A3_Project_Specs_Preston_Peak.pdf
PDF 372 KB Posted
- Attached to
- Preston Peak Barracks Emergency Repair Federal contract opportunity
- Solicitation number
- AG-9AC7-S-16-0093
About this file
A3 Project Specs
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A3_Drawings_05-25-2016.pdf | ||
| A3_Asbestos_Survey_and_Report_Preston_Peak.pdf | ||
| A3_SF30.pdf | ||
| Amendment_000002_Preston_Peak.pdf | ||
| SF30.pdf | ||
| A1_Preston_Peak_Asbestos_Report.pdf | ||
| A1_Preston_Peak_Updated_Specs_Emerg_51216_.pdf | ||
| 1._Updated_Project_Specs_Preston_Peak.pdf | ||
| 3._CA41 _Mod_0 _01082016.pdf | ||
| 2._Photos _Maps_ _Drawings_updated.pdf | ||
| AG-9AC7-S-16-0093_Solicitation.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HAPPY CAMP - PRESTON PEAK BARRACKS RECONSTRUCTION SPECIAL PROJECT SPECIFICATIONS
Amendment 003 Page 1 of 56
Table of Contents
SECTION 01010 - SUMMARY OF WORK
SECTION 01060 - REGULATORY REQUIREMENTS
SECTION 01340 - SUBMITTALS
SECTION 01640 - PRODUCT HANDLING
SECTION 01711 - CLEAN UP AND DISPOSAL
SECTION 02080 – ASBESTOS ABATEMENT
SECTION 06100 - ROUGH CARPENTRY
SECTION 06200 - FINISH CARPENTRY
SECTION 06400 - ARCHITECTURAL WOODWORK
SECTION 07190 - BUILDING PAPER
SECTION 07311 - ROOFING
SECTION 07600 - FLASHING AND SHEET METAL
SECTION 09260 - GYPSUM DRYWALL SYSTEM AND FINISHES
SECTION 09900 - PAINTING
SECTION 15400 - BUILDING PLUMBING
SECTION 16010 - GENERAL PROVISIONS ELECTRICAL
List of Attachments:
• Preston Peak Barracks Emergency Repairs (11x17 Drawings -1957 as-built markups)
• Happy Camp Vicinity Map
• Happy Camp Location Map
• Happy Camp Site Map
• Photos
Amendment 003 Page 2 of 56
SECTION 01010 - SUMMARY OF WORK
PART 1 GENERAL
1.01 SCOPE: Furnish all labor, equipment and materials required to renovate or repair facility as described in the contract documents. The work includes, but is not limited to, removing existing shingles, roof sheathing/1x decking and roof framing as delineated on contract drawings, removing existing ceiling joists, drywall and insulation in the two southeast bedrooms at the front of the building and any others that show damage, remove any loose or unstable bricks from existing chimney in attic space, disconnect and remove existing wiring that is impacted by roof and ceiling removal, remove drywall in two bedrooms complete, including walls, closets and ceilings, removing existing gutters and soffit boards from east wing of building, and removing any damaged siding (see drawings. Additionally the work includes but is not limited to running new electrical circuits back to circuit panel, and installing fixtures to replace ones removed, installing new drywall, installing new ceiling joists, roof framing, sheathing/decking and metal shake shingles, installing new attic and wall insulation in areas with replaced drywall, installing new gutters, downspouts and soffit, and repairing hole and metal shake shingles in front porch roof overhang.
All drywall on walls and ceilings shall be tape, textured and painted to match existing. All work shall be done in accordance with the contract documents and applicable state and local adopted building, electrical and plumbing codes. All material removed from building becomes property of the contractor and shall be disposed of properly outside of the National Forest.
Note: It is anticipated that drywall materials and flooring materials will contain asbestos in the work areas (two front bedrooms). An asbestos sampling and testing report will be made available as part of this contract (see attachments). Removal and disposal of drywall and flooring material (as applicable) will be performed in accordance with Section 02080 ASBESTOS ABATEMENT, and as applicable, the CAC asbestos sampling and testing report. No other testing of materials was conducted. Plans show that this structure was originally constructed in the 1930s with renovations in the 1940s and 1950s. It shall be noted that most homes built before 1978 contain some lead-based paint. All precautions shall be taken to protect the workers, occupants and environment from any potentially harmful effects of any and all construction materials. It is the contractors’ responsibility to be aware of any potentially harmful materials and conduct their work accordingly, mitigating any harmful effects through proper removal and disposal methods in accordance with all applicable local, state and federal regulations.
List of Attachments:
• Preston Peak Barracks Emergency Repairs (11x17 Drawings -1957 as-built markups)
• Happy Camp Vicinity Map
• Happy Camp Location Map
• Happy Camp Site Map
Amendment 003 Page 3 of 56
• Photos
• Asbestos Testing Report
1.02 CODES AND STANDARDS: All work shall be done in accordance with the 2010 California Building Code, 2010 California Plumbing Code, 2010 California Electrical Code, 2010 California Mechanical Code, 2010 California Fire Code, 2010 California Energy Code, and 2010 Architectural Barriers Act (ABA) as specified elsewhere herein.
1.03 GOVERNMENT FURNISHED: Power and water are on the site for use by the Contractor.
Restrooms for construction workers shall be provided by the Contractor. Contractor shall be responsible for locating and protecting above and below ground utilities in the project areas.
1.04 WORK COORDINATION: The Contractor shall coordinate the work, scheduling and traffic control with the Contracting Officer. Pavement, buildings, landscaping and other improvements shall be protected by the contractor. The contractor shall be responsible for repairing any damage to improvements. All demolished materials generated by the work shall be removed from government land and disposed of by the contractor.
