Atch 1_SOW Building 520 Floor Coating Repair.doc
DOC document 125 KB Posted
- Attached to
- Epoxy Floor Coating Repair, Ames Federal contract opportunity
- Solicitation number
- 12639525Q0164
About this file
This is a Statement of Work (SOW) for a floor coating repair project at the USDA National Centers for Animal Health in Ames, Iowa. The project involves removing and replacing the existing epoxy floor coating in Building 520, covering approximately 1,016 square feet and 202 linear feet of cove base. The new flooring system will use Stonhard Stonclad GS epoxy for the cove base and Stonchem 441 polyurea-polyurethane hybrid coating with a Pewter color and 90 grit white aluminum oxide texture for traction. The contractor must complete the work within 30 days of room availability, with a total contract period of 180 days, working during normal business hours (7 a.m. to 3:30 p.m.).
Key requirements include submitting product documentation, a project schedule, and safety policy, preparing surfaces using mechanical means with HEPA vacuum systems, and providing a minimum three-year warranty for materials and labor. The project has strict security protocols, including sign-in procedures, identification badges, and restricted site access. The estimated project value ranges between $25,000 and $100,000, with the NAICS code 238330 (Flooring Contractors) and a small business size standard of $19 million. The technical point of contact is Michael Kuennen from the USDA, and the solicitation is managed by Contracting Officer Jim Roloff.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12639525Q0164-0001.pdf | ||
| Site visit sign-in sheet.pdf | ||
| Atch 7_StoncladGS PDS.pdf | ||
| 12639525Q0164.pdf | ||
| Atch 5_Specification Section 096723 Resinous Flooring.docx | DOCX document | |
| Atch 9_ Floor Photos.pdf | ||
| Atch 8_ Stonkote HT4 Product Data.pdf | ||
| Atch 6_Stonchem 441 Product Data.pdf | ||
| Atch 4_G001 Title Page Building 520 Floor Coating Repair.pdf | ||
| Atch 3_Bldg 520 A 2.0 with Blue Beam Markups.pdf | ||
| Atch 2_Federal Construction Wage Rates_Story Cty.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1, 12639525Q0164
Attachment 1, 12639525Q0164
Statement of Work (SOW) Project: Building 520 Floor Coating Repair USDA, National Centers for Animal Health, 1920 Dayton Avenue, Ames, IA 50010
GENERAL INFORMATION
1.0 Background: The USDA, NCAH building 520 located at 1920 Dayton Avenue, Ames, IA is a modular animal research building constructed by Artsway Scientific in 2008 with a 17-year-old epoxy floor coating system that has cracked and deteriorated. This floor needs a new coating. The new floor coating must resist cracking from any structural movement in order to maintain integrity while being easy to clean. The floor coating must also have good traction when wet to prevent caretakers from falling.
2.0 Scope of Work: The work includes removing four-inch epoxy integral base and epoxy floor coating from the existing subfloor. The existing fiberglass mat sealed in resin over ¾” plywood is to remain. New ¾” tongue and grove plywood shall be installed over the existing subfloor fastened with construction adhesive and screws. A troweled Stonhard Stonclad GS epoxy shall be used to form new 6” integral cove base. The new subfloor and 6” cove base shall be coated with a minimum of 30 mils of Stonchem 441 polyurea-polyurethane hybrid coating system with 90 grit texture 12 white aluminum oxide mixed into a suspension with the Pewter colored Stonkote HT4 topcoat and applied in the areas designated on attached drawing A-2.0. Provide and install any necessary transition strips at the door openings or floor drain assemblies as required.
The total area is approximately 1016 square feet, with approximately 202 linear feet of new 6” integral cove base. No gaps or voids shall be present between the new cove base and the wall. Attached are drawings G-001, A-2.0 and Photos 1- 6 with building 520 location, construction route and room details. Per the attached drawing room 105 and 106 will need the existing epoxy floor and cove base coating removed. Rooms 107 and 108 have most of the epoxy floor coating removed with an existing epoxy paint coating but the existing 4” cove base will need to be removed.
CONTRACTOR REQUIREMENTS
3.0 Technical Requirements/Tasks: The contractor is responsible for all labor, material, disposal and equipment to complete the work. The work required to install the new polyurea-polyurethane hybrid coating includes:
1. The length of the contract will be 180 days after award of contract and the work must be completed within 30 days once the rooms are made available.
2. Submit Stonhard STONCLAD GS, STONCHEM 441, STONKOTE HT4 product and Safety Data Sheets for Flooring System – Color = Pewter with 90 grit texture 12 white aluminum oxide mixed into a suspension with the Pewter colored STONKOTE HT4 topcoat. Black aluminum oxide is not acceptable.
3. Provide schedule for the work no later than 10 days after the award of the Contract.
4. Submit contractor safety policy for review by COR at least 10 business days prior to starting work on site.
5. The work must be completed during normal business hours of 7 a.m. to 3:30 p.m. excluding Government Holidays.
6. Contractor is responsible for removing and reinstalling door sweeps as required to complete the floor coating.
7. Contractor is responsible for the restoration or repair of any damages to structures, finishes, site grounds or surroundings. Damages to be restored to the same condition or better at no additional cost to Government.
8. Prepare surfaces in accordance with manufacturer instructions. Any work necessary to use mechanical means (self-contained grinding and /or shotblasting) must have a HEPA vacuum system to collect dust.
9. After removal of the existing epoxy coating and integral base, install grooved ¾” plywood for a new subfloor that is glued with construction adhesive and screwed to the existing floor.
