ATCH 03 SOW_315972_DISCOVERY CENTER_10.05.20.pdf

PDF 338 KB Posted

Attached to
FORT PICKENS BLDG INTERIOR REPAIRS (H. SALLY)
Solicitation number
140P5221Q0024
Issued by

About this file

This statement of work and related federal contract opportunity describe interior repair work for six facilities at Fort Pickens in Gulf Islands National Seashore. The statement of work requires replacing drywall, ceiling tiles, and wall panels damaged by storms. It also includes remodeling two restrooms. The contractor must provide labor, materials, equipment, and supervision. Estimated value is between $100,000 and $2,500,000. The opportunity is set aside for small businesses in five Florida counties. The National Park Service is seeking a fixed-price contract to restore the interiors to pre-disaster condition within 90 days of notice to proceed. Submittals required include technical proposals, safety plans, and references demonstrating similar past work experience.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW)

FP Repairs of Discovery Center

Statement of Work GUIS Page 1 of 7

GULF ISLANDS NATIONAL SEASHORE

FLORIDA AND MISSISSIPPI

Interior Repairs of Fort Pickens

Discovery Center

PMIS 315972

OCTOBER 2020

NATIONAL PARK SERVICE

SOUTH ATLANTIC GULF REGION

Statement of Work GUIS Page 2 of 7

1. PARK INTRODUCTION

2. PROJECT INTRODUCTION AND OVERVIEW

3. PROJECT TASKS

4. OTHER CONTRACTOR RESPONSIBILITIES

5. GOVERNMENT FURNISHED PROPERTY, MATERIALS & SUPPLIES

6. WORKING HOURS

7. PERIOD OF PERFORMANCE

8. SAFETY & ENVIRONMENTAL COMPLIANCE

9. MOTOR VEHICLE & TRAFFIC REGULATIONS

10. EMPLOYEE IDENTIFICATON BADGES AND PARKING

11. CONTRACTOR’S PROPOSAL PACKAGE REQUIREMENTS

12. SUBMITTAL REQUIREMENTS LIST (POST-AWARD)

13. CONSTRUCTION MONITORING

14. ATTACHMENTS

Acronyms

ASCE American Society of Civil Engineers AWPA American Wood Protection Association CO Contracting Officer COR Contracting Officer’s Representative FBC Florida Building Code FL State of Florida GUIS Gulf Islands National Seashore IBC International Building Code ICC International Code Council MS State of Mississippi NPS National Park Service OSHA Occupational Safety and Health Act PM Project Manager PMIS Project Management Information System SAE Society of Automotive Engineers SOW Statement of Work USACE U.S. Army Corp of Engineers USCG U.S. Coast Guard UV Ultraviolet (Radiation wavelength)

Statement of Work GUIS Page 3 of 7

Interior Repairs of Discovery Center

1. PARK INTRODUCTION

Gulf Islands National Seashore is a place of myriad riches - blue-green, sparkling waters, magnificent white beaches, and fertile coastal marshes. Its 12 areas include historic forts, shaded picnic areas, trails, and campgrounds. From Cat Island, Mississippi, it stretches eastward 160 miles to the Okaloosa Area east of Fort Walton Beach, Florida.

The Gulf of Mexico has shaped, and still shapes American history and culture. During the age of exploration and colonization, Europeans entered the Gulf and laid claim to the New World.

Deepwater anchorages at Pensacola Bay in Florida and at Ship Island in Mississippi supported Spanish, French, and British development along the northern Gulf Coast. The annexation of coastal Mississippi territories in 1804 and Spain ceded its Florida territories to the United States in 1819 setting the stage for the series of events which define American history and established protections for natural and cultural resources preserved by the national seashore. From General Andrew Jackson’s military conquests of Pensacola, to the celebrated artwork of Walter Anderson, to your first splash into the Gulf’s warm emerald waters, people shape and are shaped by the Gulf of Mexico. This complex and storied history motivated Americans in the 20th century to advocate for the creation of Gulf Islands National Seashore, which was established by Congress on January 8, 1971. What follows is for you to help create.

