The following deliverables are scheduled for the project initiation phase.
| ID # |
| Deliverable Name |
| Due Date/ Frequency |
| 1. |
| Kickoff meeting |
| 15 Calendar Days after Contractor Engagement Start (CES) |
| To be scheduled. |
| 2. |
| Project Work Plan – Final |
| 45 Calendar Days after CES |
| To be created and maintained by new contractor |
| 3. |
| Contract Schedule – Final |
| 45 Calendar Days after CES |
| To be created and maintained by new contractor |
| 4. |
| Risk Management Plan |
| 45 Calendar Days after CES |
| To be created by new contractor |
| 5. |
| Risk Register |
| 45 Calendar Days after CES |
| To be created and maintained by new contractor |
| 6. |
| Project Issue Log |
| 45 Calendar Days after CES |
| To be created and maintained by new contractor |
The following deliverables are scheduled for the project execution phase, including Design, Development and Integration Testing.
| ID # |
| Deliverable Name |
| Due Date/ Frequency |
| 1. |
| Business Requirement Document (BRD) |
| Mutually agreed by the SCM and the Contractor, and approved by the SCM. |
| To be created by new contractor |
| 2. |
| Requirements Traceability Matrix (RTM) |
| Mutually agreed by the SCM and the Contractor, and approved by the SCM. |
| To be created and maintained by new contractor |
| 3. |
| Detailed Functional Design Document (DFDD) |
| Mutually agreed by the SCM and the Contractor, and approved by the SCM. |
| To be created by new contractor |
| 4. |
| Detailed Design Document (DDD) |
| Mutually agreed by the SCM and the Contractor, and approved by the SCM. |
| To be created by new contractor |
| 5. |
| Interface Control Document (ICD) |
| Mutually agreed by the SCM and the Contractor, and approved by the SCM. |
| To be created and maintained by new contractor |
| 6. |
| System Test Plan |
| Mutually agreed by the SCM and the Contractor, and approved by the SCM. |
| To be created by new contractor |
| 7. |
| System Test Case and Test Data |
| Mutually agreed by the SCM and the Contractor, and approved by the SCM. |
| To be created by new contractor |
| 8. |
| System Test Summary |
| Upon system test completion |
| To be created by new contractor |
| 9. |
| Monthly Project Status Report |
| Monthly |
| To be created by new contractor |
| 10. |
| Project Weekly Meeting |
| Weekly |
| To be created by new contractor |
| 11. |
| Project Weekly Status Report |
| Weekly |
| To be created by new contractor |
| 12. |
| Project Monthly Status Summary |
| Monthly |
| To be created by new contractor |
The following deliverables are scheduled for the cloud migration phase.
| ID # |
| Deliverable Name |
| Due Date/ Frequency |
| 1. |
| Cloud Infrastructure Plan – Final |
| 90 Calendar Days after CES |
| To be created by new contractor if not available at the time of contract award |
| 2. |
| Cloud Security Plan - Final |
| 90 Calendar Days after CES |
| To be created by new contractor if not available at the time of contract award |
| 3. |
| Cloud Network Plan – Final |
| 90 Calendar Days after CES |
| To be created by new contractor if not available at the time of contract award |
| 4. |
| Cloud Capacity Plan – Final |
| 90 Calendar Days after CES |
| To be created by new contractor if not available at the time of contract award |
| 5. |
| Cloud System Cutoff Plan – Final |
| 90 Calendar Days after CES |
| To be created by new contractor if not available at the time of contract award |
| 6. |
| Cloud Risk Management Plan – Final |
| 90 Calendar Days after CES |
| To be created by new contractor if not available at the time of contract award |
| 7. |
| Cloud Disaster Recovery Plan – Final |
| 90 Calendar Days after CES |
| To be created by new contractor if not available at the time of contract award |
| 8. |
| Data Migration Plan |
| 90 Calendar Days after CES |
| To be created by new contractor |
| 9. |
| System Logical Architecture Diagram |
| 90 Calendar Days after CES |
| To be transferred from incumbent contractor to new contractor and maintained by new contractor |
| 10. |
| System Physical Architecture Diagram |
| 90 Calendar Days after CES |
| To be transferred from incumbent contractor to new contractor and maintained by new contractor |
| 11. |
| Cloud Migration Weekly Status Report |
| Weekly |
| To be created by new contractor |
| 12. |
| Cloud Migration Monthly Status Summary |
| Monthly |
| To be created by new contractor |
| 13. |
| Cloud Migration Weekly Meeting |
| Weekly |
| To be created by new contractor |
| 14. |
| Cloud Platform Operations Manual/Helpdesk Guide |
| 210 Calendar Days after CES |
| To be created by new contractor if not available at the time of contract award |
| 15. |
| Cloud Migration Validation Result |
| At least three (3) weeks before the end of the cloud migration phase. |
| To be created by new contractor |
| 16. |
| Cloud Migration Completion Certificate |
| At least two (2) weeks before the end of the cloud migration phase. |
| To be created by new contractor |
The following deliverables are scheduled for the UAT phase.
