Appendix 7 - Test_Report_Template.docx

DOCX document 40 KB Posted

Attached to
History Hub - External Support Community System
Solicitation number
88310322Q00053
Issued by

About this file

This request for quotation solicits proposals for a software as a service solution with out-of-the-box capabilities for the National Archives and Records Administration's customer support community, History Hub. The performance work statement in Attachment 2 outlines the required functionality to support NARA's external user base. Quotations are due by 4:00 PM ET on April 27, 2022. Evaluation will consider factors such as technical approach, past performance, and price. The base period of performance is one year with four one-year options. The National Archives and Records Administration will award a firm-fixed-price contract to the offeror representing the best value based on the evaluation criteria.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

<PROJECT TITLE>

TEST REPORT

<Version Number> for the

NATIONAL ARCHIVES AND

RECORDS ADMINISTRATION

<Draft or Final> <Date>

PREPARED BY:

<Testing Organization>

Document Change Control Sheet

Document Title: <Project Title>

Date
Filename/Version #
Author
Revision Description

TABLE OF CONTENTS

Document Change Control Sheetii
1.0INTRODUCTION4
1.1Purpose4
1.2Test Overview4
1.3Acronyms and Definitions4
2.0OVERVIEW OF TEST ACTIVITIES5
2.1Test Schedule5
2.2Goals and Objectives6
2.3Test Activities6
3.0SUMMARY OF TEST RESULTS6
3.1Defect Summary6
3.2Test Result Summary7
3.3Issues and Concerns7
APPENDIX A. <Project Title> UAT Requirement Status8
APPENDIX B: <Project Title> Open Defects9
APPENDIX C: <Project Title> CLOSED Defects10

LIST OF TABLES

Table 1-1: Acronyms List5
Table 2-1: Test Milestones5
Table 3-1: <Project Title> Defects Summary6

<Project Title> Test Report

INTRODUCTION

This <Project Title> Test Report (TRP) document addresses the results of the testing performed in support of the National Archives and Records Administration (NARA) <Project Title> program. The TRP covers the testing performed by the NARA Information Quality Assurance Test (IQT) Team.

Purpose This document provides a summary of the evaluation and verification results from testing the <Project Title>. Specifically, this report documents the following:

· An overview of the acceptance testing results;

· Requirements pass/fail overview;

· Overview of the defects status; and

· A list of issues and concerns.

This report focuses on the test results and status based on the testing performed.

Test Overview Provide a description of each of the NAC R1 functional capabilities and the test strategy used to ensure quality of the system.

NARA User Acceptance Testing (UAT) consisted of a rigorous verification of the delivered product based on the <Project Title> System Requirements Specification (SyRS), Government Furnished Information (GFI) documents, and developer contractor design documents. Regression testing was performed with each new build to ensure that no new faults were introduced into the system by the deployment of the modified code as the result of an enhancement, patch, or configuration change. The coverage of the regression testing depended on the availability of scheduled time.

Provide an overview of the deliveries and the testing performed.

Acronyms and Definitions Provide a table with a list of acronyms along with full names that are utilized within this document.

ACRONYM
DESCRIPTION
AT
Acceptance Test
CAT
Customer Acceptance Test
ERA
Electronic Records Archives
HTTPS
Hypertext Transfer Protocol Secure
IBM
International Business Machines
IQT
Information Quality Assurance Test
NARA
National Archives and Records Administration
SIT
System Integration Testing
SWIT
Software Integration Testing
TDL
Technical Direction Letter
TP
Test Plan
TRP
Test Report
TSP
Testing Management Plan
UAT
User Acceptance Test

Table 1-1: Acronyms List

OVERVIEW OF TEST ACTIVITIES

The goal of UAT is to provide NARA a sufficient level of confidence that the delivered <Project Title> meets the required objectives and acceptance criteria. This is accomplished by determining the verification and evaluations that must be covered by the testing activities for this project that will demonstrate that the system is ready for use. This section details the test activities to achieve this objective.

Test Schedule This section should include a list of key milestones for all test phases covered by this test plan. All dates should be the actual completed date. The last activity for testing will be the Test Report covering the test results. A timeline is presented in Table 2-1, Test Milestones. Reference the project Integrated Schedule for the specific dates.

Below is an example of the Test Milestones table:

Milestone
Date
NARA Test Plan
05/25/2015
NARA Testing Start
06/01/2015
NARA Testing Complete
06/25/2015
NARA Go/No Go Recommendation
06/25/2015
NARA Test Status Report
06/30/2015

Table 2-1: Test Milestones Goals and Objectives The objective of the test process was to demonstrate that the <Project Title> system is operationally ready for use, to determine the extent to which the <Project Title> has met the requirements, and to evaluate the delivered system and products to see if they met the Program Management expectations:

· Ensure the system satisfies user requirements and expectations;

· Identifying discrepancies, deficiencies, and limitations;

· Verify interfaces;

· Demonstrate operational capabilities and prove adequacy of documentation;

· Ensure usability of the system; and

· Ensure the highest quality of the <Project Title> system and code quality

Before acceptance testing began the application had gone through a comprehensive testing effort from the Vendor, which included unit/string, integration, and system testing. Acceptance testing is designed to provide an additional level of confidence and demonstrate that the <Project Title> system is operating as desired.

Test Activities Describe the overall strategy of the testing. Identify the methods and criteria used in performing test activities. Define the specific methods and procedures for each type of test. Provide a list of functions (applications, subsystems) that will be verified during the execution of this test plan.

SUMMARY OF TEST RESULTS

Verification of the <Project Title> was based on performing not only the Development Contractor delivered Test Procedures but also performing NARA Test Team developed regression test procedures.

Defect Summary At the conclusion of testing of <Project Title> on <Month Day, Year>, there were a total of <number> defects identified during the NARA AT. All defects were fixed by the Development Contractor, and retested and closed by NARA Test Team. Table 3-1 <Project Title> Defects List represents the issues identified during testing.

Severity
Open

(NARA)

Closed

(NARA)

Open (User) Closed (User) Open (Vender) Closed (Vender) Total

1
0
0
0
0
0
0
0
2
0
0
0
0
0
0
0
3
0
0
0
0
0
0
0
Total
0
0
0
0
0
0
0

Table 3-1: <Project Title> Defects Summary

Test Result Summary On <Month Day, Year>, the NARA Test Officer sent out email regarding the <Project Title> Final Acceptance Test Status, and provided a Go Recommendation for deployment.

Provide an overview of the test results.

Total Number of New Requirements: xxx

Passed:xxx
Failed:xx

Requirement in Appendix A.

Issues and Concerns Provide a list of the issues and concerns that were found during the execution of this test.

APPENDIX A. <Project Title> UAT Requirement Status

The following table show the Pass/Fail coverage along with the complete text of each requirement. If a requirement was “Failed” the associated defect is listed in the “Comments” column if the UAT team identified the defect. It should be noted that if a requirement failed then by default the parent requirement will also be marked as Failed since partial Pass is not an accepted Test Status. The status of each <Project Title> requirement is listed in the following table:

APPENDIX B: <Project Title> Open Defects

The following table contains a list of all open defects at the completion of <Project Title>on <Date>. The resolution status reflects a sub-status of the opened defect. The listed open defects include issues identified by the users.

APPENDIX C: <Project Title> Closed Defects

The following table contains a list of all closed defects at the completion of AT on <Date>. The listed closed defects include issues identified by the users.

File details come from the government source that posted it. Updated .