10. Prefill surface irregularities, holes and cracks if necessary.
11. Provide and install any necessary transition strips at door openings or around drain assemblies as required.
12. Trowel new 6” integral base using Stonhard Stonclad GS epoxy per manufacturer instructions.
13. Apply manufacturers primer compatible with the Stonchem 441 product per manufacturer instructions.
14. Apply Stonchem 441 Color: Pewter in a uniform 30 mil thickness.
15. After curing properly prepare and clean the cured Stonhard 441 surface. Apply a suspension of 90 grit texture 12 white aluminum oxide in the Pewter colored Stonkote HT4 to make a uniform traction topcoat. Also apply Pewter colored Stonkote HT4 to the integral base without aluminum oxide.
16. All work to be performed per Manufacturer’s specifications and details.
17. Remove all trash or debris accumulated from completing the work from the site and dispose in a responsible manner.
18. Provide documentation for a minimum of a three-year material and labor warranty that starts after completion of the work.
3.0A Product Specifications
The recommended product to use for the floor coating is Stonhard STONCLAD GS and Stonhard STONCHEM 441 polyurea-polyurethane hybrid, color = Pewter. Traction material shall be 90 grit texture 12 white aluminum oxide mixed in a suspension of Pewter colored Stonkote HT4 and applied as traction topcoat. Black aluminum oxide is not acceptable.
3.0B Warranty/Closeout
Provide a minimum of a three-year warranty for labor to repair faulty workmanship and/or material. The warranty shall start at the completion of the project. The contractor shall provide technical specifications and product information along with the cost proposal.
An award will not be completed until the product has been determined to be acceptable.
3.1 Work Restrictions & Conditions
Site Security Access
a. Access to the construction site is controlled by a security fence and visitor/contractor check-in/check-out system. All contractor/subcontractor employees shall always sign-in and out at the main entrance gate and wear contractor/visitor identification badge at all times while on the site. The ID badges will be turned in at the end of each workday. A current government-issued identification with a picture ID is required for entry. Real ID driver’s license is required.
b. This project construction site is located in the limited access zone.
c. Construction vehicles and a construction trailer will be allowed access adjacent to the work; contractor employee’s personal vehicles shall be parked in the facility parking lots.
d. The Contractor shall use only the service roads and access routes approved by the Contracting Officer’s Representative.
e. Work shall be confined to the areas identified on the Drawings. Unless accompanied by a NCAH/USDA employee, the Contractor, subcontractors, and their employees shall not enter buildings or facilities not specifically part of this project. Reasons included, but are not limited to, disease control and health requirements.
f. Additional security requirements may be imposed when the Federal Government raises the Homeland Security Alert Level. Additional directions will be provided if the situation occurs.
g. Failure to comply with access requirements shall be adequate grounds for removal of the Contractor/subcontractor employees from the site and barring further site access to individuals.
h. No pets or animals are allowed inside the Security Gate, even if left in vehicle.
i. No firearms or weapons are allowed on site.
Work Hours: Regular work hours for the site are 7 a.m. to 3:30 p.m., Monday through Friday, excluding Government holidays. Work outside these hours is not allowed.
3.2 Temporary Facilities
a. Utilities: The existing USDA utilities at the site may be used by the Contractor for completion of the contract work at no cost to the Contractor. The Contractor shall be responsible for making and removing any temporary utility connections.
b. Telephones: The Contractor shall equip all his foremen and work leaders with cell phones as necessary to coordinate the work effort. The Government will not provide any phone service to the project.
c. Construction Trailer: Will be allowed for the Project with location to be coordinated with
COR.
d. Toilet Facilities: Contractor should provide a portable toilet and services to maintain the toilet facilities, placement and removal after the work has been completed. The location is to be coordinated with the COR.
3.3 Warranty Documentation
a. Warranty List: Provide a 3-year warranty summary sheet in spreadsheet format with all warranties listed by section, description, supplier, warranty contact, start date, end date. Provide electronic PDF to COR.
b. Warranty Copies in Binder: Provide the COR one signed & dated copy of all warranties for products and equipment installed on the project. An electronic (scanned) copy of the Warranty Binder in a PDF file shall be submitted with the final close-out documentation.
4.0 Government Furnished:
The existing USDA utilities at the site may be used by the Contractor for completion of the contract work at no cost to the Contractor. The rooms have two 20 Amp. 120V single phase power circuits. The Contractor shall be responsible for making and removing any temporary utility connections. The Contractor may use larger floor preparation equipment with appropriate HEPA vacuum capture system, but they will need to provide their own portable generator, fuel and power cables to operate the equipment outside building 520. Construction trailer may be used for the project with the location coordinated with COR. The COR or Location Coordinator will direct Contractor to park near Building 520 exterior entry and available parking spaces on concrete as directed.
5.0 Deliverables / Schedule
| Item No. |
| Deliverable |
| Objective |
| Due |
| 1 |
| Project Schedule |
| Defining the responsibilities, timeline, risks, and milestones of contract objectives. Ref. Subtask 3.0.3 |
| No later than five (10) business days after contract award |
| 2 |
| Contractor Safety Policy. |
| For review and approval by COR. Ref. Sub Task 3.0.4 |
| Ten business days before starting work on site. |
| 1 |
| Material Submittal |
| Defining the characteristics of the materials used to complete the project. Ref. Subtask 3.0.2 |
| No later than five (10) business days after contract award |
| 2 |
| Warranty |
| For review and approval by COR. Ref. Sub Task 3.0.15, 3.3.1 & 3.3.2 |
| At completion of project. |
6.0 Technical Point of Contact:
Michael Kuennen, Engineering Technician, michael.kuennen@usda.gov
Office Phone: 515-337-7297, Cell Phone: 515-231-4598