1.05 LOCATION: The project is located at the US Forest Service’s Lower Station Compound, Preston peak Barracks owned by the Klamath National Forest. The barracks is located at 64312 Second Avenue Happy Camp, California 96039. Refer to project map on the plans
1.06 MEASUREMENT AND PAYMENT: Measurement will be by the completed job and payment will be on a Lump Sum Unit Basis as provided for in Section B. Such payment will be considered full compensation for providing all materials, labor, equipment, tools and incidentals associated with the work.
PART 2 PRODUCTS
2.01 MATERIALS: AS SHOWN ON THE DRAWINGS and as specified elsewhere herein.
PART 3 EXECUTION
3.01 AS SHOWN ON THE DRAWINGS and specified elsewhere herein.
3.02 – Roof Structure
• Remove damaged roof assembly as outline on drawings, protecting any existing ductwork or utilities.
• Remove damaged ceiling joists and associated ceiling drywall.
• Remove wiring and fixtures in attic space and on ceiling areas to be removed.
Amendment 003 Page 4 of 56
• Install new roof framing and ceiling joists to match existing and as shown in contract drawings.
New roof sheathing shall match existing pattern, dimensions and spacing of existing 1” nominal planks.
• Submit proposed framing plan to contracting officer for approval prior to performing framing work. Care shall be taken to match existing roof plane with new construction. Note: the existing structure is declared historic and all work on it shall be in accordance with 36 CFR, part 68.
• Patch nail holes in existing metal shakes not slated for removal.
• Install new R-30 batt insulation.
• Install new electrical circuits and fixtures to replace ones removed during demolition. Circuits shall not be spliced and shall run back to panel box.
• Install new metal shake roofing to match existing. Metal Shakes shall be TimberCreek Shake, 26 gauge galvanized steel with “Maple” ThermoBond finish. Manufactured by Classic Products.
• Roofing underlayment shall be 30# felt.
• Install new roof sheathing to match existing.
3.03– Exterior Siding
• Remove existing damaged siding, soffit, exposed insulation, and fascia. Dispose of all elements properly off of Forest Service property. Furnish and install new R-13 bat insulation where existing siding is removed and install new siding and building paper (or house wrap). Siding shall match existing. May require milling. Color and pattern to closely match existing siding. Siding to meet salient features described in section 094626 and building paper to meet specifications of section 07190.
• Existing soffit boards shall be removed and replaced with new boards matching existing and as per contract drawings. Soffits and siding shall be painted to match existing in accordance with section 09900.
• Existing gutters and downspouts shall be removed from south, east and north portion of building and replaced with gutter and downspout system of continuous extruded galvanized steel. Color to match existing. Install gutter support blocking at maximum spacing of 32” O.C. to position and secure gutter to soffit and rafters.
3.05 – Bedrooms
• Remove & dispose of existing drywall in ceiling and walls that show signs of cracking and damage. Furnish and install new ceiling and walls as needed. New ceiling to be 5/8” tape and textured drywall. Ceiling to be painted after texturing. Paint surfaces with two coats of acrylic latex paint. Contracting officer to approve paint prior to application. Ceilings shall be eggshell.
Walls to be satin. Follow manufacturer’s application instructions. Spray applications shall be back-rolled. Paint wall and ceiling surfaces with two coats of acrylic latex paint. Contracting officer to approve paint prior to application. Drywall removed on any wall shall be removed completely and replaced, at a minimum, to the nearest corner transition point (floor to ceiling, wall corner to wall corner.
Amendment 003 Page 5 of 56
• Furnish and install new 90V-130V LED light fixture(s) and associated to replace fixture(s) removed with ceiling. Light fixture to be approved by the contracting officer. Light fixture shall be energy star compliant. Furnish and install a combination smoke alarm and carbon monoxide (CO) detector in each room. Smoke alarm/CO Detector shall wired in series and have a 10-year lithium battery backup.
• Install new baseboard to match existing on walls where drywall was removed.
END OF SECTION
Amendment 003 Page 6 of 56
SECTION 01060 - REGULATORY REQUIREMENTS
PART 1 - GENERAL
1.01 SCOPE: This section describes the codes and standards which apply to the work in this contract.
Additional codes and standards may apply as specified elsewhere in the specifications.
1.02 CODES AND STANDARDS
A. The codes and standards applicable to the work in this contract shall include, but not necessarily limited to the following:
1 Building Code: 2010 CBC (2010 California Building Code – CCR Title 24, Part 2) 2 Plumbing Code: 2010 CPC (2010 California Plumbing Code – CCR Title 24, Part 5) 3 Electrical Code: 2010 CEC (2010 California Electrical Code – CCR Title 24, Part 3) 4 Mechanical Code: 2010 CMC (2010 California Mechanical Code – CCR Title 24, Part 4) 5 Fire Code: 2010 CFC (2010 California Fire Code – CCR Title 24, Part 9) 6 Energy Code: California Energy Compliance 2010 (2010 California Energy Code – CCR Title 24, Part 6) 7 Architectural Barriers Act (ABA) 8 American Institute of Steel Construction (AISC) latest edition.
9 American Society for Testing & Materials (ASTM) latest edition.
10 Underwriter's Laboratories, (UL) 11 Architectural Aluminum Manufacturers Association (AMMA) 12 Steel Door Institute, Standard 100 13 American Water Works Association (AWWA) 14 National Fire Protection Association (NFPA) 101 Life Safety 15 American Gas Association (AGA) 16 Standard Specifications for Roads & Bridges on Federal Projects 17 American Association of State Highway and Transportation Officials (AASHTO) Standard Specifications
B. Unless otherwise specified in this contract, reference to a specific standard or specification shall mean the latest edition or amendment in effect on the date of the invitation to bid.
1.03 DEFINITIONS: Administrative Authority as used in the Uniform Mechanical Code, the Uniform Plumbing Code, the National Electrical Code, the International Building Code and Uniform Fire Code will be the Contracting Officer.
