AG-84M8-S-14-0001_00002.pdf
PDF 2 MB Posted
- Attached to
- Intermountain Region Road and Bridge MATOC Federal contract opportunity
- Solicitation number
- AG-84M8-S-14-0001
About this file
Contains solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| AG-84M8-S-14-0001_0001.pdf | ||
| Performance_Questionaire.pdf | ||
| Attach_F.xlsx | XLSX spreadsheet | |
| Attach_G.xlsx | XLSX spreadsheet | |
| Attach_B_Sample_Task.pdf | ||
| Attach_C.pdf | ||
| Attach_H.pdf | ||
| Performance_Questionaire.pdf | ||
| Attach_Definitions.pdf | ||
| Attach_e.xlsx | XLSX spreadsheet | |
| AG-84M8-S-14-0001_043014.pdf | ||
| Attach_I_Submittal.pdf | ||
| Attach_A_Specifications.pdf | ||
| Attach_D.xlsx | XLSX spreadsheet |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
AG-84M8-S-14-0001
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
SW IDAHO-NEVADA ACQUISITION CENTER
84M8
OGDEN UT 84401
324 25TH STREET
INTERMOUNTAIN REGION
05/01/2014000002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
05/01/2014
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to replace the 1442 and solicitation with the attached.
This amendment includes the following changes/information:
B-5 removed the blanks
B 6-8 were renumbered
Added B-9 Adjustment for Fuel Cost and Bituminous Material costs
J-1 verified and updated wage determination
L added Factor 5 and changed Factor 5 Cost to Factor 6 Cost
Provide Q&As from prebid meeting
Send Proposal information to
Matt Morris
1249 S Vinnell Way, Ste 200
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
MATTHEW A. MORRIS
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 75
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
AG-84M8-S-14-0001/000002
Boise, ID 83709 Due date 17 Jun 2014 Questions to mamorris@fs.fed.us
No Fax or Email Proposals accepted
--See note in section L for proposal assembly information
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
INTERMOUNTAIN REGION
324 25TH STREET
OGDEN UT 84401
84M8
USDA Forest Service Attn Matt Morris 1249 S Vinnell Way, Ste 200 Boise, ID 83709
Matthew Morris 208-373-4166
1x 05/01/2014
AG-84M8-S-14-0001
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Road and Bridge Maintenance and Construction (IDIQ) Multiple Award Task Order
Contract
Intermountain Region
Nevada, Utah, Southern Idaho, and Western Wyoming
Price Range
The Government Estimate is more than $10,000,000
The soliciation is a Request for Proposals. Selection will be based on an evaluation described in Section M. Pleasereview section L instructions for the preparartion of Technical & Business Proposals, and Section M prior to submitting your proposal.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 calendar days and complete it within ________________ ________________ calendar days after receiving
06/17/2014
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected. _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
INTERMOUNTAIN REGION
324 25TH STREET
OGDEN UT 84401
84M8
BRIAN WHARTON
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
452.216-73 Minimum and Maximum Contract Amounts. (FEB 1988) C- 2 - Location 52.252-2 Clauses Incorporated by Reference. (FEB 1998) SECTION D - Packaging and Marking SECTION E - Inspection and Acceptance 52.252-2 Clauses Incorporated by Reference. (FEB 1998) SECTION F - Deliveries or Performance 52.252-2 Clauses Incorporated by Reference. (FEB 1998) The Region 4 Acquisition Office of the United States Forest Service, Department of Agriculture is responsible for this solicitation, award and administration of the contract. All written correspondence shall reference the contract number and/or solicitation number. Communications shall be directed to:
USDA Forest Service Intermountian Region Attention: Brian Wharton, Contracting Officer Ogden, UT The following have authority to place Task Orders under this contract: All Acquisition Service Center Contracting Officers and purchasing agents within NIAT with the appropriate warrant authority.
These individuals are authorized to utilize this contract for project work in accordance with the terms and conditions set forth in the contract Base IDIQ: A post award conference with the successful offeror(s) is required and will be scheduled within 30 days after the date of contract award. The conference will be held at a time and location to be determined SECTION H - Special Contract Requirements H-8 - 452.237-74 Key Personnel. (FEB 1988) I- 1 52.252-2 Clauses Incorporated by Reference. (FEB 1998) 52.222-42 Statement of Equivalent Rates for Federal Hires. (MAY 1989) I-4 - 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters. (JUL 2013) I-5 - 52.216-18 Ordering. (OCT 1995) I-6 52.216-19 Order Limitations. (OCT 1995) I-7 52.216-22 Indefinite Quantity. (OCT 1995) I-8 52.217-8 Option to Extend Services. (NOV 1999) I-9 52.217-9 Option to Extend the Term of the Contract. (MAR 2000) I-10 52.219-14 Limitations on Subcontracting. (NOV 2011) I-12 52.222-54 Employment Eligibility Verification. (AUG 2013) I-13 52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items. (MAY 2008) I-14 52.225-11 Buy American Act - Construction Materials under Trade Agreements. (NOV 2013) I-16 - 52.232-33 Payment by Electronic Funds Transfer - System for Award Management. (JUL 2013)43 I-17 52.236-1 Performance of Work by the Contractor. (APR 1984) I-18 52.236-7 Permits and Responsibilities. (NOV 1991) I-19 52.252-6 Authorized Deviations in Clauses. (APR 1984) 452.228-70 Alternative Forms of Security. (NOV 1996) 452.232-70 Reimbursement for Bond Premiums - Fixed-Price Construction Contracts. (NOV 1996) .. 45 SECTION J - List of Documents, Exhibits, and Other Attachments SECTION K - Representations, Certifications, and Other Statements of Offerors 52.204-8 Annual Representations and Certifications. (JAN 2014) 52.222-5 Davis-Bacon Act-Secondary Site of the Work. (JUL 2005) 52.223-1 Biobased Product Certification. (MAY 2012) SECTION L - Instructions, Conditions, and Notices to Offerors or Respondents 52.252-1 Solicitation Provisions Incorporated by Reference. (FEB 1998)
AG-84M8-S-14-0001 00002
52.204-7 System for Award Management. (JUL 2013) 52.209-7 Information Regarding Responsibility Matters. (JUL 2013) 52.215-1 Instructions to Offerors - Competitive Acquisition. (JAN 2004) 52.216-1 Type of Contract. (APR 1984) 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction. (FEB 1999) 52.225-12 Notice of Buy American Act Requirement - Construction Materials under Trade Agreements.
