Appendix A_WPS_Information for Bidders.pdf
PDF 176 KB Posted
- Solicitation number
- IFB1 OAAA 2027000019 3
- Issued by
- Arapahoe County, Colorado
About this file
This is an Information for Bidders document prepared for the Windsor Readiness Center Backup Battery project in Colorado. The document provides guidance and requirements for contractors bidding on this state procurement opportunity. The project involves supplying and installing backup battery systems for the Windsor Readiness Center. Bidders are directed to review all project specifications, scope of work documents, and supporting exhibits included in the bid package. The document outlines the mandatory requirements for bid submission, including documentation of contractor qualifications, experience with similar projects, and compliance with state procurement regulations. Site visits and pre-bid meetings may be scheduled to allow potential bidders to inspect the facility and clarify project requirements with state representatives. All bids must be submitted by the stated deadline, with award anticipated following the evaluation period.
The document establishes pricing terms requiring bidders to provide firm, fixed pricing for the complete backup battery system installation. Bidders must demonstrate financial capability and bonding requirements as specified in the procurement documents. The project may include preferences for in-state contractors or small businesses if applicable under Colorado procurement law. The document references compliance with applicable federal and state regulations, prevailing wage requirements if applicable, and insurance requirements. Bidders should review all addenda and amendments issued prior to the bid deadline, as these documents modify the original specifications and requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SBP-6.12
Rev 7/2025
STATE OF COLORADO
OFFICE OF THE STATE ARCHITECT
STATE BUILDINGS PROGRAM
INFORMATION FOR BIDDERS
Institution or Agency:
Project No./Project Name:
1. BID FORM: Bidders are required to use the Bid form attached to the solicitation.
Each bidder is required to bid on all alternates and indicate the time from the date of the Notice to Proceed to Substantial Completion in calendar days. In addition, the bidder is required to indicate the period of time to finally complete the project from Substantial Completion to Final Acceptance, in calendar days.
Bids indicating times for Substantial Completion and Final Acceptance in excess of the number of days indicated in the Advertisement for Bids for completion of the entire Project may be found non-responsive and may be rejected. The bid shall not be modified or conditioned in any manner. Bids and applicable bid security shall be submitted according to the following instructions:
2. INCONSISTENCIES AND OMISSIONS: Bidders may request clarification of any seeming inconsistencies, or matters seeming to require explanation, in the bidding documents at least three (3) business days prior to the time set for the opening of Bids. Decisions of major importance on such matters will be issued in the form of addendum.
3. APPLICABLE LAWS AND REGULATIONS: All work under this Contract shall comply with the provisions of all state and local laws, approved state building codes, ordinances and regulations which might in any manner affect the work to be done or those to be employed in or about the work. Labor for work shall be governed by the provisions of Colorado law which are hereinafter set forth in Articles 27 and 52 of the General Conditions. This includes the requirements for apprenticeship and prevailing wage on Public Projects. The bidder should be aware that reporting of embodied carbon emissions of eligible materials shall be governed by the provisions of Colorado State Law. This includes the requirements for Environmental Product Declarations (EPDs) that meet the maximum acceptable Global Warming Potential (GWP) limits as established by the Office of the State Architect.
4. BID SECURITY: A bid security of not less than 5% of the bid price is required when the price is estimated to be $50,000 or more. The security shall be a bond by a surety company, the equivalent in cash, or otherwise supplied in a form
SBP-6.12
Rev 7/2025 satisfactory for the State. Noncompliance requires the bid to be rejected as nonresponsive.
5. TAXES: The Bid submitted shall exclude all applicable federal excise or manufacturers’ taxes and all state sales and use taxes as hereinafter set forth in Article 9.3 of the GENERAL CONDITIONS.