2. PROJECT INTRODUCTION AND OVERVIEW

This project will be to repair or replace damaged ceiling tiles, drywall and wall paneling. All work will be accomplished within the housing units of the Fort Pickens Area. All work shall be accomplished using durable and resilient materials and be designed and fastened in accordance with applicable codes and standards. All work shall be done in accordance with the requirements of this SOW.

Offerors are encouraged to propose process improvements and industry best practices in their proposals.

3. PROJECT TASKS

The Contractor shall provide all labor, tools, equipment, materials and supervision required to complete the following tasks:

Task 1: Replace Drywall and Paint-Discovery Center Library-Sally

• Replace 90 sq. ft of drywall – taped, 3 coat mud application allowing mud to dry between applications and sanded.

• Paint – 1 coat latex primer, two coats interior latex Task 2: Replace Walls Conference Room - FP Discovery Center – Sally

• Replace 18 ft.² of tongue and groove boards and re-tape drywall mud joints and paint

• Paint – One coat of latex interior primer, two coats of interior latex paint in gray

Task 3: Replace Damaged Ceiling Tiles - FP Discovery Center – Sally

• Replace 82 sq. ft. of suspended ceiling tile, 2 x 2

Statement of Work GUIS Page 4 of 7

Project Site Location: Fort Pickens Area, Discovery Center Coordinates: 30°19'45.74"N 87°17'32.78"W (Refer to Attachment A: Project Area Map)

• FP Discovery Center

4. OTHER CONTRACTOR RESPONSIBILITIES

• The Contractor shall submit a Debris Disposal Plan. All demolished materials are the property of the Contractor and shall be disposed of at a licensed/registered debris disposal facility. Refer to the Submittal Section of this document for requirements.

• Contractor shall submit an Inclement Weather Plan describing the procedures that will be carried out in the event that the park starts to prepare for inclement weather. Plan shall detail how equipment and materials will be restrained and secured in order to leave the site in a prepared state for inclement weather. Refer to the Section 12 Submittal requirements.

• Technical Approach with project schedule to describe the work to complete the project.

Contractors are encouraged to provide detailed and specific information on their technical approach to complete the project. Approach shall address each bulleted tasks identified in Section 3. The approach will be evaluated to ensure the contractor possesses a thorough understanding of the work. Approach shall also include a list of subcontractors or list the general contractor, if applicable, that is completing the significant portions of the work. At a minimum, the performing contractor(s) shall be listed that will perform the following tasks:

o A: Carpentry/framing o B. Drywall o C. Painting

• Technical Proposal based on Technical Approach for review and approval as a post-award submittal. Refer to Section 12 for Technical Proposal submittal requirements.

• Demonstration of Qualification to demonstrate technical capability for this project with previous experience. This Demonstration of Qualification requirement is met by providing documentation of previous projects similar in scope to this project. Contractor shall provide five (5) such projects completed within the last five (5) years. To satisfy this requirement and demonstrate capability through previous experience, this Demonstration of Qualification shall include the following documentation for each project:

o A narrative description of the past example project o Location of the project with GPS coordinates o A minimum of two (2) project references with contact information to verify the contractor successfully completed the project on time and on budget Refer to Section 11 for Demonstration of Qualification proposal requirements.

• A completed Schedule of Values based on a project task breakdown is required in the project proposal.

• Government Furnished Property, Materials & Supplies None.

Statement of Work GUIS Page 5 of 7

5. WORKING HOURS

The Contractor shall complete on-site work during normal business hours as specified in the project associated FAR documentation for this project. Working hours shall apply, Monday through Friday, excluding Federal holidays. The Contractor shall coordinate the on-site work schedule with the Contracting Officer (CO) and Contracting Officer Representative (COR) by the submittal and approval of the project schedule. While on site, the COR may be reached by mobile phone during these specified work hours. Any requests to work outside of normal approved hours shall be pre-approved by the CO and COR with a minimum of 72 hours’ notice for request review.

6. PERIOD OF PERFORMANCE

Work shall be completed within 90 days after Contracting Officer issues notice to proceed.