(FEB 2009)
52.233-2 Service of Protest. (SEP 2006) 52.236-28 Preparation of Proposals - Construction. (OCT 1997) 52.252-5 Authorized Deviations in Provisions. (APR 1984) 452.215-71 Instructions for the Preparation of Technical and Business Proposals. (SEP 1999) 452.215-72 Amendments to Proposals. (FEB 1988) 452.237-71 Pre-Bid/Pre-Proposal Conference. (FEB 1988) 52.236-27 Site Visit (Construction). (FEB 1995) SECTION M - Evaluation Factors for Award 52.217-3 Evaluation Exclusive of Options. (APR 1984) 452.216-72 Evaluation Quantities - Indefinite Delivery Contract. (FEB 1988)
PART I--THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
Road and Bridge Maintenance and Construction (IDIQ) Multiple Award Task Order Contract Intermountain Region
Nevada, Utah, Southern Idaho, and Western Wyoming
This is an Indefinite Delivery Indefinite Quantity (IDIQ) Multiple Award Task Order Contract (MATOC) that will be effective for a base period, and, at the option of the government, for four (4) additional one-year option periods. This contract is for routine, recurring, or emergency road and bridge maintenance, repair and construction projects. Work may be performed anywhere in the Intermountain Region within the states of Nevada, Utah, Southern Idaho, Western
Wyoming and California Bridgeport Ranger District.
Instructions: Offerors shall submit unit prices for each item of work shown in the SCHEDULE OF ITEMS, and option year co-efficients. Offerors must provide Location Coefficients for each location within Zone 1 or within Zone 2, or if you would like to be considered for award in both zones by providing coefficients in both zones. Offeror will only be considered for task orders in those Geographic Zone(s) for which co-efficients are provided and contract awarded. The Government anticipates making a minimum of three and a maximim of ten awards.
Failure to comply with the instructions may render your proposal incomplete and ineligible for possible contract award.
B- 1 – CONSTRUCTION SCHEDULE OF ITEMS
Item No. Description Method & Unit of Measure Unit Price
150 PROJECT REQUIREMENTS
157.31 TEMPORARY EROSION CONTROL PLAN CQ – EACH $ _________
157.02 SILT FENCE 3FT WOOD STAKES CQ – LF $ _________
158.01 WATERING FOR DUST CONTROL CQ – MGallon $ _________
200 EARTHWORK
201.31 CLEARING AND GRUBBING- LIGHT
DISPOSE BY SCATTERING
CQ – ACRE
201.32 CLEARING AND GRUBBING- HEAVY
DISPOSE BY SCATTERING
CQ – ACRE
203.30 REMOVAL OF STRUCTURES AND OBSTRUCTIONS CQ – CY
204.80 EXCAVATION AND EMBANKMENT – COMMON
AND LOOSE ROCK COMPACTION METHOD B
CQ – CY
207.01 EARTHWORK GEOTEXTILES:TYPE IV CQ – SY $ _________
208.03 STRUCTURAL EXCAVATION AND BACKFILL CQ – CY
209.03 STRUCTURAL BACKFILL-PIPE BEDDING CQ – CY $ _________
210.01 ROLLING DIP CQ – EACH $ _________
210.02 WATER BAR CQ – EACH $ _________
211.01 ROADWAY OBLITERATION: RIPPING 8” TO
12” DEPTH
CQ – LANE MILE
211.02 ROADWAY OBLITERATION: SCARIFYING
DECOMPACATION TO 18” DEPTH
CQ – LANE MILE
211.03 ROADWAY OBLITERATION:
FULL RE-CONTOUR
CQ – LANE MILE
212.01 LINEAR GRADING CQ – LANE MILE $ _________
230.01 ROADSIDE BRUSHING- MEDIUM CQ - ACRE $ _________
230.02 ROADSIDE BRUSHING- HEAVY CQ - ACRE $ _________
251.01 RIPRAP: MACHINE PLACED CLASS 4
COMMERCIAL SOURCE
CQ – CY $ _________
251.02 RIPRAP: MACHINE PLACED CLASS 5
COMMERCIAL SOURCE
CQ – CY
251.03 RIPRAP: MACHINE PLACED GOVERNMENT
SOURCE
CQ – CY
252.05 ROCK EMBANKMENT AND ROCK BUTTRESS:
CLASS 6
CQ – CY
252.51 ROCK: BOULDER PLACEMENT CQ - EACH $ _________
253.01 GABIONS:WELDED WIRE: GALVANIZED CQ – CY $ _________
255.01 MECHANICALLY STABILIZED EARTH WALLS –
MEASURE PER AREA OF WALL FACE,
EXCAVATION AND BACKFILL EXCLUDED
CQ – SF
259.01 SOIL NAIL RETAINING WALLS: PER SOIL NAIL
PLACED 20 FT DEPTH
CQ – EACH $ _________
259.11 SOIL NAIL RETAINING WALLS: 8 IN SHOT CRETE
FACE MEASURE PER AREA OF WALL FACE
262.01 REINFORCED SOIL EMBANKMENT: GEOGRID:
CATEGORY 2. EXCAVATION AND EMBANKENT
EXCLUDED
CQ – SY
262.01 REINFORCED SOIL EMBANKMENT: GEOGRID:
CATEGORY 3. EXCAVATION AND EMBANKENT
EXCLUDED
300 AGGREGATE
301.01 CRUSHED AGGREGATE: GRADATION C
COMPACTION METHOD B
FURNISH AND PLACE, EXCLUDE HAUL
AQ – CY
301.02 CRUSHED AGGREGATE SURFACE COURSE: WITH
2% BENTONITE
COMPACTION METHOD B