1.04 MEASUREMENT AND PAYMENT: No separate measurement or payment will be made for the work of this section.
PART 2 – PRODUCTS NOT APPLICABLE
PART 3 – EXECUTION NOT APPLICABLE
Amendment 003 Page 7 of 56
SECTION 01340 - SUBMITTALS
PART I GENERAL
1.01 SCOPE: This work consists of furnishing samples, shop drawings, pertinent data, catalog cut sheets and the submittal of technical information, including requests for substitutions. It describes the review time for submittals, shop drawings, and substitutions.
1.02 MEASUREMENT AND PAYMENT: No separate measurement or payment will be made for the work specified in this section.
PART 2 PRODUCTS
Not Applicable
PART 3 EXECUTION
3.01 SUBMITTALS
A. Samples: Provide samples, unless otherwise specified or directed by the Contracting Officer, identical to the article proposed and of sufficient size to demonstrate design, color, texture and finish. Samples for the following shall be provided:
1. Shingles
2. Gutters
3. Base molding
4. Electrical fixtures
5. Textured walls and painted surfaces
6. Others as required elsewhere herein
B. Shop Drawings: Provide three sets of blueline or blackline prints, including one reproducible, as required elsewhere herein. Make drawings accurately and to a scale large enough to show all pertinent aspects of the item and its connection to the work. Shop drawing, specifications and construction drawings shall be submitted as specified and shall show any revision date.
C. Catalog Data: Provide catalog cuts, data, pertinent information and other items specified or as directed by the Contracting Officer. Clearly indicate by circling or highlighting each Item.
3.02 APPROVALS: Approval of satisfactory samples, substitutions and shop drawings will be made within 14 calendar days of the receipt of the submittal. Upon approval two copies of the approved shop drawings, samples and other items will be returned to the contractor. The Contracting Officer will retain the reproducible.
3.03 RESUBMITTAL: When a resubmittal is required, one print so indicating will be returned to the Contractor. After revisions of the original, three new copies including one reproducible shall be submitted for approval.
Amendment 003 Page 8 of 56
3.04 TIMING: Make submittals far enough in advance of the scheduled dates of installation to provide time for reviews, for securing necessary approvals, for possible revisions and resubmittals and for placing orders and securing delivery.
3.05 No portion of the work requiring a shop drawing, sample, or catalog data shall be started nor shall any materials be fabricated or installed prior to the approval of such Item.
Amendment 003 Page 9 of 56
SECTION 01640 - PRODUCT HANDLING
PART 1 GENERAL
1.01 DESCRIPTION: Work includes protecting products scheduled for use in the work by means including, but not necessarily limited to, those described in this section.
1.02 QUALITY ASSURANCE: Include within the Contractor's quality assurance program such procedures as are required to assure full protection of work and materials.
1.03 TESTING LABORATORY RECOMMENDATIONS: Except as otherwise approved by the Contracting Officer, determine and comply with testing Laboratory's recommendations on product handling, storage and protection.
1.04 PACKAGING:
A. Delivery of products to the job site:
1. Maintain packaged materials with seal unbroken and labels Intact until time of use.
2. Promptly remove damaged material and unsuitable items from the job site, and promptly replace with material meeting the specified requirements, at no additional cost to the Government.
B. The Contracting Officer will reject as non-complying such material and products that do not bear identification satisfactory to the Contracting Officer as to grade, quality, and other pertinent information.
1.05 PROTECTION:
A. Protect finished surfaces over which equipment and materials are handled.
B. Maintain finished surfaces suitably protected until accepted by the Government.
1.06 REPAIRS AND REPLACEMENTS:
A. In event of damage, promptly make replacements or repairs to the item as directed and approved by the Contracting Officer and at no additional cost to the Government.
B. Additional time required to secure replacements and to make repairs will not be considered by the Contracting Officer to justify an extension of the contract time.
1.07 MEASUREMENT AND PAYMENT: No separate measurement or payment will be made for work specified in this section.
PART 2 PRODUCTS - NOT APPLICABLE
PART 3 EXECUTION - NOT APPLICABLE
Amendment 003 Page 10 of 56
SECTION 01711 - CLEAN UP AND DISPOSAL
PART I GENERAL
1.01 SCOPE: This work consists of the cleanup required in areas affected by the construction, the final cleanup of the project, and the disposal of refuse and excess material resulting from construction operations.
1.02 MEASUREMENT AND PAYMENT: No separate measurement or payment will be made for the work specified in this section.
PART 2 PRODUCTS
2.01 PRODUCTS: All cleaning materials and equipment used shall be selected and used with care to avoid scratching, marring, defacing, staining or discoloring the surfaces cleaned.
PART 3 EXECUTION
3.01 EXCESS MATERIALS AND REFUSE: All refuse and unused materials generated by the Contractor's operations including wood, asphalt, concrete, vegetative materials and the like shall be removed from the project site and disposed of off Government land in accordance with local regulations.
3.02 CLEAN–UP DURING CONSTRUCTION: The Contractor as required to prevent accidents to personnel and protect all work in-place shall perform clean-up. Construction clean-up shall consist of the removal of all dirt, trash, scrap, debris, and excess materials from any floor space or walking surface that may cause the tripping or sliding of workers, ladders, equipment and the like.
3.03 FINAL CLEAN-UP: Immediately prior to the Contractor's request for final inspection of the project, a thorough final cleanup of the entire project site shall be performed.
3.04 QUALITY OF CLEAN-UP: In addition to the normal "broom clean" requirements, the exposed surfaces of the following materials shall be cleaned as listed below:
A. Glass: Remove excess putty, stickers and paint and then wash, and polish.
B. Painted Surfaces: Remove marks, stains, fingerprints, and dirt.
C. Roof: Remove all dust, dirt, and debris. Clean all gutters.
D. Hardware: Clean and polish.
E. Site: Remove all trash, debris, and surplus excavated material. No items shall be left or discarded elsewhere on the site. Items that will be discarded shall be removed from Government property and disposed of in accordance with all applicable state and local regulations. Leave premises "broom clean”.
