Attachment_J-1.pdf
PDF 3 MB Posted
- Attached to
- Lake George Work Center Office Expansion
- Solicitation number
- AG-82X9-S-15-0006
About this file
Specifications Attachment J.1.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site_Visit_Q As_-_III.pdf | ||
| Site_Visit_Q As_-_II.pdf | ||
| Site_Visit_Attendance_Roster.pdf | ||
| Site_Visit_Q As.pdf | ||
| Amendment_000003.pdf | ||
| Amendment_000002.pdf | ||
| Amendment_000001.pdf | ||
| Attachment_J-4.pdf | ||
| Attachment_J-5.pdf | ||
| Attachment_J-3.pdf | ||
| Attachment_J-2.pdf | ||
| AG-82X9-S-15-0006.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture
Forest Service
Region 2 Pike and San Isabel National Forests, Cimarron and Comanche National Grasslands
February 2015
Lake George Work Center Office Expansion
Final Specifications
AUSD
Attachment J.1. AG-82X9-S-15-0006 Page 1 of 316
This page intentionally left blank.
Attachment J.1. AG-82X9-S-15-0006 Page 2 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 001500-1
PSICC NFs AND NGs LIST OF DRAWINGS AND SPECIFICATIONS
SECTION 001500
PSICC NATIONAL FORESTS AND GRASSLANDS
LAKE GEORGE WORK CENTER OFFICE EXPANSION
LIST OF DRAWINGS AND SPECIFICATIONS
PART 1 – GENERAL
1.1 DESCRIPTION
A. List of Contract Drawings:
1. Index of Sheets:
T1.0 Title Sheet D1.0 Demolition Site Plan C1.0 Site Layout Plan and Details A0.1 A1.1 A2.1 A2.2 A2.3 A3.1 A3.2 A4.1 A5.1 A6.1 A7.1 A8.1 A9.1 A10.1
Notes, Symbols, Abbreviation and Wall Types First Floor Demo Plan First Floor Plan Reflected Ceiling Plan Finish Floor Plan Existing Exterior Elevations Exterior Elevations Building Section Wall Sections Roof Plan & Details Entrance Ramp Details Architectural Details Restroom Plan & Elevations Window, Door Types & Schedules
S0.1 Legend & Abbreviations S0.2 General Notes and Design Criteria S0.3 General Notes S0.4 Quality Assurance and Quality Control S0.5 Quality Assurance and Quality Control S2.1 First Floor Foundation Plan S2.2 Roof Framing Plan S3.1 Typical Details S3.2 Typical Wall Details M0.1 Schedules, General Notes, and Legend M1.1 Mechanical and Plumbing Floor Plans and Isometrics M1.2 Mechanical Basement Plan and Photographs E0.1 Schedules, General Notes, Legend, and Panelboard E0.2 One Line Diagram and Details E1.1 Electrical Removal Floor Plan and Photographs E2.1 Power and Lighting Floor Plans U1.1 Utility Site Plan U2.1 Utility Details 35 Total Plan Sheets in this Contract
Attachment J.1. AG-82X9-S-15-0006 Page 3 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 001500-2
B. List of Contract Specifications
1. Index of Specifications
DIVISION 1 - GENERAL REQUIREMENTS
Section 001500 List of Drawings and Specifications Section 010250 Definition of Contract Items and Measurement and Payment Section 011000 Summary of Work Section 011400 Work Restrictions Section 011500 Hazardous Materials Requirements Section 011700 Accident Prevention Section 013100 Project Management and Coordination Section 013300 Submittal Procedures Section 014000 Quality Requirements Section 014500 Construction Indoor Air Quality Management Section 015000 Temporary Facilities and Controls Section 017300 Execution Requirements Section 017419 Construction Waste Management Section 017700 Closeout Procedures Section 017823 Operation and Maintenance Data
DIVISION 2 – EXISTING CONDITIONS
Section 024119 Selective Demolition
DIVISION 3 – CONCRETE
Section 033000 Cast-in-Place Concrete
DIVISION 4 – MASONRY N/A
DIVISION 5 – METAL
Section 055213 Pipe and Tube Railings
DIVISION 6 – WOOD AND PLASTICS
Section 061000 Rough Carpentry Section 061600 Section 062013 Section 062023
Sheathing Exterior Finish Carpentry Interior Finish Carpentry
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
Section 071113 Section 072100 Section 072119 Section 072500 Section 072600 Section 073113 Section 076200 Section 077100 Section 079200