301.02 AGGREGATE PLACEMENT COMPACTION
METHOD B
GOVERNMENT FURNISHED
306.01 DUST PALLIATIVE: MAGNESIUM CHLORIDE CQ – SY $ _________
303.01 ROAD RECONDITIONING: INCLUDES SCARIFY 6
IN DEPTH, SURFACE BLADING, AND
COMPACTION
CQ – MILE
303.05 ROAD RECONDITIONING: SURFACE BLADING
ONLY
CQ – MILE
324.01 MINOR CRUSHED AGGREGATE:
QUANTITIES LESS THAN 50 CY
CQ – CY
400 ASPHALT
403.01 HOT ASPHALT CONCRETE PAVEMENT
AQ - TON
404.01 MINOR HOT ASPHALT CONCRETE PAVEMENT:
(LESS THAN 50 TON)
AQ - TON
408.01 COLD RECYCLED ASPHALT BASE COURSE CQ – SY $ _________
409.01 ASPHALT SURFACE TREATMENT – CRS2P
ASPHALT
AQ - TON
409.02 ASPHALT SURFACE TREATMENT – AGGREGATE
CHIPS – ½ IN, 30#/SY
410.01 ASPHALT SURFACE TREATMENT – SLURRY SEAL,
TYPE II CSS-1H
CQ – SY
411.01 ASPHALT PRIME COAT CQ - GALLON $ _________
411.05 ASPHALT FOG COAT CQ – SY $ _________
413.01 ASPHALT PAVEMENT MILLING: 3 IN DEPTH CQ – SY $ _________
414.01 ASPHALT PAVEMENT CRACK AND JOINT
SEALING, POLYMER OR RUBBER MODIFIED
AQ –GALLON
414.31 ASPHALT PAVEMENT: SAW CUTTING AQ –LF $ _________
430.01 ASPHALT PAVEMENT PATCHING: FULL DEPTH
HOT ASPHALT CONCRETE MIX
AQ –SY
500 RIGID PAVEMENTS
501.01 REINFORCED PORTLAND CEMENT CONCRETE
SLABS
CQ – CY
550 BRIDGE REPAIR
552.01 STRUCTURAL CONCRETE CLASS A(AE) CQ – CY $ _________
553.01 PRECAST, PRESTRESSED CONCRETE
STRUCTURAL MEMBER CLASS P(AE)
CQ – CY
556.01 BRIDGE RAILING TYPE II CLASS B CQ – LF $ _________
556.02 REMOVE AND RESET BRIDGE RAILING CQ – LF $ _________
556.01 APPROACH GUARDRAIL TYPE II CQ – LF $ _________
557.01 TREATED STRUCTURAL TIMBER AND LUMBER CQ – MBF $ _________
557.02 TREATED STRUCTURAL TIMBER AND LUMBER –
GLULAM
CQ – MBF
561.01 BRIDGE TIMBER CURB: REMOVE AND REPLACE CQ – LF $ _________
600 INCIDENTAL CONSTRUCTION
602.01 CMP CULVERT-18 INCH – 16 GA AQ – LF $ _________
602.02 CMP CULVERT-24 INCH – 14 GA AQ – LF $ _________
602.03 CMP CULVERT-36 INCH – 12 GA AQ – LF $ _________
602.04 CMP CULVERT-48 INCH – 10 GA AQ – LF $ _________
603.11 STRUCTURAL PLATE CULVERTS – MEASURED BY
SPAN TIMES LENGTH OF STRUCTURE
605.01 UNDERDRAIN SYSTEM: INCLUDES 6 IN
PERFORATED PVC PIPE, TYPE I-A GEOTEXTILE, ½
IN DRAIN ROCK AND BACKFILL MATERIALS
CQ – LF
607.01 REMOVE, CLEAN, AND RESET EXISTING
CULVERT
AQ – LF
614.01 LEAN CONCRETE BACKFILL AQ – CY $ _________
615.01 CONCRETE PAVEMENTS: SIDEWALKS AND PADS AQ – CY $ _________
617.01 GUARDRAIL TYPE II, CLASS A AQ – LF $ _________
617.01 GUARDRAIL TERMINAL SECTION CQ – EACH $ _________
617.01 GUARDRAIL REPLACE POST CQ – EACH $ _________
624.01 TOPSOIL: FURNISH AND PLACE CQ – CY $ _________
624.02 TOPSOIL: PLACE CONSERVED CQ – CY $ _________
625.07 SEEDING: DRY METHOD GOVT FURNISHED SEED CQ- ACRE $ _________
625.08 SEED & MULCH HYDRAULIC METHODS CQ-ACRE $ _________
629.01 EROSION CONTROL: TYPE 2.D CQ – SY $ _________
629.02 EROSION CONTROL: TYPE 3.B CQ – SY $ _________
629.03 WATTLES: 9 IN DIA STRAW CQ – LF $ _________
PERMANENT TRAFFIC CONTROL
633.01 SIGN SYSTEM – HDO PLYWOOD, TYPE III
PRISMATIC SHEETING
633.05 POSTS: 4X4 TREATED WOOD CQ – EACH $ _________
633.06 OBJECT MARKER CQ – EACH $ _________
633.07 DELINEATOR CQ – EACH $ _________
633.11 REMOVE AND RESET SIGN OR OBJECT CQ – EACH $ _________
634.01 PERMANENT PAVEMENT MARKING:
4” WIDE STRIPE, THERMOPLASTIC TYPE H
CQ – LF
635.01 TRAFFIC CONTROL PLAN CQ- EACH $ _________
635.05 TYPE III BARRICADES CQ- EACH $ _________
635.07 CONSTRUCTION SIGNS CQ- EACH $ _________
635.09 FLAGGER AQ- HR $ _________
648.01 STREAM SIMULATION MATERIAL PLACEMENT CQ – CY $ _________
648.02 STREAM SIMULATION MATERIAL PLACEMENT-
FURNISH AND PLACE CLASS 14
CQ – CY
648.51 BOULDER PLACEMENT: SIZE 4 CQ – EACH $ _________
648.52 BOULDER PLACEMENT– FURNISH AND PLACE
SIZE 4
CQ – EACH
800 MATERIAL HAUL
801.1 MATERIAL SHORT HAUL < 5 MILE AQ – CY MILE $ _________
801.2 MATERIAL LONG HAUL > 5 MILE AQ – CY MILE $ _________
801.3 WEIGHED MATERIAL HAUL AQ–TON MILE $ _________
B-2 SERVICE SCHEDULE OF ITEMS
*These line items shall only be used on Task Orders subject to the Service Contract Act (SCA).
Description, Method, and Measurement for these items shall be the same as the cooresponding 200 series specifications; Payment shall be per this Service Task Order Schedule.
Item No.
Description