Amendment 003 Page 11 of 56
F. Toilet Fixtures and Accessories: Remove protective covering, spots, dirt, paint, labels, and adhesives. Wash clean and clear.
G. General: Remove paper labels from glass fixtures and equipment only after respective items have been inspected, verified and approved to assure that each complies with requirements of the Specifications and Drawings. Labels and plates that are permanently attached to equipment shall not be removed. Remove paint and clean all permanent labels so that they are legible.
3.05 SALVAGEABLE ITEMS: Salvageable items not intended for use in this contract and not specifically designated to remain on the property of the Government shall become the property of the Contractor.
Amendment 003 Page 12 of 56
SECTION 02080 – ASBESTOS ABATEMENT
2.1 Applicable Codes and Standards
All work is to be performed in accordance with local, State and Federal laws and regulations and guidelines published by the Environmental Protection Agency (EPA) and the Occupational Safety and Health Administration (OSHA).
2.2 Abatement Methods
The following work practices and engineering controls shall not be used for work related to asbestos or for work which disturbs ACM or PACM, regardless of measured levels of asbestos exposure or the results of initial exposure assessments: high-speed abrasive disc saws that are not equipped with point of cut ventilator or enclosures with HEPA filtered exhaust air, compressed air used to remove asbestos, or materials containing asbestos, unless the compressed air is used in conjunction with an enclosed ventilation system designed to capture the dust cloud created by the compressed air, dry sweeping, shoveling or other dry clean-up of dust and debris containing ACM and PACM, employee rotation as a means of reducing employee exposure to asbestos.
2.3 Worker Protection
The Contractor shall be duly licensed in the State of California in Accordance with the provisions of Chapter 9 of Division 3 of the Business and Professions Code, as amended. Prior to commencing work, the contractor shall provide evidence of certification as an asbestos abatement contractor by the California Contractor's State License Board. Prior to commencing work, Contractor shall provide copy of, or evidence of, registration with the Chief of the Division of Occupational Safety and Health, State of California (Cal/OSHA) as a Contractor involved in the construction, repair, renovation, maintenance, demolition or salvage activities in which any materials containing more than 0.1% asbestos are handled. The Contractor shall comply with all Federal and State Occupational Safety and Health Administration regulations to insure the safety of his employees and government personnel on the site.
Amendment 003 Page 13 of 56
The Contractor shall provide or require the use of protective clothing, such as coveralls or similar whole-body clothing, head coverings, gloves, and foot coverings for any employee exposed to airborne concentrations of asbestos that exceed the TWA and/or excursion limit prescribed in subsection (c) of this section, or for which a required negative exposure assessment is not produced, and for any employee performing Class I operations which involve the removal of over 25 linear or 10 square feet of TSI or surfacing ACM and PACM. The Contractor shall prohibit the removal of asbestos from protective clothing and equipment by blowing, shaking, or brushing.
The Contractor shall establish a decontamination area that is adjacent and connected to the regulated area for the decontamination of such employees. The decontamination area shall consist of an equipment room, shower area, and clean room in series. The Contractor shall ensure that employees enter and exit the regulated area through the decontamination area.
The Contractor shall ensure that employees do not smoke in work areas where they are occupationally exposed to asbestos because of activities in that work area.
The Contractor shall keep an accurate record of all measurements taken to monitor employee exposure to asbestos. The Contractor shall establish and maintain an accurate record for each employee subject to medical surveillance. The Contractor shall be responsible for medical surveillance and record keeping.
3.4 Control of Emissions
The work area will be completely isolated from the rest of the building so as to prevent asbestos containing dust or debris from passing beyond the isolated area.
Contractor shall construct a critical barrier, which will ensure that the abatement area is isolated and contained, by building impermeable barriers at all exits or openings, including doorways, ducts, mechanical shafts, elevator shafts, drains, etc. so that all possible entrance or exit routes are barricaded and sealed.
3.5 Submittals
Prior to commencing work the Contractor shall submit a written work plan for the intact removal and disposal of the texturing compound and associated drywall. The Plan shall follow the requirements outlined in 29 CFR 1910 and 1926 for Class II asbestos work. The plan shall address the following:
1. Material and equipment to be used.
2. Method of work isolation.
3. Method for worker decontamination system.
4. Method for asbestos removal.
5. Method and frequency for monitoring presence of asbestos material.
Amendment 003 Page 14 of 56
6. Cleanup procedure and final inspection for asbestos materials.
7. Method for loading, hauling and disposal of asbestos materials.
8 Written Hazard Communication Plan and MSDS for products brought on-site by the Contractor.
9. Written Respiratory Protection Plan
10. Sign Plan
Project Work Schedule, Project Work Plan, Health and Safety Plan, proof of insurance, current certification, licensing and applicable medical documentation of all personnel performing work under this contract, the name of the waste transporter, the waste disposal means and destination location shall be included in the work plan.
Upon approval of the plan by the Contracting Officer, no alternative method or procedures shall be used unless approved Contracting Officer.
All post-abatement submittals shall be submitted in a similar fashion within ten (10) working days of completion of the abatement project. Post-abatement submittals shall include: Waste Manifest;
Abatement Contractor Daily Logs; copies of strip-charts from PDM - noting date of collection, work area location and supervisor's initials; OSHA Monitoring results; and, applicable project -specific data.
3.6 Notification
Prior to commencing work, Contractor shall provide written proof of submittal of notifications to the following agencies regarding activities at this temporary work site. Notifications shall made within the time frame specified by each Agency.
