Attachment 1 Scope of Work.pdf
PDF 2 MB Posted
- Attached to
- Install Solar System
- Solicitation number
- 12805B23Q0597
About this file
This document is a scope of work for a federal contract opportunity to design, install and commission an agrivoltaic solar system at the USDA Agricultural Research Service Northern Great Plains Research Laboratory in Mandan, North Dakota. Key requirements include providing a cost proposal and technical proposal to design and install a 45.36kW DC high clearance ground mount solar system with 84 bifacial solar modules and three phase inverters. The contractor must perform all electrical and trenching work to interconnect the photovoltaic array to an existing Montana Dakota Utilities meter. Additional specifications cover array configuration, foundation and support details, permitting, submittal schedules, and project closeout. The related federal contract opportunity is solicitation number 12805B23Q0597 for installing the solar system, issued by the USDA Agricultural Research Service Plains Area.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1 of
United States Department of Agriculture Agricultural Research Service
SPECIFICATIONS FOR AGRIVOLTAIC DESIGN, INSTALLATION AND
COMMISSIONING AT THE USDA-ARS Northern Great Plains Research Laboratory (NGPRL)
USDA, ARS, PA, Northern Great Plains Research Laboratory (NGPRL) 1701 10th Avenue SW Mandan, ND.
DATE: July 12, 2023
STATEMENT OF WORK
TABLE OF CONTENTS
1.0 Project Information
2.0 Project Contact Persons
3.0 Scope of Services
4.0 Technical Project Requirements
5.0 Background and Site Description
6.0 Technical Cost Proposal
7.0 Specific Requirements
8.0 Performance Schedule
1.0 Project Information:
A. Project Number: TBD
B. Project Title: Specifications for the Agrivoltaic Design, Installation and Commissioning of a High Clearance, Adjustable Angle, Ground Mount Solar System.
C. Project Location:
USDA, ARS, PA, Northern Great Plains Research Laboratory 1701 10th Ave SW.
Mandan, ND 58554
2.0 Project Contact Persons:
A. WARRANTED CONTRACTING OFFICER
TDB
Page 2 of
B. ENGINEERING PROJECT MANAGER (EPM):
Mark McWilliams, USDA, ARS, WBSC Phone: 970- 631-7513 2150 Avenue, Building D, Suite 300 Fort Collins, CO 80526 Email: mark.mcwilliams@usda.gov
C. RESEARCH PROGRAM REPRESENTATIVES (RPR):
David Archer Phone: 701-667-3048 USDA, ARS, PA, NGPRL Email:
David.archer@usda.gov Northern Great Plains Research Laboratory
D. LOCATION ADMINISTRATIVE OFFICER (LAO):
Jeremy Will Phone: 701-667- 3014 USDA, ARS, PA, NGPRL Email:
Jeremy.will@usda.gov Northern Great Plains Research Laboratory
E. LOCATION MONITOR (LM):
Mike Eberle Phone: 701-667-3075 USDA, ARS, PA, NGPRL Email:
Michael.eberle@usda.gov Northern Great Plains Research Laboratory
F. COLLATERAL DUTY SAFETY OFFICER (CDSO):
Holly Johnson Phone: 701-667-3003 USDA, ARS, PA, NGPRL Email:
Holly.Johnson@usda.gov Northern Great Plains Research Laboratory
3.0 Scope of services:
The Contractor shall provide all professional services necessary for the accomplishment of each project and such required services shall be in accordance with requirements as described herein.
A. The Contractor shall provide services for the following tasks marked “X”:
[X] Provide a cost proposal and a technical proposal to complete the project as per project requirements.
mailto:mark.mcwilliams@usda.gov mailto:David.archer@usda.gov mailto:Jeremy.will@usda.gov mailto:Michael.eberle@usda.gov mailto:Holly.Johnson@usda.gov
Page 3 of
[X] The contractor shall furnish all the skilled labor, materials, equipment, tools, transportation, and supervision necessary to Photovoltaic design, Installation and Commissioning of a High Clearance Ground Mount Solar System at the USDA-ARS, Northern Great Plains Research Lab.
4.0 Technical Project Requirements:
The Contractor will work with site personnel to ensure each task is accomplished in a timely manner within 90 working days from the start date of the project.
A. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction shall comply with applicable federal, state, and local code requirements as well as current industry standards, (i.e.: EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.
B. All work to meet all pertinent Unified Facilities Guide Specifications
(UFGS) and ARS 242.1M standards. UFGS available at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs. ARS 242.1M available at https://www.afm.ars.usda.gov/ppweb/pps-and- manuals/.
5.0 Background & Site Description:
A. See attached “jpgs” for approximate location of the project installation site. A site visit is strongly recommended contact:
Mike Eberle at 701-527-1524.