Method & Unit of Measure
Unit Price
910.01 ROLLING DIP CQ – EACH $ _________
910.02 WATER BAR CQ – EACH $ _________
911.01 ROADWAY OBLITERATION: RIPPING 8” TO
12” DEPTH
CQ – LANE MILE
911.02 ROADWAY OBLITERATION: SCARIFYING
DECOMPACATION TO 18” DEPTH
CQ – LANE MILE
911.03 ROADWAY OBLITERATION:
FULL RE-CONTOUR
CQ – LANE MILE
912.01 LINEAR GRADING CQ – LANE MILE $ _________
930.01 ROADSIDE BRUSHING – MEDIUM CQ – ACRE $__________
930.02 ROADSIDE BRUSHING – HEAVY CQ – ACRE $__________
B-3 ZONE 1 COEFFICIENTS (see instructions below)
Item No.
Description
LOCATION COEFFICIENTS FOR ZONE 1
Coefficient
Humbolt-Toiyabe National Forests
1.1 Carson Ranger District, Carson City NV ________________
1.2 Bridgeport Ranger District, Bridgeport, CA ________________
1.3 Spring Mountains NRA, Las Vegas, NV ________________
1.4 Austin Ranger District, Austin, NV ________________
1.5 Tonopah Ranger District, Tonopah, NV ________________
1.6 Ely Ranger District, Ely, NV ________________
1.7 Mountain City Ranger District, Elko, NV ________________
1.8 Ruby Mountains/Jarbridge Ranger Districts, Wells, NV ________________
1.9 Santa Rosa Ranger District, Winnemucca, NV ________________
Ashley National Forest
1.10 Vernal Ranger District, Vernal, UT ________________
1.11 Flaming Gorge National Recreation Area, Manila, UT ________________
1.12 Dutchesne Ranger District, Duchesne, UT ________________
1.13 Roosevelt Ranger District, Roosevelt, UT ________________
Dixie National Forest
1.14 Cedar City Ranger District, Cedar City, UT ________________
1.15 Pine Valley Ranger District, St. George, UT ________________
1.16 Powell Ranger District, Panguitch, UT ________________
1.17 Excalante Ranger District, Escalante, UT ________________
Fishlake National Forest
1.18 Richfield Ranger District, Richfield, UT
1.19 Fillmore Ranger District, Fillmore, UT ________________
1.20 Beaver Ranger District, Beaver, UT ________________
1.21 Loa/Teasdale Ranger Districts, Loa & Teasdale, UT ________________
Manti-La Sal National Forest
1.22 Price Ranger District, Price, UT ________________
1.23 Sanpete Ranger District, Ephraim, UT ________________
1.24 Ferron Ranger District, Ferron, UT ________________
1.25 Moab Ranger District, Moab, UT ________________
1.26 Monticello Ranger District, Monticello, UT ________________
Uinta-Wasatch-Cache National Forest
1.27 Heber Ranger District, Heber City, UT ________________
1.28 Pleasant Grove Ranger District, Pleasant Grove, UT ________________
1.29 Spanish Fork Ranger District, Spanish Fork & Nephi, UT ________________
1.30 Salt Lake City Ranger District, Salt Lake City, UT ________________
1.31 Kamas Ranger District, Kamas, UT ________________
1.32 Evanston Ranger District, Evanston, WY ________________
1.33 Logan Ranger District, Logan, UT ________________
1.34 Ogden Ranger District, Ogden, UT ________________
B-4 ZONE 2 COEFFICIENTS
2 LOCATION COEFFICIENTS FOR ZONE 2
Bridger-Teton National Forest
2.1 Jackson Ranger District, Jacksonl, WY _______________
2.2 Kemmerer Ranger District, Kemmerer, WY _______________
2.3 Big Piney Ranger District, Big Piney, WY _______________
2.4 Greys River Ranger District, Afton, WY _______________
2.5 Blackrock Ranger District, Moran, WY _______________
Boise National Forest
2.6 Mountain Home Ranger District, Mountain Home, ID _______________
2.7 Idaho City Ranger District, Idaho City, ID _______________
2.8 Cascade Ranger District, Cascade, ID _______________
2.9 Lowman Ranger District, Lowman, ID _______________
2.10 Emmett Ranger District, Emmett, ID _______________
Caribou-Targhee National Forest
2.11 Palisades Ranger District, Idaho Falls, ID ________________ 2.12 2.13
Ashton Ranger District, Ashton, ID Island Park Ranger District, Island Park, ID
2.14 Dubois Ranger District, Dubois, ID ________________
2.15 Montpelier Ranger District, Montpelier, ID ________________
2.16 Soda Springs Ranger District, Soda Springs, ID ________________
2.17 Teton Basin Ranger District, Driggs, ID ________________
2.18 Westside Ranger District, Pocatello, ID ________________
Payette National Forest
2.19 2.20
Krassel Ranger District, McCall, ID McCall Ranger District, McCall, ID
2.21 Council Ranger District, Council, ID ________________