Bituminous Dampproofing Thermal Insulation Foamed-In-Place Insulation Weather Barriers Vapor Retarders Asphalt Shingles Sheet Metal Flashing and Trim Roof Specialties Joint Sealants
Attachment J.1. AG-82X9-S-15-0006 Page 4 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 001500-3
DIVISION 8 – DOORS AND WINDOWS
Section 081416 Section 085200 Section 087100
Flush Wood Doors Wood Windows Door Hardware
DIVISION 9 – FINISHES
Section 092900 Section 093013 Section 096513 Section 096519 Section 096813 Section 099000
Gypsum Board Ceramic Tile Resilient Base and Accessories Resilient Tile Flooring Tile Carpeting Painting
DIVISION 10 – SPECIALITIES
Section 101423 Section 102800
Panel Signage Toilet, Bath and Laundry Accessories
DIVISION 22 – PLUMBING
Section 220050 Plumbing Materials and Methods Section 224000 Plumbing Fixtures
DIVISION 23 – HEATING VENTILATING AND AIR CONDITIONING
Section 230050 HVAC Materials and Methods Section 230100 HVAC Equipment Section 230593 Testing, Adjusting, and Balancing For HVAC
DIVISION 26 – ELECTRICAL
Section 260050 Electrical Materials and Methods
DIVISION 27 – COMMUNICATIONS
Section 270050 Voice and Data Communication Materials and Methods
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY N/A
DIVISION 31 – EARTHWORK
Section 312250 Earthwork Section 312500 Temporary Erosion and Sedimentation Control
DIVISION 32 – EXTERIOR IMPROVEMENTS
Section 321123 Aggregate Base Course Section 321313 Concrete Paving
Section 321316.23 Stamped Concrete Paving
DIVISION 33 – UTILITIES
Section 331100 Water Distribution Section 333110 Sanitary Sewerage
Attachment J.1. AG-82X9-S-15-0006 Page 5 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 001500-4
END OF SECTION 001500
Attachment J.1. AG-82X9-S-15-0006 Page 6 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 010250-1
PSICC NFs AND NGs DEFINITION OF CONTRACT ITEMS AND
MEASUREMENT AND PAYMENT
SECTION 010250
DEFINITION OF CONTRACT ITEMS
AND
MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general; what is and what is not included in a contract item; the limits or cut-off points where one item ends and another begins; and method of measurements and basis of payment for work items listed in the Schedule of Items.
B. Work: Furnishing all labor, materials, equipment, and other incidentals necessary to successfully complete the project or any portion of it, and carrying out all duties and obligations imposed by the contract on the Contractor.
C. Payment: For each individual item listed here and in the Schedule of Items, payment shall be full compensation for all work related to the particular item in accordance with these specifications and as shown on the drawings.
D. Measurement and payment for contract work shall be made only for and under those pay items included in the Schedule of Items. All other work and materials shall be considered incidental or as included in the payment for items shown.
1.2 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
B. Lump Sum: Do not measure directly. The bid amount is complete payment for all work described in the contract and necessary to complete the work for that item.
PART 2 - METHOD OF MEASUREMENT
2.1 GENERAL
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
B. LUMP SUM QUANTITIES (LSQ)
1. These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall be measured complete and in-place.
Attachment J.1. AG-82X9-S-15-0006 Page 7 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 010250-2
MEASUREMENT AND PAYMENT
PART 3 – DEFINITION OF CONTRACT ITEMS
3.1 SCHEDULE OF ITEMS
A. The project Schedule of Items includes several sections to organize the contract items into Base Items and Optional Items. When a pay item is described as a Base Item, the description will be the same when that item or a similar item is included as an Optional Item. Provide item pricing for all items listed in the Schedule of Items.
Contract award will be made for all Base Items. Those items listed as Optional Items will be awarded based on available project funding.
