APPENDIX_1_-_Permits.pdf

PDF 322 KB Posted

Attached to
Pass A Grille Way and Gulf Way from 9th Ave. to 22nd Ave Water Improvement: Phase 2
Solicitation number
23-0030-ITB-CONSTRUCTION STEP 2
Issued by
Pinellas County, Clewiston City, Florida

About this file

This document is a Permit Index for the Pass-A-Grille Way and Gulf Way Water Main Improvements Project (P.I.D. No. 004573A), involving multiple agencies including the Florida Department of Environmental Protection, City of St. Pete Beach, and Pinellas County. The permit index outlines the permitting requirements for the water main replacement project, which includes obtaining various permits such as a Right of Way Use Permit from the City of St. Pete Beach and potential Dewatering and National Pollutant Discharge Elimination System (NPDES) Permits to be issued to the contractor after the pre-construction meeting.

The Florida Department of Environmental Protection has provided an exemption for the Potable Water Permit, noting that no construction permit is required for replacing an existing water main with a new main at the same location, provided the new main meets specific size requirements. The awarded contractor will be responsible for ensuring compliance with water quality protocols, pressure testing, and disinfection of new potable water components. The project does not eliminate the need for obtaining other federal, state, or local permits, and any deviations from the proposed plan may require additional permit review.

View the file

Other files

File Type Posted
Section_F_-_Bid_Submittal_Sheet-protected.xls XLS spreadsheet
Addendum_No._1-23-0030.pdf PDF
Plans.pdf PDF
ITB.pdf PDF
Section_I_-_Agreement.pdf PDF
Section_E_-_Technical_Specifications.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX 1

PERMITS

PASS-A-GRILLE WAY AND GULF WAY FROM 9th AVE. TO 22nd AVE. WATER MAIN IMPROVEMENTS

PROJECT

(P.I.D. No. 004573A)

PERMIT INDEX

AGENCY PERMIT No. PERMIT FEE / OTHER

Florida Department of Environmental Protection

– Potable Water Permit

Exemption Received (see attached)

Exempted from FDEP Water Permit.

The awarded contractor must implement the County Water quality protocol.

City of St. Pete Beach – Right of Way Use Permit

Before construction commences, awarded contractor will need to secure ROW Utilization Permit from the City of St. Pete Beach. The City is fully aware of this project.

Pinellas County Habitat Management Permit

N/A N/A

Dewatering Permit Issued to Contractor following the Pre-construction Meeting if applicable or as directed by the County

Awarded contractor's responsibility

National Pollutant Discharge Elimination System (NPDES) Permit

Issued to Contractor following the Pre-construction Meeting if applicable or as directed by the County

Awarded contractor's responsibility

Information regarding Pinellas County’s permits:

Chapter 166 - ENVIRONMENTAL AND NATURAL RESOURCE PROTECTION | Code of Ordinances | Pinellas County, FL | Municode Library https://library.municode.com/fl/pinellas_county/codes/code_of_ordinances?nodeId=PTIIILADECO_CH166ENNAREPR_ARTIIHAMAPR_DIV2PE_S166-81GEPEAPPR https://library.municode.com/fl/pinellas_county/codes/code_of_ordinances?nodeId=PTIIILADECO_CH166ENNAREPR_ARTIIHAMAPR_DIV2PE_S166-81GEPEAPPR

Pissarides, Stephanie R

From: Lopez, Karla A <Karla.A.Lopez@FloridaDEP.gov>

Sent: Tuesday, January 11, 2022 11:34 AM

To: Nestor Murray

Cc: SWD_WF_Permitting

Subject: FW: Water permitting Determination Inquiry

Attachments: image001.jpg; You've been sent large files

Greetings, Thank you for your inquiry regarding permitting requirements for the proposed project.

Potable Water Permit Determination

Based on the information provided, no Department permit is required for the Potable Water portion of the proposed construction.

Pursuant to Rule 62-555.520(1)(c)2, of the Florida Administrative Code (F.A.C.), no Department construction permit is required for replacement of any existing water main with a new main at the same location as the existing main, provided the new main will be either the same size as the existing main, no more than two sizes larger than the existing main, or no larger than the minimum size required or recommended in

Recommended Standards for Water Works as incorporated into Rule 62-555.330, F.A.C.

Please note however, in accordance with 62‐555.520(1)(c), F.A.C., that suppliers of water are responsible for ensuring that potable water work that does not require a permit nevertheless complies with all standards applicable to potable water construction that does require a Department construction permit. Specifically, suppliers of water are required to pressure test and disinfect new potable water components with monitoring

(bacteriological testing) to confirm that satisfactory disinfection was achieved before placing new potable water components into service.

Additionally, this determination does not, eliminate the necessity for obtaining any other federal, State, or local permits that may be required for the construction if this potable water mains. Any deviations from the plan proposed to the Department may require another permit determination review.

Should you have any questions, please feel free to contact me directly.

Thank you, Karla A Lopez

Engineering Specialist I

Southwest District

Florida Department of

Environmental Protection

Karla.A.Lopez@FloridaDEP.gov

Office: (813) 470-5936 mailto:Karla.A.Lopez@FloridaDEP.gov mailto:Karla.A.Lopez@FloridaDEP.gov

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

PLEASE NOTE: Florida has a very broad public records law. Most written communications to or from state owned e-mail accounts are considered to be public records and will be made available to the public or the media upon request.

Therefore, your e-mail messages may be subject to public disclosure.

Please consider the environment before printing this e-mail.

From: Nestor Murray <NMurray@mckimcreed.com> Sent: Monday, January 10, 2022 1:50 PM To: SWD_WF_Permitting <SWD_WF_Permitting@dep.state.fl.us>

Cc: Howerton, Ali <Ali.Howerton@FloridaDEP.gov> Subject: RE: Water permitting Determination Inquiry

I'm using Mimecast to share large files with you. Please see the attached instructions.

Hi, Please see attached the FDEP Exemption Letter and 90% Project Plans for your review and approval.

Respectfully, Nestor

Nestor Murray | Senior Project Manager

T 727.442.7196 | M 813.812.4391

1365 Hamlet Avenue, Clearwater, FL 33756-3331

NMurray@mckimcreed.com | www.mckimcreed.com

Voted "Best Firm To Work For" - Zweig Group mailto:NMurray@mckimcreed.com mailto:SWD_WF_Permitting@dep.state.fl.us mailto:Ali.Howerton@FloridaDEP.gov mailto:NMurray@mckimcreed.com http://www.mckimcreed.com/