2.22 New Meadow Ranger District, New Meadows, ID ________________
2.23 Weiser Ranger District, Weiser, ID ________________
Salmon-Challis National Forest
2.24 Salmon/Cobalt Ranger District, Salmon, ID ________________
2.25 North Fork Ranger District, North Fork, ID ________________
2.26 Challis, Middle Fork & Yankee Fork Ranger Districts, Challis, ID
2.27 Leadore Ranger District, Leadore, ID ________________
2.28 Lost River Ranger District, Mackay, ID ________________
Sawtooth National Forest
2.29 Minidoka Ranger District, Burley, ID ________________
2.30 Ketchum Ranger District, Ketchum, ID ________________
2.31 Sawtooth National Recreation Area, Ketchum, ID ________________
2.32 Fairfield Ranger District, Fairfield, ID ________________
B-5 OPTION YEAR COEFFICIENTS
3 OPTION YEAR COEFFICIENTS
3.1 Option Year One 2015 – 2016 _____________
3.2 Option Year Two 2016 – 2017 _____________
3.3 Option Year Three 2017 – 2018 _____________
3.4 Option Year Four 2018 – 2019
*month and day same as base award date
B-6 Coefficients
The Coefficients are listed in THE SCHEDULE OF ITEMS and are proposed by the offeror. Due to the wide geographic distribution of potential task orders and the possible variability in cost based on location of the work, THE SCHEDULE is divided into two Geographic Zones. An offeror shall propose Location Coefficients for each Ranger District within one or both Geographic Zones.
The proposed Coefficient for each Ranger District shall cover all work within the Administrative Area/Boundary of that District.
Information regarding National Forest Boundary maps may be found at http://www.fs.fed.us/maps/forest-maps.shtml.
The coefficients are proposed as a multiple (in decimal format) increase or decrease to the line item Unit Price proposed by the offeror on the schedule. For example, a coefficient of 1.2 would result in an additional 20 percent to the listed unit price; 0.9 would result in a 10 percent decrease of the listed prices, and 1.00 would leave the unit price as your proposed unit price. The offeror shall limit the Coefficients to three decimal places. The offeror shall propose an Option Year Coefficient for each option year. The offeror’s Coefficients shall be all inclusive and shall include, but not limited to, the following costs:
1. Overhead
2. Profit and risk
3. Task Order preparation
4. Social security contributions
5. General insurances
6. Workman’s compensations insurance
7. State unemployment insurance
8. Federal unemployment insurance
9. Mobilization and demobilization costs
10. Site cleanup
11. Labor adjustments between the RS Means given labor rates and the Davis/Bacon Labor Rates included in the contract
12. Supervision
13. Quality control
14. Transportation of contractor’s personnel to, from, and within the job site
15. Shipping of all materials to the jobsite
16. Lodging and per-diem
17. Adjustment factors to account for small jobs
18. Incidental tools and equipment
19. Submittals (unless noted otherwise)
20. Any markups for materials and all contingencies
B-7 Pricing Structure for Task Orders
STANDARD WORK (PRE-PRICED)
(a) Pricing for this contract will be based upon unit prices for Standard Items of Work as proposed by the offeror within the Schedule of Items of the original solicitation. Task Orders shall be developed using the Schedule of Items and Coefficients. The Schedule may be updated over time through contract modification to include additional standardized items of work, but the offeror’s costs for line items initially listed herein shall not be revised throughout the duration of the contract.
Task Orders will be comprised of entirely construction line items of work or service line items of work. Individual task orders will not mix service and construction work.
(b) Standard Schedule of Items calculation: The coefficients (in decimal format) listed in The Schedule will be multiplied by the unit price listed in the schedule to obtain the adjusted price for each line item. For example, a coefficient of 1.2 would result in an additional 20 percent to the listed unit price; 0.9 would decrease of the listed price by 10 percent, and 1.00 would leave the unit price unchanged.