| ID # |
| Deliverable Name |
| Due Date/ Frequency |
| 1. |
| Report Manual |
| 20 Calendar Days before the start of UAT. |
| To be transferred from incumbent contractor to new contractor and maintained by new contractor |
| 2. |
| User Manual |
| 20 Calendar Days before the start of UAT. |
| To be transferred from incumbent contractor to new contractor and maintained by new contractor |
| 3. |
| Training Plan |
| 30 Calendar Days before the start of UAT. |
| To be created by new contractor |
| 4. |
| UAT Readiness Certificate |
| At least 3 Calendar Days before the start of UAT release. |
| To be created by new contractor |
| 5. |
| Production Readiness Certificate |
| At least one (1) week before the start of production release. |
| To be created by new contractor |
| 6. |
| Release Notes (for UAT, and Production only) |
| One (1) week before the deployment of changes to UAT or production. |
| To be created by new contractor |
| 7. |
| Production Implementation Plan |
| 20 Calendar Days before the deployment of changes to production. |
| To be created by new contractor |
| 8. |
| Project Monthly Status Report |
| Monthly |
| To be created by new contractor |
| 9. |
| Project Weekly Meeting |
| Weekly |
| To be created by new contractor |
| 10. |
| Project Weekly Status Report |
| Weekly |
| To be created by new contractor |
| 11. |
| UAT Issue Log |
| Daily |
| To be created by new contractor |
The following deliverables are scheduled for the transition phase.
| ID # |
| Deliverable Name |
| Due Date/ Frequency |
| 1. |
| Transition Plan (Incoming) - Final |
| 45 Calendar Days after CES |
| To be created by new contractor |
| 2. |
| Staffing Plan – Final |
| 45 Calendar Days after CES |
| To be created by new contractor |
| 3. |
| Business Continuity Plan – Final |
| 45 Calendar Days after CES |
| To be transferred from incumbent contractor to new contractor and maintained by new contractor |
| 4. |
| Operations Manual/ Helpdesk Guide |
| At least 90 Calendar Days before the end of the transition phase. |
| To be transferred from incumbent contractor to new contractor and maintained by new contractor |
| 5. |
| System Handoff Certificate |
| At least 20 Calendar Days before the end of the transition phase. |
| To be created by new contractor |
| 6. |
| Monthly System Operations Status Report |
| Monthly |
| To be created by new contractor |
The following deliverables are scheduled for the system operations and maintenance phase.
| ID # |
| Deliverable Name |
| Due Date/ Frequency |
| 1. |
| Monthly System Operations Status Report |
| Monthly |
| To be created by new contractor |
| 2. |
| Monthly Maintenance Plan |
| Monthly |
| To be created by new contractor |
| 3. |
| End-of-Day (EOD) Processes Report |
| Daily |
| To be created by new contractor |
| 4. |
| Quarterly Resource Utilization Report |
| Quarterly |
| To be created by new contractor |
| 5. |
| Weekly Operations Meeting |
| Weekly |
| To be created by new contractor |
| 6. |
| System Issue Tracker |
| Ongoing |
| To be created and maintained by new contractor |
| 7. |
| Transition Plan (Outgoing) – Draft |
| 300 Calendar Days before the Contract ends |
| To be created by new contractor |
| 8. |
| Transition Plan (Outgoing) – Final |
| 240 Calendar Days before the Contract ends. |
| To be created by new contractor |