Questions and Answers - 2nd Response
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site_Visit_Q As_-_III.pdf | ||
| Site_Visit_Attendance_Roster.pdf | ||
| Site_Visit_Q As.pdf | ||
| Amendment_000003.pdf | ||
| Amendment_000002.pdf | ||
| Amendment_000001.pdf | ||
| Attachment_J-4.pdf | ||
| Attachment_J-5.pdf | ||
| Attachment_J-3.pdf | ||
| Attachment_J-2.pdf | ||
| Attachment_J-1.pdf | ||
| AG-82X9-S-15-0006.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Forest Service
Rocky Mountain Region
Acquisition Management
740 Simms Street Golden, CO 80401 Voice: 303-275-5350
TDD: 303-275-5367
Caring for the Land and Serving People Printed on Recycled Paper
Lake George Work Center Expansion
AG-81X9-S-15-0006
Questions & Answers (2nd Response)
12. Has the building been tested for asbestos?
Answer: No.
13. What is the required Warranty period for the project?
Answer: One year unless otherwise specified.
14. Will communication cabling be installed by the owner?
Answer: No, contractor to provide raceway, wire, termination and testing per specifications.
15. All documents required with submittal …..is that submitted on 1 May or beforehand?
Answer: The submittals are required after the contact is awarded but prior to any construction taking place.
16. Section 017419 was discussed to the pre-bid?
Answer: COR recommends that this section be deleted from the contract. Construction waste is the responsibility on the contractor and it is required to be removed and disposed of properly from the construction site in a timely manner.
17. Soil testing required?
Answer: Yes, guidelines are given in section 312250.
18. Compaction testing?
Answer: Yes, guidelines are given in section 312250.
19. Do we need to change the electrical service to the office and Warehouse?
Answer: Yes, drawing sheet E0.2.
20. Where are the items to be removed located?
Answer: All items to be removed are located on sheet A1.1. The new finishes are called out on Sheet A2.3.
21. What does “EXG” mean?
Answer: The abbreviation “EXG” means existing.
22. Will the government occupy the building during construction?
Answer: Yes.
23. Is sub metering required for each of the electrical panels on the buildings?
Answer: Yes.
24. Can we sub-feed the warehouse from the office panel?
Answer: NO, the subpanel to the warehouse and office are to originate at the MEP.
25. Who is responsible for building inspection?
Answer: Keep in mind this is federally owned property, sometimes the State and local building officials will not issue permits for this type of facility, therefore the inspection will result back to the Forest Service. The Forest Service will require a letter stating that the State or Local official will not inspect.