The total cost for all items of work within a Task Order will be calculated as follows:
Line item price from the Schedule of Items x quantity of item (per Method & Unit of Measure on the Schedule) = Sum of line items x Location Coefficient x Option-Year Coefficient (if applicable) Total Price for Task Order
Firm-Fixed Price Task Order Example: The following sample calculations. All coefficients and dollar figures are fictitious.
Asphalt Concrete Pavement Overlay – cost per ton $100.00 Total tons per Task Order= 35 tons ($100 X 35) $3,500
Location Coefficient –District @ 115% (1.15) Option Year Coefficient – Option Year 1 @ 102% (1.02) (1.15 X 1.02) 1.173
TOTAL TASK ORDER PRICE $4,105.50
NON-STANDARD WORK (NON PRE-PRICED)
(a) Non-pre-priced work is categorized as follows:
(i) Road construction activity that is not specifically included in the Schedule of Items, but is within the basic intent and general scope of the contract.
(ii) The current edition, at time of task order pricing, of RS Means Heavy Construction Cost Data, or other industry standard cost estimating tools shall be used in developing proposed costs for non-standard work. The current edition of the Rental Rate Blue Book shall be utilized for equipment cost. The government shall use prices from these industry publications as well as Forest Service construction cost data in validating the cost of non-standard work items. Location coefficients shall be applied to non pre-priced work items; option year coefficients shall not be applied unless costs are shown to have been obtained from Rental Rate Blue Book, or other industry standard published in the first year of this contract.
(b) Non-pre-priced work will be negotiated by the Contracting Officer and may be added to Task Orders when necessary at any time during the contract term.
Non-Pre-Priced Task Order Example: The cost for a specific constructed feature is not included in the schedule. For example a gravity-block retaining wall. The installed cost for the wall is $75.00 per square foot face for a 100 SF wall. The cost of this item may be calculated per unit price to be multiplied by quantity for total price of item. Location Coefficients is 1.15
Retaining Wall $75.00 per SF $75.00 Coefficient (1.15) x 1.15 Item unit price $86.25 per SF x Quantity (100 SF) x100 Total Item Price $8625.00
Non-pre-priced items may be included in addition to standard items on a Task Order; however where components of work can be defined using the Standard Items, those existing line items shall be used. Non-pre priced components of work shall not be redundant to standard items of work in a Task Order.
Computing Hours and Equipment Task Order Example: Cost for labor and equipment from Rental Rate Blue Book is $5,571.30.
Location Coefficient is 1.15. All work is accomplished in an unrestricted area during standard work days/hours. All coefficients and dollar figures are fictitious. Calculation shown below:
Labor $28.7 @ 16 Hrs $460.00 Equipment Operator (crane) $38.8 @ 16 Hrs $620.80 Hyd. Excavator 3.5 CY $2,166.00 D@ 2 Days $4,332.00 Trench Box $79.25 D@ 2 Days $158.50 Total Cost (Labor, Material and Equipment) $5,571.30 Location Coefficient = 1.15 $5,571.30 x 1.15
TOTAL TASK ORDER PRICE $6,407.00
B-8 Minimum and Maximum Contract Amounts
452.216-73 Minimum and Maximum Contract Amounts. (FEB 1988)
During the period specified in FAR clause 52.216-18, ORDERING, the Government shall place orders totaling a minimum of $5,000.00, but not in excess of $25,000,000.00.
(End of Clause)
Maximum Contract Amount: The maximum total amount available for ordering purposes is $5,000,000.00 for the basic year and $5,000,000.00 for each option year, for a total of $25,000,000.00 for the aggregate amount for all awards. However, if the maximum contract Value Per Year for a particular option year is not reached, the unused portion of that ceiling may be rolled over to the next option year, but the Total Cumulative Value for that year may not be exceeded.
During the life of the contracts, the approximate maximum amount available (i.e., contract price ceiling) for placement under orders is a cumulative amount with each option exercised, as exemplified below:
Contract Year: Value Per Year: Total Cumulative Value Per Year:
Base Year: $ 5,000,000 $5,000,000 Option Year 1: $ 5,000,000 $10,000,000 Option Year 2: $ 5,000,000 $15,000,000 Option Year 3: $ 5,000,000 $20,000,000 Option Year 4: $ 5,000,000 $25,000,000
Total: $25,000,000 $25,000,000
B-9 Adjustment for Fuel Cost and Bituminous Material costs
This price adjustment provision is intended to minimize risk to the Contractor due to potential volatile price fluctuations for fuel and bituminous materials that might occur throughout the duration of the Contract. The Contractor may invoke this provision by written notification to the Contracting Officer prior to the effective date of the Option Year renewal. In cases where the fuel rates have decreased, the Contracting Officer may invoke this provision by written notification to the Contractor prior to exercising of an option year.
This adjustment will only be applied if the monthly mean average of the first quarter crude oil price varies from the base award contract year’s mean average of the first quarter crude oil price by at least 20% at the first option year, plus 8% for each additional option year. Adjustments will not be made to Task orders awarded prior to Option Renewal. Adjustments will apply only to that option year. When adjustments are in effect, task order calculation sheets shall be adjusted to sum the defined Bituminous Tasks separately from other tasks for application of the adjustment factors. The adjustment factors may also be applied to the Rental Rate Blue Book if the book is used from the base year.
