Attachment 1 Schedule of Supplies.xlsx
XLSX spreadsheet 27 KB Posted
- Attached to
- Electronic Security System Maintenance Support Services Federal contract opportunity
- Solicitation number
- SP330025Q0013
- Issued by
- Defense Logistics Agency Distribution
About this file
This document is an attachment to a federal contract opportunity for Electronic Security System (ESS) Maintenance and Repair Services at DLA Distribution Puget Sound, WA. The contract will be a Firm Fixed Price agreement with Time & Materials CLINs for a base year from December 28, 2024 to December 27, 2025, with four one-year option periods. The key services required are preventative maintenance, remedial maintenance, and cyber documentation production. Estimated labor hours and materials ceilings are provided for each CLIN. The solicitation has a NAICS code of 561621 with a $25.0 Million size standard, and is being issued on an Unrestricted basis by the Defense Logistics Agency Distribution.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0003.pdf | ||
| Amendment 0001.pdf | ||
| Attachment 1 Schedule of Supplies.xlsx | XLSX spreadsheet | |
| Attachement 3 Equipment List.pdf | ||
| Attachment 2 Performance Work Statement.pdf | ||
| Attachement 5 Maintenance Task List.pdf | ||
| Attachemnt 4 Wage Determination.pdf | ||
| CSS SP330025Q0013.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BaseYear
DESCRIPTION QTY U/I UNIT PRICE TOTAL PRICEIR IR
BASE Year December 28, 2024- December 27, 2025
| Firm-Fixed-Price | ||||
| CLIN 0001 | Material Number: V00012980 Short Description: PREVENTATIVE MAINTENANCE ON IESS at DDPW | Preventative Maintenance Service for Integrated Electronic Security System (IESS) at DLA Distribution Puget Sound Quarterly Complete System TEST | 4 | EA |
Total Firm-Fixed-Price $0.00
| Time & Materials | Ceiling Price | ||||
| CLIN 0002 | Material Number: V00012981 Short Description: REMEDIAL MAINTENANCE ON IESS at DDPW | Hourly labor rate to perform repairs on the Integrated Electronic Security System (IESS) at DLA Distribution Puget Sound during normal working hours. The number of hours shown is an estimate only. Contractor will be paid only for the actual number of hours worked. | 140 | HR |
| Time & Materials | Ceiling Price | ||
| CLIN 0003 | Material Number: N00004092 Short Description: PARTS for Remedial Maint of IESS at DDPW | PARTS for Remedial Maintenance of IESS at DDPW. | $5,000.00 |
| Time & Materials | Ceiling Price | ||||
| CLIN 0004 | MATERIAL NUMBER: N/A Labor for CYBER DOCUMENTATION PRODUCTION | Hourly labor rate to perform cyber documentation production. The number of hours shown is an estimate only. Contractor will be paid only for the actual number of hours worked. | 20 | HR |
Total Time & Materials $5,000.00
| Total Ceiling Price - Base Year | $5,000.00 |
| Total Ceiling Price - Option Year 1 | $5,000.00 |
| Total Ceiling Price - Option Year 2 | $5,000.00 |
| Total Ceiling Price - Option Year 3 | $5,000.00 |
| Total Ceiling Price - Option Year 4 | $5,000.00 |
| Total Ceiling Price - Base + 3 Option Year Periods | $25,000.00 |
IGCE - ESS MAINT SERV
AT DLA DIST HILL UT &"Arial,Bold"&11SOURCE SELECTION INFORMATION
SEE FAR 2.101 AND 3.104&12
&"Arial,Bold"SOURCE SELECTION INFORMATION -
SEE FAR 2.101 AND 3.104 &P
OptionYear1
DESCRIPTION QTY U/I UNIT PRICE TOTAL PRICE
Option Year 1 December 28, 2025 - December 27, 2026
| Firm-Fixed-Price | ||||||
| CLIN 1001 | Material Number: V00012980 Short Description: PREVENTATIVE MAINTENANCE ON IESS at DDPW | Preventative Maintenance Service for Integrated Electronic Security System (IESS) at DLA Distribution Puget Sound Quarterly Complete System TEST | 4 | EA | $0.00 | $0.00 |
Total Firm-Fixed-Price $0.00
| Time & Materials | Ceiling Price | |||||