1. Cal/OSHA (P.O. Box 630, San Francisco, CA)
2. Environmental Protection Agency
3. California Department of Health Services
4. California Air Resources Board
3.7 Use of Government Facilities
The Forest Service will make available to the Contractor, at no expense, the use of the existing water, sanitary and electrical utilities at the sites. Any delay in the Contractor’s operation resulting from the interruption of these utilities, for any reason, shall not result in an expense to the Government. The Contractor is responsible for investigating site utilities, if available, for use compatibility. No telephone service will be provided by the Government.
Amendment 003 Page 15 of 56
All driveways and parking areas and access roads shall be kept open to all traffic and maintained by the Contractor in such a condition that traffic will be adequately accommodated. The Contractor’s operations shall at no time interfere with emergency vehicle traffic.
Contractor shall be responsible for providing for the safety of their employees and for adequate barriers to protect Forest Service employees from any construction hazards that may exist at the job site.
Parking and storage areas for the Contractor's use is available. Upon request by the Contractor, areas for such use will be designated by the Contracting Officer. Security for the Contractor's equipment and supplies shall be the sole responsibility of the Contractor.
3.8 Control of Site Access
The Contractor shall post a sign readable at 20 feet at the location where abatement is occurring.
The warning sign shall contain the following information:
DANGER
ASBESTOS
CANCER AND LUNG DISEASE HAZARD
AUTHORIZED PERSONNEL ONLY
RESPIRATORS AND PROTECTIVE CLOTIIING
ARE REQUIRED IN THIS AREA
3.9 Cleanup and Disposal
Where vacuuming methods are selected, HEPA filtered vacuuming equipment must be used. The equipment shall be used and emptied in a manner that minimizes the reentry of asbestos into the workplace. The Contracting Officer will provide the contractor with an EPA waste generator number.
The Contractor shall initiate and ensure completion of a Uniform Hazardous Waste Manifest (UHWM) for each shipment. The generator's copy shall be given to the Contracting Officer on completion of the work.
The Contractor shall provide proof of required licenses and permits for transportation, storage and/or disposal of asbestos waste in an approved site.
Asbestos waste, scrap, debris, bags, air filters, containers, equipment, and contaminated clothing consigned for disposal shall be collected and disposed of in sealed, labeled, impermeable bags or other closed, labeled, impermeable containers.
Labels shall contain the following information:
DANGER
CONTAINS ASBESTOS FIBERS
Amendment 003 Page 16 of 56
AVOID CREATING DUST
CANCER AND LUNG DISEASE HAZARD
BREATHING AIRBORNE ASBESTOS FIBERS
IS HAZARDOUS TO YOUR HEALTH
The waste must be disposed of at a landfill approved for accepting asbestos waste. All waste shall be doubled -bagged in asbestos disposal bags, affixed with applicable labels. All waste bags shall be sealed with duct tape, the neck of the bag bent over itself, and an additional three (3) wraps of duct tape applied Bagged asbestos containing waste, which is ready for disposal, shall not be stored in the open outside of the work area. These bags will be taken directly to a closed truck or dumpster. No bagged asbestos containing waste is to be left within the building or premises without the approval of the Contracting Officer. The Contractor shall not allow unauthorized persons access to the materials. All bagged waste shall be transported out of the buildings in closed containers.
Waste disposal bags must be transported in closed containers that are packed in a manner that will prevent tipping, spilling, or breaking during transport.
3.10 Monitoring and Clearance
Ambient air samples shall be collected in and around the work areas, in addition to air clearance sampling. All monitoring and clearance sampling shall be performed under the supervision of and certified by a Certified Industrial Hygienist. Air clearance samples shall be collected using aggressive sampling techniques.
If perimeter air monitoring and analysis for total airborne fiber concentrations during abatement exceed 0.010 f/cc outside the immediate work area, and it can be determined that the Contractor was the cause of the elevated airborne fiber levels, the Contractor shall immediately stop all work, isolate the immediate area(s) with critical barriers consisting of two (2) layers of 6 mil polyethylene sheeting, and perform project decontamination.
The air clearance criteria for this project shall be: 0.010 fibers per cubic centimeter (0.010), as analyzed by Phase Contrast Microscopy (PCM), for each clearance air sample.
Once the work areas have achieved air clearance, the Contractor shall remove containment barriers.
Amendment 003 Page 17 of 56
SECTION 06100 - ROUGH CARPENTRY
1.01 SCOPE: The work of this Section consists of furnishing and installing all rough carpentry such as;
sills, posts, supports, beams, stud walls, decking, connectors, sheathing, siding and the like, AS SHOWN ON THE DRAWINGS and as specified herein or elsewhere in these special project specifications.
1.02 SUBMITTALS
A. Product data. Unless otherwise indicated, submit the following for each type of product provided under work of this Section:
1. Recycled Content:
a. Engineered Wood Products:
1) Indicate recycled content; indicate percentage of consumer and post-consumer recycled content per unit of product.
2) Indicate relative dollar value of recycled content product to total dollar value of product included in project.
3) If recycled content product is part of an assembly, indicate the percentage of recycled content product in the assembly by weight.
4) If recycled content product is part of an assembly, indicate relative dollar value of recycled content product to total dollar value of assembly.
b. Salvaged Lumber: Provide documentation certifying products are from salvaged lumber sources.
c. Recovered Lumber: Provide documentation certifying products are from recovered lumber sources.
2. Local/Regional Materials:
a. Sourcing location(s): Indicate location of extraction, harvesting, and recovery; indicate distance between extraction, harvesting, and recovery and the project site.
b. Manufacturing location(s): Indicate location of manufacturing facility; indicate distance between manufacturing facility and the project site.
c. Product Value: Indicate dollar value of product containing local/regional materials;
include materials cost only.
d. Product Component(s) Value: Where product components are sourced or manufactured in separate locations, provide location information for each component. Indicate the percentage by weight of each component per unit of product.
3. VOC data:
a. Adhesives:
Amendment 003 Page 18 of 56
1) Submit manufacturer’s product data for adhesives. Indicate VOC limits of the product.