3.2 DEFINITION OF BASE ITEMS
A. Base Items:
1. Base Item No. 1– Mobilization, Demobilization, Bonding and Insurance
a. Measurement: This item is measured as a Lump Sum quantity.
b. Payment: The contract lump sum price shown in the Schedule of Items shall include all materials, equipment, labor and incidentals required to perform all operations necessary for the movement of personnel, equipment, supplies and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site.
2. Base Item No. 2– Quality Control, Survey and Staking, As-Builts
a. Measurement: This item is measured as a Lump Sum quantity.
b. Payment: The contract lump sum price shown in the Schedule of Items shall include all materials, equipment, labor and incidentals required to perform all operations necessary including all Contractor sampling, testing, quality control work, construction surveying, staking, and as-builts.
3. Base Item No. 3 –Plumbing / Mechanical / Electrical / Telecommunications
Work
a. Measurement: This item is measured as a Lump Sum quantity.
b. Payment: The contract lump sum price shown in the Schedule of Items shall include all materials, equipment, labor, and incidentals required for removal and new plumbing, mechanical, electrical and telecommunications work inside the buildings to 5 feet beyond the building and site electrical work including trenching and backfilling.
4. Base Item No. 4 – Site Work
b. Payment: The contract lump sum price shown in the Schedule of Items shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications. Item includes shifting the existing road to the east to accommodate the building addition, elevating
Attachment J.1. AG-82X9-S-15-0006 Page 8 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 010250-3
MEASUREMENT AND PAYMENT
the finished road surface, complying with State of Colorado Stormwater Permit; and installation and maintenance of temporary erosion and sedimentation controls for the duration of the contract.
5. Base Item No. 5 – Water System Modifications
b. Payment: The contract lump sum price shown in the Schedule of Items shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications. Item includes installation of water lines, valves, valve boxes, and trenching.
6. Base Item No. 6 – Wastewater System Modifications
b. Payment: The contract lump sum price shown in the Schedule of Items shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications. Item includes installation of wastewater lines, cleanouts, connections, and trenching.
7. Base Item No. 7 – Building Addition
b. Payment: The contract lump sum price shown in the Schedule of Items shall include all materials, equipment, labor and incidentals required to perform all operations necessary to complete the work as shown on the drawings and specifications including all structural and architectural modifications to construct the building addition and entry ramp and porch but excluding building Mechanical / Electrical / Plumbing Work included in Base Item No. 3. Items also include interior and exterior building demolition.
3.3 OPTIONAL ITEMS
A. No items have been identified as optional items.
END OF SECTION 010250
Attachment J.1. AG-82X9-S-15-0006 Page 9 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 010250-4
MEASUREMENT AND PAYMENT
THIS PAGE INTENTIONALLY LEFT BLANK.
Attachment J.1. AG-82X9-S-15-0006 Page 10 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 011000-1
PSICC NFs AND NGs SUMMARY OF WORK
SECTION 011000
SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of the contract is to provide for the complete construction of the project as described in the contract. The project requires the contractor to be responsible for supplying all labor, materials, equipment, miscellaneous items, freight, delivery, and all necessary valid licenses and permits required to complete work identified in Division 1 specification, “Definition of Contract Items and Measurement and Payment.”
B. The Lake George Work Center is the duty station for six permanent and typically eight to ten fire and fuels seasonal employees. The Lake George Work Center office is a 1,300 square foot log building on a stone foundation constructed in 1939 by the Civilian Conservation Corps. This project will expand the Lake George Work Center office to provide two accessible restrooms and additional entry space. The building addition will extend the eastern gable end of the office to the east and into the current site access road. The road will be shifted to the east to accommodate the expansion.
C. The Lake George Work Center is approximately 35 miles west of Colorado Springs, Colorado. Address: 140 Trail Creek Road, Lake George, CO 80827. From Colorado Springs, head west on U.S. Highway 24 for approximately 35 miles to Lake George, Colorado. The work center is just off of Highway 24 on the east side of the community, on the north side of the highway.
D. The site has several features of historic and/or archaeological significance. A Forest Service provided archaeologist will be onsite during all excavation phases of this project to observe and record any findings. The Forest Service archaeologist will coordinated with the COR and the Contractor may be required to stop work in the event of a historically and/or archaeologically significant finding.
