC 3-101-01 and UFC 3-120-10. For Navy and Marine Corps Unaccompanied Housing facilities, only use FC 4-721-10N.
1206.3 Structure-borne sound [Replacement]
Use UFC 3-101-01 and UFC 3-120-10. For Navy and Marine Corps Unaccompanied Housing facilities, only use FC 4-721-10N.
2-12.3 Section 1207 – INTERIOR SPACE DIMENSIONS.
1207.3 Room area [Replacement]
Use UFC 3-101-01 and UFC 3-120-10. For Navy and Marine Corps Unaccompanied Housing facilities, only use FC 4-721-10N.
1207.4 Efficiency dwelling units [Replacement]
Use UFC 3-101-01 and UFC 3-120-10. For Navy and Marine Corps Unaccompanied Housing facilities, only use FC 4-721-10N.
2-13 CHAPTER 13 – ENERGY EFFICIENCY [REPLACEMENT].
Use UFC 1-200-02.
2-14 CHAPTER 14 – EXTERIOR WALLS [SUPPLEMENT].
Use IBC Chapter 14 except as modified below.
[C] CHAPTER 12 – INTERIOR ENVIRONMENT [SUPPLEMENT]
Refer to other Federal guidance and UFC for additional interior space requirements for ventilation, lighting, acoustics, and other environmental characteristics.
FA4608-21-R-0004
Pg 28 of 77
2-14.1 Section 1402 – PERFORMANCE REQUIREMENTS.
1402.5 Vertical and lateral flame propagation [Deletion]
2-14.2 Section 1406 – METAL COMPOSITE MATERIALS (MCM).
2-14.2.1 1406.10 Type I, II, III and IV construction.
1406.10.4 Full-scale tests [Replacement]
The MCM system must be tested in accordance with, and comply with, the acceptance criteria of NFPA 285. Perform testing on the MCM system with the MCM in the maximum thickness intended for use. Where noncombustible materials or combustible materials permitted by Sections 603, 1405, or UFC 3-600-01 differ from assembly to assembly or within an assembly, multiple tests shall not be required.
1406.10.4 Full-scale tests, Exception [Addition]
Exception: The MCM system is not required to be tested in accordance with, and comply with, acceptance criteria of NFPA 285 in buildings equipped throughout with an automatic sprinkler system in accordance with UFC 3-600-01.
2-15 CHAPTER 15 – ROOF ASSEMBLIES AND ROOFTOP STRUCTURES
[SUPPLEMENT].
Use IBC Chapter 15 except as modified by UFC 3-110-03 and UFC 3-600-01.
2-16 CHAPTER 16 – STRUCTURAL DESIGN [SUPPLEMENT].
Use IBC Chapter 16 except as modified below and by UFC 3-301-01 and\1\ 3-301-02 /1/.
2-16.1 Section 1604 – GENERAL DESIGN REQUIREMENTS.
1604.11 Fall prevention and protection [Addition]
Provide fall protection as required by UFC 3-101-01. The anchorages and the structural elements that support these anchorages must meet the requirements of Section 1607.10.4, as modified by UFC 3-301-01. Where fall protection is required in the vicinity of weight-handling equipment, prevent conflicts between the weight-handling equipment and the fall protection measure.
2-16.2 Section 1612 – FLOOD LOADS [Supplement].
Use Section 1612 except as modified by UFC 3-201-01 \1\ /1/
1612.3 Establishment of flood hazard areas [Supplement]
Comply with UFC 3-201-01.
FA4608-21-R-0004
Pg 29 of 77
2-17 CHAPTER 17 – SPECIAL INSPECTIONS AND TESTS [SUPPLEMENT].
Use IBC Chapter 17 except as modified below and by UFC 3-220-01, UFC 3-301-01, and UFC 3-600-01.
2-17.1 Section 1701 – GENERAL.
1701.1 - Scope [Supplement]
Contractual relationships and the composition of the architect / engineer / construction (AEC) team differ from that contemplated by the language of 2018 IBC, when doing DoD construction. When performing design or construction using typical methods for in-house design, AE design, and contracting for construction, 2018 IBC/ASCE 7-16 terms of Authority Having Jurisdiction and Building Official are to be as defined in UFC 1-200- 01.
2-17.2 Section 1704 – SPECIAL INSPECTIONS AND TESTS, CONTRACTOR
RESPONSIBILITY AND STRUCTURAL OBSERVATION.
1704.2 Special inspections and tests [Replacement]
The contractor must employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections defined in Section 110. The inspecting agency must provide reports of the special inspections directly to the government.
2-18 CHAPTER 18 – SOILS AND FOUNDATIONS [SUPPLEMENT].
Use IBC Chapter 18 except as modified below and by UFC 3-201-01, UFC 3-220-01, and UFC 3-301-01.
2-18.1 Section 1804 – EXCAVATION, GRADING, AND FILL.
1804.4 Site grading [Supplement]
Ensure that the grading and associated storm water runoff do not adversely affect surrounding sites. Establish finished floor elevations a minimum of 6 inches (150 mm) above finished grade at the perimeter of the building and provide site grading in
[C] 1701.1 - Scope [Supplement]
The context of the IBC terms “permit”, “permit application”, “permit applicant”, and “owner” must be modified for DoD projects. Refer to Paragraph 1-5. DoD functions as the building department/jurisdiction and the AHJ functions as the building official.
When DoD advertises a project, the building permit is effectively implied/granted.
However, the overall project may still require other permits related to site storm water, air quality, demolition disposal, etc.
FA4608-21-R-0004
Pg 30 of 77 accordance with UFC 3-201-01. Comply with UFC 3-600-01 for design of entrances and exits from buildings.
1804.4 Site grading, Exception 1 [Deletion]
1804.4 Site grading, Exception 2 [Replacement]