Submit MSDS highlighting VOC limits.
2) Submit Green Seal Certification to GS-36 and description of the basis for certification.
3) Submit manufacturer’s certification that products comply with SCAQMD Rule 1168 in areas where exposure to freeze/thaw conditions and direct exposure to moisture will not occur. In areas where freeze/thaw conditions do exist or direct exposure to moisture can occur, submit manufacturer’s certification that products comply with Bay Area AQMD Reg. 8, Rule 51 for containers larger than 16 oz and with California Air Resources Board (CARB) for containers 16 oz or less.
b. Engineered Wood Products: Provide documentation that composite wood and agrifiber products contain no added urea-formaldehyde resins.
1) ANSI A208.1 – 1999, Particleboard
2) ANSI A208.2 – 2002, Medium Density Fiberboard (MDF) for Interior Applications
B. Letter of Certification(s) for Sustainable Forestry. Provide certification of lumber provided by one of the following:
1. Forest Stewardship Council (FSC): Provide letter of certification signed by lumber supplier.
Indicate compliance with FSC "Principles for Natural Forest Management" and identify certifying organization.
a. Submit FSC certification numbers; identify each certified product on a line-item basis.
b. Submit copies of invoices bearing the FSC certification numbers.
2. Sustainable Forestry Board: Provide letter of certification signed by lumber supplier.
Indicate compliance with the Sustainable Forestry Board’s "Sustainable Forestry Initiative" (SFI) and identify certifying organization.
a. Submit SFI certification numbers; identify each certified product on a line-item basis.
C. Submit copies of invoices bearing the SFI certification numbers.
1.03 QUALITY ASSURANCE
A. Sustainably Harvested Wood: Certification Organizations shall be accredited by the Forest Stewardship Council or Sustainable Forestry Board.
B. Recycled Content Materials: Where recycled lumber materials are used for structural applications, include lumber certification and quality grading.
C. Engineered Wood Products:
1. Determine formaldehyde concentrations in air from wood products under test conditions of temperature and relative humidity in accordance with ASTM D6007 or E1333.
2. Determine Volatile Organic Compounds VOC), excluding formaldehyde, emitted from manufactured wood-based panels in accordance with ASTM D6330.
Amendment 003 Page 19 of 56
1.02 CODES AND STANDARDS: The Contractor shall comply with the following codes, provisions and recommendations:
A. California Building Code (2010 edition).
B. American Institute of Timber Construction (AITC), "Timber Construction Manual."
C. American Plywood Association (APA), "U.S. Product Standard PS 1-07 Construction and Industrial
Plywood" and "Plywood Specifications and GradeGuide."
D. American Wood Preservers Association (AWPA), "Standard UC2."
E. Western Wood Products Association (WWPA), "Western Woods Use Book."
F. West Coast Lumber Inspection Bureau (WCLIB), "Standard Grading and Dressing Rules No. 16."
G. Redwood Inspection Service, "Standard Specification for Grades of California Redwood Lumber."
1.03 PRODUCT HANDLING: Comply with pertinent provisions of Section 01640.
Deliver the materials to the job site and store, in a safe area, out of the way of traffic, and shored up off the ground surface. Identify framing lumber as to grades, and store each grade separately from other grades. Protect metals with adequate waterproof outer wrapping.
1.04 MEASUREMENT AND PAYMENT: No separate measurement and payment will be made for the work specified in this Section.
PART 2 PRODUCTS
2.01 LUMBER
A. All wood products shall be of the type and grade required for the end use of the product. In the case of several types and grades, the higher quality shall be used where not specifically defined on the drawings or in the specifications.
1. Resource Management:
a. Virgin Lumber: Provide sustainably harvested; certified or labeled in accordance with FSC or SFI guidelines.
b. Salvaged Lumber: Lumber from deconstruction or demolition of existing buildings or structures. Unless otherwise noted, salvaged lumber shall be delivered clean, denailed, and free of paint and finish materials, and other contamination.
c. Recovered Lumber: Previously harvested lumber pulled from riverbeds or otherwise abandoned. Unless otherwise noted, recovered lumber shall be delivered clean and free of contamination.
2.02 ENGINEERED WOOD PRODUCTS:
A. Toxicity/IEQ: Products shall contain no added urea-formaldehyde.
2.03 SHEATHING:
A. Plywood, APA: Provide exterior grade plywood with phenol resins for interior and exterior applications.
Amendment 003 Page 20 of 56
B. OSB: Provide Phenolic-glued, low-formaldehyde board.
C. Fiberboard:
1.Recycled Content:
Structural: Minimum 80% recycled content.
Non-Structural: Minimum 100 % post consumer recycled content.
2.04 GRADE STAMPS:
A. Framing Lumber: Identify all framing lumber by the grade stamp of the WCLIB, or other recognized grading agency.
B. Plywood: Identify plywood as to species, grade, and glue type by the stamp of the American Plywood Association.
C. Other: Identify all other materials of this section by the stamp of the appropriate agency or by such other means as approved by the Contracting Officer.
2.05 MATERIALS: All specified and miscellaneous lumber shall meet or exceed the following or shall be AS SHOWN IN THE DRAWINGS or as described elsewhere in these project specifications:
2.06 ROUGH HARDWARE: All items of rough hardware, connections, bolts and the like, required to complete the work shall be furnished by the Contractor. Bolts, nuts, and washers for weather exposed connectors and the like shall be galvanized meeting the requirements of ASTM Designation A307.
Hardware for attaching blocking shall also be galvanized.
A. Nails shall be common wire. Galvanized nails shall be used for all exposed framing.
B. Bolts and Lag Bolts for connectors shall be galvanized standard mild steel, hexagonal head, coarse thread machine bolts with matching nuts and cut washers as shown on the drawings.