1.2 MEALS AND LODGING
A. Meals and lodging are commercially available in Woodland Park, Colorado.
1.3 FIELD VERIFICATION
A. Field verify all dimensions affecting the work of this contract before ordering products.
1.4 PERMITS
A. Special permits for electrical work or any other permits required by County, State, or Federal laws or regulations shall be obtained by the Contractor.
Attachment J.1. AG-82X9-S-15-0006 Page 11 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 011000-2
PSICC NFs AND NGs SUMMARY OF WORK
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 011000
Attachment J.1. AG-82X9-S-15-0006 Page 12 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 011400-1
PSICC NFs AND NGs WORK RESTRICTIONS
SECTION 011400
WORK RESTRICTIONS
PART 1-GENERAL
1.1 USE OF PREMISES
A. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to immediate area of work.
2. Government Occupancy: Allow for Government occupancy of Project site.
Maintain areas for access and use by public visitors.
3. Driveways and Entrances: Keep driveways, parking areas, loading areas and en-trances serving premises clear and available to Government, Government's em-ployees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
B. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used fa-cilities without written permission from Government and authorities having jurisdic-tion.
1.2 GOVERNMENT'S OCCUPANCY REQUIREMENTS
A. Full Government Occupancy: Government will occupy site during construction peri-
od. The Government requires periodic access to building areas to access files and in-formation. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits.
1.3 WORK RESTRICTIONS
A. Nonsmoking Building: Smoking is not permitted within the buildings or within 25 feet (8 m) of entrances, operable windows, or outdoor air intakes.
B. Sanitary Facilities: Use of on-site Government sanitary facilities will be permitted as long as the facilities are kept in a clean and operable condition.
C. Overnight camping on the Site is not permitted.
Attachment J.1. AG-82X9-S-15-0006 Page 13 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 011400-2
PSICC NFs AND NGs WORK RESTRICTIONS
1.4 CONTRACTOR’S RESPONSIBILITIES
A. The Contracting Officer will designate areas on the site for material storage, stockpil-ing, and temporary storage buildings. Confine storage of materials to areas as ap-proved by the CO.
B. Provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Minimize disturbance of all undisturbed areas.
PART 2- PRODUCTS (NOT USED)
PART 3- EXECUTION (NOT USED)
END OF SECTION 011400
Attachment J.1. AG-82X9-S-15-0006 Page 14 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 011500-1
PSICC NFs AND NGs HAZARDOUS MATERIALS REQUIREMENTS
SECTION 011500
HAZARDOUS MATERIALS REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes general administrative requirements and procedures in the event hazardous materials are discovered during the project.
1.2 SUBMITTALS
A. Material Safety Data Sheets (MSDS): Retain copies on site of all material safety data sheets for all applicable products, including but not limited to: paints, adhesives, mastics, solvents and finishes, etc. used during the construction work. Furnish copies of all MSDS’s to the Government upon request and include in the Project Record Document submittal.
B. Certification: Submit written certification that no asbestos-containing materials or hazardous materials have been used or incorporated in the new Work. Submit certification prior to Final Completion.
1.3 QUALITY ASSURANCE
A. No known asbestos containing materials are located in the building. Contractor is responsible for reviewing the existing construction documents of the original building at the project site and becoming familiar with any hazardous materials in the work areas.
1.4 PROJECT/SITE CONDITIONS
A. If hazardous materials are discovered during the construction period; immediately notify the Contracting Officer. Abatement measures will be taken by the Government under separate contract. The Contractor shall coordinate sequencing and scheduling with that of the hazardous materials abatement work.
B. Hazard Communication Requirements: Comply with mandatory federal rules and regulations concerning Hazardous Communication, specifically for those regulations contained in 29 CFR 1910.1200 Hazard Communication.