Definition of Terms for calculating adjustments is as follows:
U.S. Office of Energy Information Administration - www.eia.gov. (For quick reference:
http://www.eia.gov/dnav/pet/hist/LeafHandler.ashx?n=pet&s=rclc1&f=m )
Contract Award Price (C) – The mean average of the price of crude oil for the first three months of the year in which the contract is awarded as reported by the U.S. Energy Information Administration. If the contract was awarded the summer of 2014, it would be (January 2014 + February 2014 + March 2014)/3.
AG-84M8-S-14-0001 00002
http://www.eia.gov/ http://www.eia.gov/dnav/pet/hist/LeafHandler.ashx?n=pet&s=rclc1&f=m
Option Year Price (O) – The Mean average of the price of crude oil the first three months of the Option Renewal year as reported by the U.S. Energy Information Administration. If the contract is being renewed the summer of 2015, it would be (January 2015 + February 2015 + March 2015)/3.
Bituminous Tasks (B) – A summation of the following task item numbers at base contract award prices:
403.01 404.01 409.01 410.01 411.01 411.05 430.01
Non-Bituminous Tasks (N) – A summation of the tasks not listed under “Bituminous Task” at base contract award prices.
Price Variance (V) - The percent change in a barrel of oil from the base contract award year to the Option Renewal year.
Adjustment Price (A) – The adjusted price for the summed tasks.
Formulas:
V = (O/C-1)*100
A = B*(1+0.23(O/C-1))
A = N*(1+0.14(O/C-1))
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C. 1 - Scope of Work
The Contractor shall provide for all labor, material, supplies, transportation, management, supervision, equipment, and all other necessary items for complete and usable projects, performing all work in complete compliance with all plans, drawings, and specifications issued. The Contractor will be required to perform multi-discipline construction and maintenance work using common trades identified in the Davis Bacon Wage Determination and other trades common to the construction industry or the Service Contract Act Determination.
Types of projects/jobs contemplated under this contract may include, but are not limited to, road repair and construction including native surface, gravel, and paved surfaces; road decommissioning and obliteration; bridge repair and maintenance; retaining wall repair and construction; culvert installation and stream channel restoration for aquatic organism passage; and road maintenance including road reconditioning, road blading, aggregate stabilization, dust abatement, guardrail installation, signing, and brushing.
C- 2 - Location
Work shall be accomplished within the administrative areas of the locations identified in Section B which includes National Forest in the states of Nevada, Utah, Southern Idaho, Western Wyoming, and Bridgeport Ranger District in California. Specific project locations shall be identified per individual task order.
C- 3 – Washing Equipment
All equipment used on the project site shall be cleaned and inspected off National Forest land prior to its arrival on the site. The equipment must be 1) free of all mud, seeds, plants, and plant fragments; and 2) free of oil, fuel, or toxic leaks that would wash off into the water. Notify the Contracting Officer 48 hours in advance of mobilizing equipment to the project site to arrange an inspection and meet the requirements of FSSS 171.
C- 4 – Fuel Storage
A written Hazardous Spill Plan may be required per individual Task Orders for projects which involve fuel storage and refueling actions. The plan shall contain a description of the specific hazardous materials, procedures, and spill containment that will be used, including inventory, storage, and handling. All vehicles carrying fuel will have specific equipment and materials needed to contain or clean up any incidental spills at the project site. Equipment and materials will be specific to each project site, and can include spill kits appropriately sized for specific quantities of fuel, shovels, absorbent pads, straw bales, containment structures and liners, and/or booms. Storing and refueling areas will be located in staging areas, away from streams, where a spill would not have the potential to reach live water. Containment structures may be necessary if prevention of spilled material from reaching live water cannot be assured.
Should quantities of stored fuel for a project exceed 660 gallons in a single tank; or exceed 1320 gallons for all storage combined;
contractors and agency operators will be required to have a standard EPA written Spill Prevention Control and Containment (SPCC) Plan onsite, which describes measures to prevent or reduce impacts from potential spills from fuel, hydraulic fluid, etc. (40 CFR 112, Oil Pollution Act relating to SPCC Plans).
Storage of fuel and other toxicants within Riparian Conservation Areas (RCA – within 300 feet of live streams) is prohibited.
Refueling of equipment may be done within the RCA only at locations approved in advance by the Contracting Officer (CO).
Centrifugal pumps used for removing water from structure excavation shall sit in a secondary spill container with sufficient capacity to contain the quantity of fuel in the pump fuel tank. A Spill Prevention & Containment Plan is required and shall be submitted to the CO for approval prior to beginning construction. A spill containment kit shall be available on site that is to accommodate potential spills from the equipment used during construction.
C- 6 – Traffic Control Plan
Individual Task Orders may require that a Traffic Control Plan be submitted for approval meeting requirements of FSSS 156.
C- 7 - Government-Furnished Materials/Equipment
(a) Government Furnished Materials (GFM)/Government Furnished Equipment (GFE): In the normal course of performance of the MATOC contract, GFM/GFE will not be furnished to the Contractor however, the Government reserves the right to provide GFM and/or GFE to be used on any Task Order. In such cases, these materials shall be receipted for by the Contractor and the Schedule of Item line item material cost shall be excluded from the price of the Task Order. Any GFM/GFE furnished to the contractor will be specifically identified in the statement of work and on the schedule of items of the individual task order. The location (as well as the type, quantity, and description) of GFM/GFE will be identified in individual Task Order.
In such cases, these materials shall be received for by the Contractor and the Schedule of Item line item material cost shall be excluded from the price of the Task Order. TThe Contractor shall follow the instructions of the Contracting Officer’s Representative (COR) regarding the disposition of all Government-furnished property not consumed in performance of the Task Order.