6. OR EQUAL: The words “OR EQUAL” are applicable to all specifications and drawings relating to materials or equipment specified. Any material or equipment that will fully perform the duties specified, will be considered “equal”, provided the bid submits proof that such material or equipment is of equivalent substance and function and is approved, in writing. Requests for the approval of “or equal” shall be made in writing at least five (5) business days prior to bid opening. During the bidding period, all approvals shall be issued by the Architect/Engineer in the form of addenda at least two (2) business days prior to the bid opening date.
7. ADDENDA: Owner/architect initiated addenda shall not be issued later than two
(2) business days prior to bid opening date. All addenda shall become part of the Contract Documents and receipt must be acknowledged on the Bid form.
8. METHOD OF AWARD - LOWEST RESPONSIBLE BIDDER: If the bidding documents for this project require alternate prices, additive and/or deductible alternates shall be listed on the alternates bid form provided by the Principal Representative.
Bidders should note the Method of Award is applicable to this Bid as stated below.
A. DEDUCTIBLE ALTERNATES: The lowest responsible Bid, taking into account the Colorado resident bidder preference provision of Colorado law, will be determined by, and the contract will be awarded on the base bid combined with deductible alternates, accepted in numerical order as listed in the Bid Alternates Form provided by the Principal Representative. The subtraction of alternates shall result in a sum total within available funds. If this bid exceeds such amount, the right is reserved to reject all bids. An equal number of alternates shall be subtracted from the base bid of each bidder within funds available for purposes of determining the lowest responsible bidder.
B. ADDITIVE ALTERNATES: The lowest responsible Bid, taking into account the Colorado resident bidder preference provision of Colorado law, will be determined by and the contract will be awarded on the base bid combined with additive alternates in numerical order in as listed in the Bid Alternates Form provided by the Principal Representative. The addition of alternates shall result in a sum total within available funds. If this bid exceeds such amount, the right is reserved to reject all bids. An equal number of alternates shall be added to the base bid of each bidder within funds available for purposes of determining the lowest responsible bidder.
C. DEDUCTIBLE AND ADDITIVE ALTERNATES: Additive alternates will not be used if deductible alternates are used and deductible alternates will not be used if additive alternates are used.
9. NOTICE OF CONTRACTOR’S SETTLEMENT – Agencies/institutions must indicate in the initial Solicitation where settlement will be advertised in electronic media.
| INFORMATION FOR BIDDERS |
| DEDUCTIBLE ALTERNATES: The lowest responsible Bid, taking into account the Colorado resident bidder preference provision of Colorado law, will be determined by, and the contract will be awarded on the base bid combined with deductible alternates, accepted in numerical order as listed in the Bid Alternates Form provided by the Principal Representative. The subtraction of alternates shall result in a sum total within available funds. If this bid exceeds such amount, the right is reserved to reject all bids. An equal number of alternates shall be subtracted from the base bid of each bidder within funds available for purposes of determining the lowest responsible bidder. |
| ADDITIVE ALTERNATES: The lowest responsible Bid, taking into account the Colorado resident bidder preference provision of Colorado law, will be determined by and the contract will be awarded on the base bid combined with additive alternates in numerical order in as listed in the Bid Alternates Form provided by the Principal Representative. The addition of alternates shall result in a sum total within available funds. If this bid exceeds such amount, the right is reserved to reject all bids. An equal number of alternates shall be added to the base bid of each bidder within funds available for purposes of determining the lowest responsible bidder. |
| DEDUCTIBLE AND ADDITIVE ALTERNATES: Additive alternates will not be used if deductible alternates are used and deductible alternates will not be used if additive alternates are used. |
| TextInput.136: Department of Military and Veterans Affairs |
| TextInput.182: 082506/ Windsor Peak Shaving |
| Submission Instructions: Send an email to https://colorado.app.box.com/f/f3d0e9f60c7242dda4d140960a07eac1 attaching the bid as a zip folder. Bids sent by other methods will not be accepted. The Zip folder must be titled with the Invitation for Bid (IFB) Number, IFB Title, and the Offeror’s name as noted below: |
082506_ Windsor Peak Shaving_ Company Name
File details come from the government source that posted it. Updated .