1. Contractor working at sites under the control of the Government shall make available to the CO, upon request, copies of the Hazard Communication Pro-gram used by their firm. In addition to this requirement, all regulations to Multi-employer workplaces shall be adhered to. These regulations are found in 29 CFR 1910.1200, (e) (2) (i) through (e) (4) specifically:
Attachment J.1. AG-82X9-S-15-0006 Page 15 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 011500-2
PSICC NFs AND NGs HAZARDOUS MATERIALS REQUIREMENTS
a. (e) (2) Multi-employer workplaces. Employers who produce, use or store hazardous chemicals at a workplace in such a way that employees of other employer(s) may be exposed (for example, employees of a construction contractor working on a site shall additionally ensure that the hazard communication programs developed and implemented under paragraph (e) include the following:
1) (3) (2) (i) The methods the employer will use to provide the other employer(s) with a copy of the material safety data sheet, or to make it available at a central location in the workplace, for each hazardous chemical the other employer(s)’ employees may be exposed to while working;
2) (e) (2) (ii) The methods the employer will use to inform the other employer(s) of any precautionary measures that need to be taken to protect employees during the workplace’s normal operating condi-tions and in foreseeable emergencies; and,
3) (e) (2) (iii) The methods the employer will use to inform the other employer(s) of the labeling system used in the workplace.
b. (e) (3) the employer may rely on an existing hazard communication pro-gram to comply with these requirements, provided that it meets the criteria established in this paragraph (e)
c. (e) (4) The employer shall make written hazard communication program available, upon request, to employees, their designated representatives, the Assistant Secretary and the Director, in accordance with the requirements of 29 CFR 1910.1200 (e).
2. The referenced regulations were excerpted from 29 CFR 1910.1200. This ex-cerpt shall not be relied upon for compliance with mandatory federal, state and local regulations. Comply with all such regulations and shall be solely liable for insuring that all requirements under applicable regulations are met.
PART 2 – PRODUCTS – (NOT APPLICABLE)
PART 3 – EXECUTION
3.1 EXAMINATION:
C. Stay alert to the possibility that the work may uncover asbestos base containing mate-rials, lead based paint, or other hazardous materials. If suspected materials are found, notify the CO and stop all work in the area immediately. If the suspected materials prove to contain asbestos, lead based paint or other hazardous materials the Govern-ment will arrange to have the materials abated in a timely manner.
END OF SECTION 011500
Attachment J.1. AG-82X9-S-15-0006 Page 16 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 011700-1
PSICC NFs AND NGs ACCIDENT PREVENTION
SECTION 011700
ACCIDENT PREVENTION
PART 1 - GENERAL
1.1 DESCRIPTION
A. The work of this section consists of establishing an effective accident prevention plan and providing a safe environment for personnel and visitors.
1.2 SUBMITTALS
A. Accident Prevention Plan: Before on-site work begins, submit a company approved accident prevention plan. This plan will be posted in the contract file. Design the plan to address Federal, State, and Local Occupational Safety and Health requirements that apply to this project. No progress payments will be processed until the plan is received. As a minimum the plan shall include:
1. Name, position title and contact information of company executive responsible for approving the Accident Prevention Plan.
2. Name and contact information of supervisor responsible to carry out the plan.
3. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, government personnel, and the Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.
4. Contingency plans for emergency situations such as medical, fire, hazard material spills and other contract assessed hazard prevention and abatement requirement needs that apply to this project.
B. Certificates: Provide certificates from a mechanic that all mechanical equipment has been inspected and meets OSHA requirements.
C. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.
D. Submit a brief report of safety meetings and of inspections.
E. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.
1.3 QUALITY ASSURANCE
A. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the General Provisions: In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
Attachment J.1. AG-82X9-S-15-0006 Page 17 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 011700-2
B. Qualifications of Employees:
1. Ensure employees are physically qualified to perform assigned duties in a safe manner.
2. To as great an extent as possible, do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
3. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment. Individually test newly hired operators by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
1.4 ACCIDENT REPORTING
A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Within 7 calendar days of a reportable accident, fill out and forward to the CO a CA-1 form, which may be obtained from CO.
B. All Other Accidents: Report all other accidents to the CO as soon as possible and assist the CO and other officials as required in the investigation of the accident.
PART 2 – PRODUCTS
2.1 FIRST AID FACILITIES
A. Provide adequate facilities for the number of employees and the type of construction at the site.
2.2 PERSONNEL PROTECTIVE EQUIPMENT
A. Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.
PART 3 – EXECUTION
3.1 EMERGENCY INSTRUCTIONS
A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
3.2 ESCAPE ROUTES
A. Provide and maintain adequate escape routes at all times in accordance with the Life Safety Code (NFPA 101-91). No corridor, aisle, stairway, door, or exit shall be obstructed or used in a manner that interferes with escape routes.