| CLIN 1002 | Material Number: V00012981 Short Description: REMEDIAL MAINTENANCE ON IESS at DDPW | Hourly labor rate to perform repairs on the Integrated Electronic Security System (IESS) at DLA Distribution Puget Sound during normal working hours. The number of hours shown is an estimate only. Contractor will be paid only for the actual number of hours worked. | 140 | HR | $0.00 | $0.00 |
| Time & Materials | Ceiling Price | ||
| CLIN 1003 | Material Number: N00004092 Short Description: PARTS for Remedial Maint of IESS at DDPW | PARTS for Remedial Maintenance of IESS at DDPW. | $5,000.00 |
| Time & Materials | Ceiling Price | |||||
| CLIN 1004 | MATERIAL NUMBER: N/A Labor for CYBER DOCUMENTATION PRODUCTION | Hourly labor rate to perform cyber documentation production. The number of hours shown is an estimate only. Contractor will be paid only for the actual number of hours worked. | 20 | HR | $0.00 | $0.00 |
Total Time & Materials $5,000.00
Total Ceiling Price - Option Year 1 $5,000.00
IGCE- ESS Maint Serv at DLA Dist Hill UT &"Arial,Bold"SOURCE SELECTION INFORMATION -
SEE FAR 2.101 AND 3.104
&"Arial,Bold"SOURCE SELECTION INFORMATION -
SEE FAR 2.101 AND 3.104
OptionYear2
DESCRIPTION QTY U/I UNIT PRICE TOTAL PRICE
Option Year 2 December 28, 2026 - December 27, 2027
| Firm-Fixed-Price | ||||||
| CLIN 2001 | Material Number: V00012980 Short Description: PREVENTATIVE MAINTENANCE ON IESS at DDPW | Preventative Maintenance Service for Integrated Electronic Security System (IESS) at DLA Distribution Puget Sound Quarterly Complete System TEST | 4 | EA | $0.00 | $0.00 |
Total Firm-Fixed-Price $0.00
| Time & Materials | Ceiling Price | |||||
| CLIN 2002 | Material Number: V00012981 Short Description: REMEDIAL MAINTENANCE ON IESS at DDPW | Hourly labor rate to perform repairs on the Integrated Electronic Security System (IESS) at DLA Distribution Puget Sound during normal working hours. The number of hours shown is an estimate only. Contractor will be paid only for the actual number of hours worked. | 140 | HR | $0.00 | $0.00 |
| Time & Materials | Ceiling Price | ||
| CLIN 2003 | Material Number: N00004092 Short Description: PARTS for Remedial Maint of IESS at DDPW | PARTS for Remedial Maintenance of IESS at DDPW. | $5,000.00 |
| Time & Materials | Ceiling Price | |||||
| CLIN 2004 | MATERIAL NUMBER: N/A Labor for CYBER DOCUMENTATION PRODUCTION | Hourly labor rate to perform cyber documentation production. The number of hours shown is an estimate only. Contractor will be paid only for the actual number of hours worked. | 20 | HR | $0.00 | $0.00 |
Total Time & Materials $5,000.00
Total Ceiling Price - Option Year 2 $5,000.00
IGCE - ESS Maint Serv DLA Dist Hill UT &"Arial,Bold"SOURCE SELECTION INFORMATION -
SEE FAR 2.101 AND 3.104
&"Arial,Bold"SOURCE SELECTION INFORMATION
SEE FAR 2.101 AND 3.104
OptionYear3
DESCRIPTION QTY U/I UNIT PRICE TOTAL PRICE
Option Year 3 December 28, 2027 - December 27, 2028
| Firm-Fixed-Price | ||||||
| CLIN 3001 | Material Number: V00012980 Short Description: PREVENTATIVE MAINTENANCE ON IESS at DDPW | Preventative Maintenance Service for Integrated Electronic Security System (IESS) at DLA Distribution Puget Sound Quarterly Complete System TEST | 4 | MO | $0.00 | $0.00 |
Total Firm-Fixed-Price $0.00
| Time & Materials | Ceiling Price | |||||
| CLIN 3002 | Material Number: V00012981 Short Description: REMEDIAL MAINTENANCE ON IESS at DDPW | Hourly labor rate to perform repairs on the Integrated Electronic Security System (IESS) at DLA Distribution Puget Sound during normal working hours. The number of hours shown is an estimate only. Contractor will be paid only for the actual number of hours worked. | 140 | HR | $0.00 | $0.00 |
| Time & Materials | Ceiling Price | ||
