Atch 3_Bldg 520 A 2.0 with Blue Beam Markups.pdf

PDF 268 KB Posted

Attached to
Epoxy Floor Coating Repair, Ames Federal contract opportunity
Solicitation number
12639525Q0164
Issued by
Department of Agriculture Animal and Plant Health Inspection Service Marketing and Regulatory Programs Business Services

About this file

This document is a floor plan and specification sheet for a floor coating repair project at the USDA-NCAH Building 520 in Ames, Iowa. The project involves removing existing epoxy coating in Rooms 105, 106, 107, and 108, and installing a new 3/4" plywood sub-floor with a 6-inch integral base and floor coating. The total floor area for new coating is approximately 1,016 square feet, with 202 linear feet of integral base to be installed.

Key specifications include maintaining existing door configurations, providing transition strips at door openings and floor drains, and ensuring the new floor coating resists cracking and provides good traction when wet. The project is classified under NAICS code 238330 for Flooring Contractors, with a small business size standard of $19 million. The estimated project magnitude is between $25,000 and $100,000, targeting a modular animal research building constructed in 2008 with a deteriorating floor coating system.

View the file

Other files for this federal contract opportunity

Other files attached to Epoxy Floor Coating Repair, Ames, newest first.
File Type Posted
12639525Q0164-0001.pdf PDF
Site visit sign-in sheet.pdf PDF
Atch 1_SOW Building 520 Floor Coating Repair.doc DOC document
Atch 7_StoncladGS PDS.pdf PDF
12639525Q0164.pdf PDF
Atch 5_Specification Section 096723 Resinous Flooring.docx DOCX document
Atch 9_ Floor Photos.pdf PDF
Atch 8_ Stonkote HT4 Product Data.pdf PDF
Atch 6_Stonchem 441 Product Data.pdf PDF
Atch 4_G001 Title Page Building 520 Floor Coating Repair.pdf PDF
Atch 2_Federal Construction Wage Rates_Story Cty.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 3, 12639525Q0164

Michael.Kuennen Rectangle

Michael.Kuennen Rectangle

Michael.Kuennen Arrow

Michael.Kuennen Arrow

Michael.Kuennen Text Box

USDA-NCAH BUILDING 520 FLOOR COATING REPAIR

Text Box Rooms 105 and 106 have existing epoxy still in place on floor and 4 inch integral cove base that needs to be removed to prepare for the new 3/4" plywood sub-floor, 6 inch integral base and floor coating. Existing doors shall not be modified, but door sweeps may be removed and reinstalled by Contractor as required for ease of installation. Contractor shall provide transition strips as needed at door openings and around floor drains as required.

Michael.Kuennen Text Box Rooms 107 and 108 have most of the existing epoxy coating removed on the floor with a peeling epoxy paint coating. The existing 4 inch epoxy integral base will need to be removed to prepare for the new 3/4" plywood sub-floor, 6 inch integral base and floor coating. Existing doors shall not be modified, but door sweeps may be removed and reinstalled by Contractor as required for ease of installation. Contractor shall provide transition strips at door openings and around floor drains as required.

Michael.Kuennen Text Box Total floor area for new coating is approximately 1,016 SF

Total linear feet of integral base is approximately 202 FT

Michael.Kuennen Arrow

Michael.Kuennen Text Box

NORTH

Michael.Kuennen Text Box

DRAWING A2.0

Michael.Kuennen Text Box Note: The floor drains are not shown as constructed, Room 106 and 108 each have four floor drains, one in each corner on the south side of the rooms and two in-between approximately equally space.

Rectangle

File details come from the government source that posted it. Updated .