C. Structural connectors shall be AS SHOWN ON THE DRAWINGS or as required by applicable codes, and shall be Simpson Strong-Tie or approved equal. Connectors in contact with pressure treated wood shall be stainless steel or “ZMAX” or “HDG”.
D. Anchor bolts shall be black steel of the size and type AS SHOWN ON THE DRAWINGS or as required by applicable codes.
E. Recycled Content: Fabricated from 30 percent recycled steel.
PART 3 EXECUTION
3.01 LAYING OUT WORK: Before commencing work, check all lines and levels indicated, and such other work as been completed. Discrepancies shall be reported to the Contracting Officer before further work is done.
3.02 CONSTRUCTION AND WORKMANSHIP:
A. General: Install all wood framing, making proper provision for work of other trades. Do all cutting of wood required to accommodate other trades.
Amendment 003 Page 21 of 56
B. Plates: Plates for partitions and walls shall be single at the bottom and double at the top unless otherwise detailed. Top plates shall be continuous when 20 feet or less.
C. Columns: Furnish and set all columns of the size, centers and locations AS ON THE DRAWINGS or as required by applicable codes. Plates shall be attached to the concrete footings by anchor bolts AS SHOWN ON THE DRAWINGS or as required by applicable codes.
D. Joists and Beams: Joists and beams shall be set with the crowning edge up.
1. Where openings occur, headers and supporting joists shall be doubled and headers and tail joists shall be hung on metal hangers.
2. Solid blocking shall be at ends and over supports and AS SHOWN ON THE DRAWINGS or as required by applicable codes.
E. Studing: Furnish and set all studding of the size, center, and locations indicated on the drawings. Provide openings for mechanical equipment, ducts, etc. at shear walls as approved by the Contracting Officer. Openings shall be solid blocked and secure to studs with joist hangers.
Exterior studs shall be 2x6 at 16" o.c. Interior permanent nonbearing partitions shall be 2x4 at 16" o.c. or AS SHOWN ON THE DRAWINGS or approved by the Contracting Officer.
F. Permanent non-bearing walls shall be attached to the trusses AS SHOWN on the Drawings. If not shown attached on the drawings all corners shall be braced with a piece of 1/2 inch plywood diagonally cut to form a 4 ft. x 4 ft. right triangle or by other means as approved by the Contracting Officer.
G. Produce joints which are tight, true, and well nailed with members assembled in accordance with the drawings and with pertinent codes and regulations.
H. Selection of lumber pieces:
1. Carefully select the members.
2. Select individual pieces so that knots and obvious defects will not interfere with placing bolts or proper nailing, and will allow making or proper connections.
3. Cut out and discard defects which render a piece unable to serve its intended function.
4. Lumber may be rejected by the Contracting Officer, whether or not it meets grade or has been installed, for excessive warp, twist, bow, crook, mildew, fungus, or mold as well as for improper cutting and fitting.
I. Do not shim any framing component.
3.03 GENERAL FRAMING:
A. General:
1. In addition to framing operations normal to the fabrication and erection AS SHOWN ON THE DRAWINGS, install wood blocking and backing required for the work of other trades such as toilet partitions and accessories.
Amendment 003 Page 22 of 56
2. Do not notch, cut, or bore members for pipes, ducts, or conduits, or for other reasons except AS SHOWN ON THE DRAWINGS or as required by applicable codes, or as specifically approved in advance by the Contracting Officer.
B. Bearings:
1. Make bearing full unless otherwise indicated on the Drawings.
2. Finish bearing surfaces on which structural members are to rest so as to give sure and even support.
3. Where framing members slope, cut or notch the ends as required to give uniform bearing surface.
3.04 INSTALLATION OF PLYWOOD/OSB SHEATHING:
A. Placement:
1. Place roof, exterior wall, underlayment, and subfloor (if applicable) plywood (or OSB) with face grain perpendicular to supports and continuous over at least two supports or AS SHOWN ON THE DRAWINGS or as required by applicable codes and consistent with industry standards.
2. Center joints accurately over supports or AS SHOWN ON THE DRAWINGS or as required by applicable codes.
B. Protection: Protect plywood from moisture by use of waterproof coverings until the plywood in turn has been covered with the next succeeding component or finish.
3.05 FASTENING:
A. Nailing:
1. Use only common wire nails or spikes of the size AS SHOWN ON THE DRAWINGS and/or CBC TABLE 2304.9.1.
2. For nailing conditions not covered provide penetration into the piece receiving the point of not less than one-half the length of the nail or spike, provided, however, that 16d nails may be used to connect two pieces of two inch (nominal) thickness.
3. Nail without splitting wood.
4. Prebore as required.
5. Remove split members and replace with members complying with the specified requirements.
B. Bolting:
1. Drill holes 1/16 inch larger in diameter than the bolts being used.
2. Drill straight and true from one side only.
3. Do not bear bolt threads on wood, but use washers under head and nut where both bear on wood, and use washers under all nuts.
Amendment 003 Page 23 of 56
C. Screws: For lag screws and wood screws, prebore holes same diameter as root of threads, enlarging holes to shank diameter for length of shank.
3.06 SITE ENVIRONMENTAL PROCEDURES:
A. As specified in Divisions 1 and below:
B. Indoor Air Quality:
1. Temporary ventilation: Provide temporary ventilation during work of this Section
a. During and immediately after installation of treated wood, engineered wood products, and laminated wood products at interior spaces, provide temporary ventilation.
C. Waste Management: As specified in Section 01351 – Construction Waste Management and as follows:
1. Select lumber sizes to minimize waste; reuse scrap lumber to the greatest extent possible. Clearly separate scrap lumber for use on site as accessory components, including: shims, bracing, and blocking.
2. Do not leave any wood, shavings, sawdust, etc. on the ground or buried in fill. Prevent saw dust and wood shavings from entering the storm drainage system.