(b) Contractor Transporting: The Contractor, with its own resources, and at no cost to the Government, shall transport all GFM and/or GFE, if any, described on the Task Order from the Government storage area to the work site indicated in the Task Order.
Transportation Cost: It is anticipated that the majority of GFM/GFE will be provided at or adjacent to the project site. In such instances, no separate transportation costs would be incurred or cost. If transportation of GFM/GFE is other than what would normally be encountered, a separate cost may be negotiated into the pricing of the associated Task Order.
(c) Risk and Responsibility: Once accepted, the Contractor assumes the risk and responsibility for the loss or damage to any
GFM/GFE.
C- 8 – Recycling and Disposal of Refuse
With the exception of materials specifically indicated or specified to be salvaged for reuse in construction, or turned over to the Government, all refuse, excess or waste materials resulting from construction operations shall become the property of the Contractor and shall be recycled and/or disposed of. All disposals shall be in accordance with federal, state, and local laws and regulations. No disposal, viewing or sale of materials and/or equipment shall be allowed on Government property.
C-9 – Safety
During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards, 29 CFR Part 1926 - Safety and Health Regulations for Construction. Smoking will not be permitted in any building or structure.
C-10 – Temporary Facilities
(a) STAGING AREA: The Contracting Officer Representative shall arrange the location for exterior stockpiling of materials. The Government will provide adequate staging area as close to the work site as practicable. The Contractor shall be responsible for protecting materials stockpiled against adverse weather, damage, theft, and other risks of loss. The Government assumes no responsibility for material or equipment left in the storage area.
(b) SANITARY FACILITIES: Toilet facilities will not be provided by the Government at work sites.
C-11 – Existing Utilities
The Contractor shall field verify all utility locations before digging or trenching. This shall include, but not limited to, the use of sonic, electronic or magnetic detection devices, by noting pull box and utility box locations at the surface, use of locator services, and by potholing. Contractor shall be responsible for repairing any utilities damaged during construction at no additional cost to the Government.
C-12 – Specifications
The work shall conform to specifications included in this contract and any supplemental specifications and/or scope of work issued in conjunction with each individual Task Order. All work shall be performed in compliance with the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects FP-03 and all Forest Service Supplements.
C-13 – Drawings
The work shall conform to drawings provided with a Task Order.
C- 14 - Submittals
(a) Definition: Submittals - Product literature, catalog cuts, product samples, shop drawings, as-built drawings, Quality Control Plans, and other documents submitted to the Contracting Officer for information or for review and approval when required by the Task Order.
(b) Submittals shall be presented in two copies unless indicated otherwise. The Contracting Officer will return one copy of the submittal to the Contractor, whether approved or rejected.
(c) All submittals shall be accompanied with a transmittal sheet signed by the Project Site Superintendent. Salient characteristics of the materials proposed for use shall be clearly identified in the submittal. The Project Site Superintendent shall certify that he has reviewed the submittal and has determined that the submittal is in full compliance with the requirements of the Contract and Task Order. Illegible, incomplete, or uncertified submittals may be rejected.
(d) Submittals shall be approved by the Contracting Officer prior to any work being performed on the Task Order or materials being delivered to the job site.
(e) Review of submittals, and corrections or comments made during the review, does not relieve the Contractor from compliance with the requirements of this Contract.
(f) Allow 14 calendar days for government review of submittals. Review time shall commence upon receipt of a satisfactory submittal certified by the Project Site Superintendent containing all information required to completely and thoroughly evaluate the submittal.
Time shall start anew for each submittal and any required resubmissions.
C-15 – Catalog Cuts
Catalog cuts shall contain manufacturer's description, specifications and sketches of the material and equipment provided. The catalog cut shall contain sufficient information, which can be used to determine compliance with these specifications. Submit catalog cuts as required by a negotiated Task Order. Clearly indicate selected item and components being proposed.
C-16 - Samples
Product samples shall include color, pattern, style, and other information required to fully describe the items being proposed as required by the Task Order.
C-17 - Shop Drawings
Submit shop drawings when required by the Task Order. Drawings shall indicate layouts, dimensions, materials, and other information required to fully describe the items being installed.
C-18 – Test Results
Submit test results as required by the Task Order.
C-19 – Permits and Certificates
Submit copies of all permits and certificates as required by the Task Order.
C-20 – Hazardous Material Identification
Submit Material Safety Data Sheets (MSDS) for any materials defined as hazardous under the most current revision of Federal Standard 313. Two copies of each MSDS shall be submitted to the Contracting Officer no later than the delivery date of the product.
C-21 - As-Built Drawings
When As-Built Drawings are required by a Task Order, the Contractor shall maintain at the job site one set of contract drawings marked in red to show any deviations which are found to exist or have been made from the contract drawings. Upon completion of the work, the marked set of drawings shall be delivered to the Contracting Officer. Request for final payment will not be approved until the marked drawings are delivered to the Contracting Officer.
C-22 - Barricades, Warning Signs, and Other Devices
The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.
The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. Trenches and other hazards will be signed and flagged in such a way that the public will be aware of the hazard.
All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.
The Contractor shall furnish, erect, maintain, and remove temporary traffic control signs. Sign details and installation shall conform to the (MUTCD) standards for temporary signs on a rural highway. A sign plan shall be submitted to the CO for approval prior to fabrication or installation of the signs. Specific locations shall be approved by the COR prior to installation. All signs shall be installed prior to commencing on-site work.
C-23 – Standard Specifications For Construction Of Roads And Bridges on Federal Highway Projects
The Standard Specifications for this project are contained within the “Standard Specifications for…