Att 01_140P8420R0002_Contract Bid Schedule.pdf

PDF 250 KB Posted

Attached to
Replace Lost Man Creek Bridges, NPS-REDW
Solicitation number
140P8420R0002
Issued by

About this file

This contract bid schedule outlines pricing requirements for the replacement of two bridges over Lost Man Creek in Redwood National Park. Offerors must submit pricing for five base line items including mobilization, demolition, new bridge structures, bridge railings, and surface improvements. Pricing is also required for five optional line items that correspond to the base line items. The total proposed price must include the base price plus the price of all options. The solicitation is being conducted by the National Park Service's Pacific West Region for work located in Humboldt County, California. A mandatory site visit is scheduled for May 20, 2020 to provide details on the project. Pricing must be submitted in lump sums or unit prices based on the specification sections referenced.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REDW – 245777 & 258461 CONTRACT BID SCHEDULE - 1

Contract Bid Schedule National Park Service (NPS) - Point Reyes MABO

Solicitation Number: 140P8420R0002

PARK-PMIS: Redwoods National Park - PMIS# 245777 and 258461 (Project Management Information System)

Developed Area: Lost Man Creek

Project Title: Replace Lost Man Road Bridges

Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars

Contract Line Item Number

(CLIN)

Contract Line Item (CLI) Title Quantity Unit of

Measure Unit Price Total Price

1 Mobilization/Demobilization 1 Lump Sum $0.00

2 Demolition 1 Lump Sum $0.00

3 New Bridge Structure 1 Lump Sum $0.00

4 New Bridge Railing 1 Lump Sum $0.00

5 Surface Improvements 1 Lump Sum $0.00

TOTAL BASE PRICE - LITTLE LOST MAN CREEK (Contract Line Item Number 1 through 5) -------------- $0.00

6 OPTION A, Mobilization/Demobilization 1 Lump Sum $0.00

7 OPTION B, Demolition 1 Lump Sum $0.00

8 OPTION C, New Bridge Structure 1 Lump Sum $0.00

9 OPTION D, New Bridge Railing 1 Lump Sum $0.00

10 OPTION E, Surface Improvements 1 Lump Sum $0.00

TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 6 through 10) ------------------------------- $0.00

TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 10) ---- $0.00

All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items.

Solicitation No. 140P8420R0002, Attachment 01, Contract Bid Schedule