6.0 Technical Cost Proposal: The contractor shall provide a price to design, install and commission a high clearance ground mount solar system with all the necessary electrical connections to connect the photovoltaic (PV) array to a Montana Dakota Utilities meter.
7.0 Specific Requirements
1. The contractor shall provide photovoltaic design that is compatible with agricultural research needs of the NGPRL (Agrivoltaics), and shall install and commission a high clearance (14ft high) ground mount solar system that is a 45.36kW DC. This includes:
2. The contractor will provide all the trenching and electrical work needed to complete the job in accordance with local codes.
3. The contractor shall provide and install eighty-four (84) bifacial solar modules of approximately 540W.
4. The contractor shall provide and install a 50kW (AC) 3-phase 208V inverter and two (2) 25kW inverters (or equivalent).
http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs http://www.afm.ars.usda.gov/ppweb/pps-and-
Page 4 of
5. The contractor shall provide and install four (4) high-clearance ground mount systems. Each wide enough to support 21 bifacial solar modules and mounts shall have manually adjustable tilt angles of up to 46 degrees.
6. The contractor shall provide and install anchoring systems for the high-clearance ground mount systems that are capable of withstanding local weather conditions.
7. The contractor shall provide and install trenching (2-3 feet in depth), boring, and wire run to connect photovoltaic array with Montana Dakota Utilities meter in building 3 of the Northern Great Plains Research Laboratory.
8. To connect photovoltsic array to MDU meter, the contractor shall provide and install wires that are PV-Rated and that will keep voltage drop below 2%.
9. The contractor shall be responsible for any utility line locations needed to cover the excavation areas both public and private.
The contractor shall be responsible for any damage that may be caused because of any trenching or excavation activities.
10. The contractor must include all required materials and equipment needed to complete the installation.
11. The contractor shall be responsible for backfilling and relandscaping any areas of trenching and excavation and return the areas to grade and re-seed any areas deemed by the COR. The grass seed and work shall be approved by the COR before considered complete.
12. The contractor shall provide and install underground waterproof conduit and connectors for the wire from the arrays to the MDU meter site.
13. The contractor shall provide and install any necessary upgrades to the service pole/meter for tie in with the system, service panel and/ or transformers necessary.
14. The contractor shall provide the electrical components, hardware, and supplies for the solar PV system wiring.
15. The contractor shall interconnect the application with a single-line electrical drawing and site plan.
16. The contractor shall provide the proper permit package, all applicable applications, and fees related to providing a complete system.
17. The contractor shall provide all the project management needs along with all the labor necessary to complete the system.
18. The contractor shall provide a qualified licensed electrician to wire and interconnect the PV system.
19. The contractor shall provide all the necessary customer training on operating the system for the number of people requested by
Page 5 of the NGPRL staff.
20. The contractor shall provide a warranty on the system and workmanship.
21. The contractor shall cleanup site of all materials and debris and dispose of these materials off-site to the satisfaction of the Location Monitor before the project is deemed complete.
22. Minimum Array Specifications:
The array must have 3 rows and 7 columns with 21 modules.
The tilt angle of 46 degrees. The array height at the tilt angle must be 14 ft.
23. Minimum Foundation Specifications:
Each hole should be approximately 36 inches round in diameter. Each solar array will have 3 poles. The first pile should be approximately 7.50 ft below grade, the second pile approximately 8.00 ft below grade, and the third pile approximately 7.50 ft below grade.
24. Minimum Support Specifications:
Pole Sizes: 12 total - 6inch steel Schedule 40 pipe 20 feet in length. Poles must be cemented into ground approximately 10 feet.
8.0 Performance Schedules:
A. Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Design Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of construction permit, licenses, inspections, etc., are the obligation of the future Construction Contractor.
B. Schedules shall be updated and furnished with each submittal.
C. Submittals shall be made as scheduled in the Special Requirements section. Each submittal shall be distributed electronically in Adobe for review, to the Location Monitor at the facility, Engineering Project Manager, and Contracting Officer. Each submittal shall contain the previous submittal's Excel comment sheet with responses, notes of meetings held with ARS personnel, design notes, calculations, and construction progress bi-weekly meetings during construction.
D. Changes in the scope of work or the task order that affect the level of effort of the Contractor must be pre-approved by the CO.
E. Disputes or questions that arise after the task order has been negotiated will be resolved by the CO.
Page 6 of
Page 7 of
Page 8 of
Page 9 of
Page 10 of
Page 11 of
SPECIFICATIONS FOR AGRIVOLTAIC DESIGN, INSTALLATION AND COMMISSIONING AT THE USDA-ARS Northern Great Plains Research Laboratory (NGPRL)
File details come from the government source that posted it. Updated .