Attachment J.1. AG-82X9-S-15-0006 Page 18 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 011700-3
3.3 PROTECTIVE EQUIPMENT
A. Inspect personal protective equipment daily and maintain in a serviceable condition.
Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
3.4 SAFETY MEETINGS
A. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.
B. Conduct monthly safety meetings for all levels of supervision. Notify the CO so the CO may attend. Use these meetings to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the accident prevention plan. The CO will enter the results of the meetings into the government’s daily log.
3.5 HARD HATS AND PROTECTIVE EQUIPMENT AREAS
A. Designate a hard hat area. Post the hard hat area in a manner satisfactory to the CO.
B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times. As a minimum, provide two hard hats for use by visitors. Change liners before reissuing hats.
3.6 TRAINING
A. First Aid: Provide adequate training to ensure prompt and efficient first aid.
B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
END OF SECTION 011700
Attachment J.1. AG-82X9-S-15-0006 Page 19 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 011700-4
Attachment J.1. AG-82X9-S-15-0006 Page 20 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 013100-1
PSICC NFs AND NGs PROJECT MANAGEMENT AND COORDINATION
SECTION 013100
PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This section includes certain administrative provisions for managing and coordinating construction operations, including but not limited to the following:
1. General project coordination.
2. Conservation.
3. Conferences and meetings.
1.2 GENERAL PROJECT COORDINATION
A. Coordination of Trades: Coordinate construction operations included in the various sections of the Specifications to provide an efficient and orderly installation of each part of the Work. Coordinate construction operations included under different sections of the Specifications that depend on each other for proper installation, connection or operation.
1. Schedule construction operations in the sequence required to obtain the best results where the installation of one part of the Work depends on installation of other components before or after that part.
2. Coordinate installation of different components to provide maximum accessibility for required maintenance, service, testing and repair.
3. Accommodate items scheduled for later installation.
B. Notification: Where necessary, prepare and distribute memoranda to each party involved, outlining special procedures required for coordination. When applicable, include notices, reports and meeting minutes as part of the memoranda.
C. Administrative Procedures: Coordinate scheduling and timing of administrative procedures with other construction activities to avoid conflicts and promote orderly progress of the Work. Administrative procedures include but are not limited to the following:
1. Preparation of schedules.
2. Installation and removal of temporary facilities.
3. Delivery and processing of submittals.
4. Progress meetings.
5. Project closeout activities.
1.3 CONSERVATION
Attachment J.1. AG-82X9-S-15-0006 Page 21 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 013100-2
A. Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water and materials.
1.4 CONFERENCES AND MEETINGS
A. Preconstruction Conference: The Contracting Officer shall schedule a preconstruction conference before starting construction at a time and place convenient to the Contractor.
Conference shall review responsibilities and personnel assignments.
1. Attendees: Participants at the conference shall be familiar with the project, shall be authorized to conclude matters relating to the Work, and shall minimally include representatives of the following parties:
a. Contracting Officer.
b. Contracting Officer’s Representative.
c. Contractor.
d. Major subcontractors.
e. Major suppliers.
f. Other concerned parties.
2. Agenda: Subjects for discussion shall include items of significance that could effect progress, including but not limited to the following:
a. Tentative construction schedule.
b. Critical work sequencing.
c. Designation of responsible personnel.
d. Procedures for processing field decisions and Change Orders.
e. Procedures for processing Applications for Payment.
f. Distribution of Contract Documents.
g. Submittal of Shop Drawings, Product Data, and Samples.
h. Preparation of Record Documents.
i. Use of the premises.
j. Parking availability.
k. Office, work, and storage areas.
l. Equipment deliveries and priorities.
m. Safety procedures.
n. First aid.
o. Security.
p. Housekeeping and progress cleaning.
q. Working hours.
3. Reporting: No later than five (5) calendar days after the conference, the Contractor shall distribute minutes of the conference to each party present and to other concerned parties, including the Contracting Officer.
B. Progress Meetings: The Contracting Officer's Representative shall conduct progress meetings at the Project Site at regular intervals. Dates of meetings shall be coordinated with preparation of the payment request.