7. SAFETY & ENVIRONMENTAL COMPLIANCE

• The contractor shall submit a Contractor Safety Plan and identify a single Safety Person in Charge with a clear transfer of responsibility in cases when there are alternates. In additional to these requirements, designated person(s) shall meet and demonstrate competency in all Occupational Safety and Health Act (OSHA) standards related to Competent Persons (CP) under 29 CFR 1910 through 1926 for the applicable areas related to this project. The Contractor Safety Plan shall also include a separate subsection for COVID-19 safety provisions to specify the contractor’s methods to address CDC Guidelines while performing the project work.

• The Contractor shall comply with pertinent provisions of the Occupational Safety and Health Act (OSHA), pertinent Environmental Protection Agency (EPA) and state, local, safety, laws.

• The Park Safety Officer shall have the authority to issue stop work orders to the Contractor when violations or unsafe acts are present and threaten Government and Contractor employees or damage to Government property.

• The Contractor shall immediately report to the CO, COR and Park Safety Officer all accidents resulting in employee injury or death or damage to property while performing this contract.

8. MOTOR VEHICLE & TRAFFIC REGULATIONS

Contractor employees operating motor vehicles shall possess a valid state driver's license.

Contractor vehicles and vessels shall be registered and have proof of insurance maintained at all times and made available upon request. Contractor employees shall comply with federal vehicle motor law requiring seat belts be worn at all times. Contractor employees shall adhere to the posted speed limits.

9. EMPLOYEE IDENTIFICATON BADGES AND PARKING

All Contractor employees shall comply with parking procedures published for the Park.

Contractor employees shall return any Park issued personal or vehicle identification badges immediately upon termination of employment or completion of this contract.

Statement of Work GUIS Page 6 of 7

10. CONTRACTOR’S PROPOSAL PACKAGE REQUIREMENTS

In addition to any FAR requirements listed for this proposal package (ie: Bonds, Insurances, etc.), the following deliverables are to be submitted with offer in response to this Statement of Work (SOW). Proposals without these minimum requirements will be considered non-responsive and not be considered for award.

• Total Cost for this Project Proposal with cost breakdown as specified in Section 4 for in the Schedule of Values form

• Technical Approach with the names of subcontractors and

• Demonstration of Qualification by submitting information as specified in Section 4.

11. SUBMITTAL REQUIREMENTS LIST (POST-AWARD)

The following items are to be submitted after the contract award.

• Technical Proposal based on the Technical Approach required as part of the Contractor’s

Proposal Package, submitted for approval prior to starting any work.

• A Debris Disposal Plan with a proposed debris receiving facility listed. The plan shall be submitted as a submittal and shall be approved by the COR prior to starting work. The Debris Disposal Plan shall also include an example method of verification from the facility receiving the waste as part of the submittal.

• Materials Submittals as required in Section 4. All materials used for the project shall first be approved prior to purchase through a material submittal.

• Contractor’s Work Safety Plan with Inclement Weather Plan, COVID safety precautions, and identification of the Competent Safety Person in Charge.

• Project Modification Request Form and Standard Procedure Detail.

12. CONSTRUCTION MONITORING

The Government will conduct contract monitoring during the project. Inspections shall be both random and at identified milestones during the project. These milestones shall be identified during the project schedule submittal and approval procedure. There shall also be a Final Inspection at the completion of the project work. Final payment shall only be processed upon confirming that all noted Contractor performance deficiencies identified during the Final Inspection have been satisfactorily corrected.

13. ATTACHMENTS

Attachment A: Project Area Map

1. Park Introduction
2. Project Introduction and Overview
3. Project tasks
4. OTHER Contractor Responsibilities
5. Working Hours
6. Period of performance
7. Safety & Environmental Compliance
8. Motor Vehicle & Traffic Regulations
9. Employee IDENTIFICATON Badges AND Parking
10. Contractor’s Proposal Package Requirements
11. Submittal Requirements List (Post-Award)
12. CONSTRUCTION MONITORING
13. ATTACHMENTS