| CLIN 3003 | Material Number: N00004092 Short Description: PARTS for Remedial Maint of IESS at DDPW | PARTS for Remedial Maintenance of IESS at DDPW. | $5,000.00 |
| Time & Materials | Ceiling Price | |||||
| CLIN 3004 | MATERIAL NUMBER: N/A Labor for CYBER DOCUMENTATION PRODUCTION | Hourly labor rate to perform cyber documentation production. The number of hours shown is an estimate only. Contractor will be paid only for the actual number of hours worked. | 20 | HR | $0.00 | $0.00 |
Total Time & Materials $5,000.00
Total Ceiling Price - Option Year 3 $5,000.00
IGCE - ESS Maint Serv DLA Dist Hill UT &"Arial,Bold"SOURCE SELECTION INFORMATION -
SEE FAR 2.101 AND 3.104
&"Arial,Bold"SOURCE SELECTION INFORMATION
SEE FAR 2.101 AND 3.104
OptionYear4
DESCRIPTION QTY U/I UNIT PRICE TOTAL PRICE
Option Year 4 December 28, 2028 - December 27, 2029
| Firm-Fixed-Price | ||||||
| CLIN 3001 | Material Number: V00012980 Short Description: PREVENTATIVE MAINTENANCE ON IESS at DDPW | Preventative Maintenance Service for Integrated Electronic Security System (IESS) at DLA Distribution Puget Sound Quarterly Complete System TEST | 4 | MO | $0.00 | $0.00 |
Total Firm-Fixed-Price $0.00
| Time & Materials | Ceiling Price | |||||
| CLIN 3002 | Material Number: V00012981 Short Description: REMEDIAL MAINTENANCE ON IESS at DDPW | Hourly labor rate to perform repairs on the Integrated Electronic Security System (IESS) at DLA Distribution Puget Sound during normal working hours. The number of hours shown is an estimate only. Contractor will be paid only for the actual number of hours worked. | 140 | HR | $0.00 | $0.00 |
| Time & Materials | Ceiling Price | ||
| CLIN 3003 | Material Number: N00004092 Short Description: PARTS for Remedial Maint of IESS at DDPW | PARTS for Remedial Maintenance of IESS at DDPW. | $5,000.00 |
| Time & Materials | Ceiling Price | |||||
| CLIN 3004 | MATERIAL NUMBER: N/A Labor for CYBER DOCUMENTATION PRODUCTION | Hourly labor rate to perform cyber documentation production. The number of hours shown is an estimate only. Contractor will be paid only for the actual number of hours worked. | 20 | HR | $0.00 | $0.00 |
Total Time & Materials $5,000.00
Total Ceiling Price - Option Year 3 $5,000.00
52.217-8
DESCRIPTION QTY U/I UNIT PRICE TOTAL PRICE
Potential 6 Month Extention - April 9, 2026 - August 8, 2026
| Firm-Fixed-Price | |||||
| Material Number: V00012980 Short Description: PREVENTATIVE MAINTENANCE ON IESS at DDHU | Preventative Maintenance Service for Integrated Electronic Security System (IESS) at DLA Distribution Hill in accordance with the attached Performance Work Statement (PWS). | 12 | MO | $0.00 | $0.00 |
Total Firm-Fixed-Price $0.00
| Time & Materials | Ceiling Price | ||||
| Material Number: V00012981 Short Description: REMEDIAL MAINTENANCE ON IESS at DDHU | Hourly labor rate to perform repairs on the Integrated Electronic Security System (IESS) at DLA Distribution Hill during normal working hours. The number of hours shown is an estimate only. Contractor will be paid only for the actual number of hours worked. | 100 | HR | $0.00 | $0.00 |
| Time & Materials | Ceiling Price | |
| Material Number: N00004092 Short Description: PARTS for Remedial Maint of IESS at DDHU | PARTS for Remedial Maintenance of IESS at DDHU. | $10,000.00 |
| Time & Materials | Ceiling Price | ||||
| MATERIAL NUMBER: N/A Labor for CYBER DOCUMENTATION PRODUCTION | Hourly labor rate to perform cyber documentation production. The number of hours shown is an estimate only. Contractor will be paid only for the actual number of hours worked. | 50 | HR | $132.18 | $6,609.00 |
Total Time & Materials $16,609.00
Total Ceiling Price - Six Month Extension $16,609.00
File details come from the government source that posted it. Updated .