Attachment J.1. AG-82X9-S-15-0006 Page 22 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 013100-3
1. Attendees: In addition to the Contractor's and Contracting Officer's representatives, each subcontractor, supplier, or other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of the previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to the status of the Project.
a. Contractor's Construction Schedule: Review progress since the last meeting. Determine where each activity is in relation to the Contractor's Construction Schedule, whether on time or ahead or behind schedule.
Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to insure that current and subsequent activities will be completed within the Contract Time.
b. Review the present and future needs of each entity present, including but not limited to the following:
1) Interface requirements.
2) Time.
3) Sequences of operations.
4) Status of submittals.
5) Deliveries.
6) Off-site fabrication.
7) Access.
8) Site utilization.
9) Temporary facilities and controls.
10) Hours of work.
11) Hazards and risks.
12) Housekeeping and progress cleaning.
13) Quality and work standards.
14) Change Orders.
15) Documentation of information for payment requests.
16) Updating of Record Documents.
3. Reporting: No later than five (5) calendar days after each meeting, the Contractor shall distribute minutes of the meeting to each party present and to other concerned parties, including the Contracting Officer. Include a brief summary, in narrative form, of progress since the previous meeting and report.
4. Schedule Updating: The Contractor shall revise the Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. The revised schedule shall be issued concurrently with the report of each meeting.
1.5 SUBMITTALS
Attachment J.1. AG-82X9-S-15-0006 Page 23 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 013100-4
A. Coordination Drawings: Comply with the shop drawing requirements specified in Division 1 Section "Submittal Procedures."
B. Staff Names: Within 15 days of commencement of construction operations, submit a list of the Contractor’s principal staff assignments, including the superintendent and other personnel in attendance at the site; identify their duties and responsibilities; and their addresses and telephone numbers.
1. Post copies of the list in the Project meeting room, the temporary field office and each temporary telephone.
PART 2 - PRODUCTS (Not applicable)
PART 3 - EXECUTION
3.1 GENERAL COORDINATION PROVISIONS
A. Inspection of Conditions: Prior to installations, require the installer of each major component to inspect both the substrate and conditions under which work is to be performed.
1. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.
2. Coordinate temporary enclosures with required inspections and tests to minimize the necessity of uncovering completed construction for that purpose.
B. Construction in Progress: Keep construction in progress, and adjoining materials in place, clean during handling and installation. Apply protective coverings where required for protection from damage or deterioration.
C. Completed Construction: Clean completed construction, and provide maintenance, as frequently as necessary to prevent damage or soiling or other deterioration through the remainder of the construction period. Adjust and lubricate operable components as necessary to assure operability without damage.
D. Limiting Exposures: Supervise construction operations to prevent exposure of any part of construction, completed or in progress, to harmful, dangerous, damaging or otherwise deleterious conditions during the construction period. Such conditions include but are not limited to the following:
1. Excessive static or dynamic loading.
2. Excessive internal or external pressures.
3. Excessively high or low temperatures.
4. Thermal shock.
5. Excessively high or low humidity.
Attachment J.1. AG-82X9-S-15-0006 Page 24 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 013100-5
6. Pollution and air contamination.
7. Water or ice.
8. Chemicals and solvents.
9. Light.
10. Radiation.
11. Puncture.
12. Abrasion.
13. Heavy traffic.
14. Soiling, staining, and corrosion.
15. Bacteria.
16. Rodent and inset infestation.
17. Combustion.
18. Electrical current.
19. High-speed operation.
20. Improper lubrication.
21. Unusual wear or other misuse.
22. Contact between incompatible materials.
23. Destructive testing.
24. Misalignment.
25. Excessive weathering.
26. Unprotected storage.
27. Improper shipping or handling.
28. Theft or vandalism.
END OF SECTION 013100
Attachment J.1. AG-82X9-S-15-0006 Page 25 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 013100-6
Attachment J.1. AG-82X9-S-15-0006 Page 26 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 013300-1
PSICC NFs AND NGs SUBMITTAL PROCEDURES
SECTION 013300
SUBMITTAL PROCEDURES
PART 1- GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submittals re-quired for the performance of the work. Submittals include action type and adminis-trative/informational submittals.