3. Do not burn scrap lumber that has been pressure treated.
a. Do not send lumber treated with pentachlorophenol, CCA, or ACA to co-generation facilities or “waste-to-energy” facilities.
Amendment 003 Page 24 of 56
SECTION 06200 - FINISH CARPENTRY
PART 1 GENERAL
1.01 SCOPE: The work of this Section consists of providing (unless noted otherwise herein) and installing all finish carpentry and related work. Finish carpentry shall include but not be limited to the following:
A. Closet and storage shelving.
B. Molding and trim.
C. Window sills.
1.02 SUBMITTALS:
A. Product data. Unless otherwise indicated, submit the following for each type of product provided under work of this Section:
1. Recycled Content:
a. Engineered Wood Products:
1) Indicate recycled content; indicate percentage of pre-consumer and post-consumer recycled content per unit of product.
2) Indicate relative dollar value of recycled content product to total dollar value of product included in project.
3) If recycled content product is part of an assembly, indicate the percentage of recycled content product in the assembly by weight.
4) If recycled content product is part of an assembly, indicate relative dollar value of recycled content product to total dollar value of assembly.
b. Salvaged Lumber: Provide documentation certifying products are from salvaged lumber sources
c. Recovered Lumber: Provide documentation certifying products are from recovered lumber sources
2. Local/Regional Materials:
a. Sourcing location(s): Indicate location of extraction, harvesting, and recovery;
indicate distance between extraction, harvesting, and recovery and the project site.
b. Manufacturing location(s): Indicate location of manufacturing facility; indicate distance between manufacturing facility and the project site.
c. Product Value: Indicate dollar value of product containing local/regional materials; include materials cost only.
d. Product Component(s) Value: Where product components are sourced or manufactured in separate locations, provide location information for each component. Indicate the percentage by weight of each component per unit of product.
Amendment 003 Page 25 of 56
3. VOC data:
a. Adhesives:
1) Submit manufacturer’s product data for adhesives. Indicate VOC limits of the product. Submit MSDS highlighting VOC limits.
2) Submit Green Seal Certification to GS-36 and description of the basis for certification.
3) Submit manufacturer’s certification that products comply with SCAQMD Rule 1168 in areas where exposure to freeze/thaw conditions and direct exposure to moisture will not occur. In areas where freeze/thaw conditions do exist or direct exposure to moisture can occur, submit manufacturer’s certification that products comply with Bay Area AQMD Reg. 8, Rule 51 for containers larger than 16 oz and with California Air Resources Board (CARB) for containers 16 oz or less.
b. Engineered Wood Products: Provide documentation that composite wood and agrifiber products contain no added urea- formaldehyde resins.
1) ANSI A208.1 – 1999, Particleboard
2) ANSI A208.2 – 2002, Medium Density Fiberboard (MDF) for Interior Applications
B. Submit environmental data in accordance with Table 1 of ASTM E2129 for products provided under work of this Section.
C. Letter of Certification(s) for Sustainable Forestry. Provide certification of lumber provided by one of the following:
1. Forest Stewardship Council (FSC): Provide letter of certification signed by lumber supplier. Indicate compliance with FSC "Principles for Natural Forest Management" and identify certifying organization.
a. Submit FSC certification numbers; identify each certified product on a line-item basis.
b. Submit copies of invoices bearing the FSC certification numbers.
2. Sustainable Forestry Board: Provide letter of certification signed by lumber supplier.
Indicate compliance with the Sustainable Forestry Board’s "Sustainable Forestry Initiative" (SFI) and identify certifying organization.
a. Submit SFI certification numbers; identify each certified product on a line-item basis.
b. Submit copies of invoices bearing the SFI certification numbers.
1.03 QUALITY ASSURANCE:
A. Sustainably Harvested Wood: Certification Organizations shall be accredited by the Forest Stewardship Council or Sustainable Forestry Board.
Amendment 003 Page 26 of 56
B. Recycled Content Materials: Where recycled lumber materials are used for structural applications, include lumber certification and quality grading.
C. Engineered Wood Products:
1. Determine formaldehyde concentrations in air from wood products under test conditions of temperature and relative humidity in accordance with ASTM D6007 or E1333.
2. Determine Volatile Organic Compounds VOC), excluding formaldehyde, emitted from manufactured wood-based panels in accordance with ASTM D6330.
1.04 CODES AND STANDARDS: Contractor shall comply with the provisions and recommendations of the latest editions of the following codes and standards:
A. Architectural Woodwork Institute (AWI) "Quality Standards" of the Architectural Woodwork Industry.
B. National Electrical Manufacturers Association (NEMA) Publication LD-1-1964 for Type 1, Class 1 Plastic Laminate.
C. Woodwork Institute of California (WIC), "Manual of Woodwork,: latest edition.
D. Western Wood Products Association (WWPA), "Western Lumber Grading Rules 81."
E. West Coast Lumber Inspection Bureau (WCLB), "1984 Standard Grading Rules #16."
F. American Plywood Association (APA).
1.05 MEASUREMENT AND PAYMENT: No separate measurement and payment will be made for the work specified in this Section.
PART 2 PRODUCTS
2.01 WOODWORK:
A. General: Unless specified otherwise herein, all finish wood materials shall conform to the AWI "Custom" grade requirements for millwork materials.
B. Interior Millwork and Trim: Millwork shall conform to profiles, details and configurations of the drawings and include any necessary specialty items and accessories for a complete installation.
Wood shall be of the species and cut specified or AS SHOWN ON THE DRAWINGS.
C. Shelving:
1. Shelves 11-1/2 inches wide or less: Salvaged Douglas-fir-Hemlock, B and Better grade; or salvaged ponderosa pine, B and Better grade.
2. Shelves wider than 11-1/2 inch: 3/4 inch thick, A-D, group 1, exterior plywood with 3/8 inch x…