1. Action Submittals.
a. Product Data.
b. Shop Drawings.
c. Samples.
d. Request for Information (RFI).
e. Contractor quality control plan.
f. Construction indoor air quality plan.
g. Construction waste management plan.
2. Administrative/Informational Submittals.
a. Contractor’s construction schedule.
b. Accident prevention plan.
c. Submittal schedule.
d. Staff names and responsibilities.
e. Contractor’s quality control daily construction reports.
f. Construction progress schedules.
g. Permits, licenses, and certificates.
h. Applications for payment.
i. Performance and payment bond.
j. Insurance certificates.
k. List of subcontractors.
l. Test reports.
m. Field reports.
n. Manufacturer’s instructions.
B. See Division 1 Section "Closeout Procedures" for submitting Closeout Submittals, Warranties, Project Record Documents, Operation and Maintenance Manuals and “as built” drawings.
1.2 DEFINITIONS
A. Action Submittals: Written and graphic information that requires Contracting Of-ficer’s (CO's) responsive action.
Attachment J.1. AG-82X9-S-15-0006 Page 27 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 013300-2
B. Administrative/Informational Submittals: Written information that does not require CO's approval. Submittals may be rejected for not complying with requirements.
C. Electronic Submittals: Where identified, transmit submittals in electronic (PDF) for-mat using Submittal Exchange, a website service designed specifically for transmitting submittals.
1. Electronic submittal process is not intended for color samples, color-charts, or physical material samples. For these items, submit actual items.
1.3 SUBMITTAL PROCEDURES
A. General: The following procedure requirements pertain to all submittals regardless of the method utilized for submission.
1. Review each submittal and check for compliance with the Contract Documents.
Highlight, encircle, or otherwise identify deviations from the Contract Docu-ments on submittals.
2. Contracting Officer will not review submittals that do not bear Contractor's ap-proval stamp and will return them without action.
3. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
4. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.
a. Initial Review: Allow 10 working days for initial review of each submit-tal. Allow additional time if processing must be delayed to permit coordi-nation with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
b. If intermediate submittal is necessary, process it in same manner as initial submittal.
c. Allow 10 working days for processing each re-submittal.
d. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
B. Submittal Stamp: Electronic or ink stamp each submittal utilized for identification and including the following:
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space approximately 2 by 3 inches on label or beside title block to record Contractor's review and approval markings and action taken by CO.
3. Include the following information on label for processing and recording action taken:
a. Project name.
Attachment J.1. AG-82X9-S-15-0006 Page 28 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 013300-3
b. Date.
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. Other necessary identification.
C. Electronic Submittal Procedures: Where identified, utilize electronic submittal proce-dure. The full cost of Submittal Exchange project subscription is provided by the Government under separate contract.
1. Preparation of Submittals: Use any or all of the following options:
a. Subcontractors and Suppliers provide electronic (PDF) submittals to Gen-eral/Prime Contractor via the Submittal Exchange website.
b. Subcontractors and Suppliers provide paper submittals to General/Prime Contractor who electronically scans and converts to PDF format.
c. Subcontractors and Suppliers provide paper submittals to Scanning Ser-vice which electronically scans and converts to PDF format.
2. Before submitting submittals to the Contracting Officer, apply electronic ap-proval stamp certifying the submittal complies with the requirements of the Contract Documents including verification of manufacturer/product, dimen-sions, and coordination of information with other parts of the work.
3. Transmit each submittal to the Contracting Officer using the Submittal Ex-change website, www.submittalexchange.com.
4. Government review comments will be made available on the Submittal Ex-change website for downloading. General/Prime Contractor will receive email notice of completed review.
5. Distribution of reviewed submittals to subcontractors and suppliers is the re-sponsibility of the General/Prime Contractor. Use only final submittals with mark indicating action taken by Contracting Officer in connection with con-struction.
6. Submit two sets of paper copies of reviewed submittals at project closeout for record purposes in accordance with Division 01, “Closeout Procedures.”
7. Training: Training regarding use of the Submittal Exchange website and PDF submittals is provided from Submittal Exchange free of charge. Contact Sub-mittal Exchange at 1-800-714-0024.
8. Internet Service and Equipment Requirements
a. Email address and Internet access at Contractor’s main office.
b. Software: Adobe Acrobat (www.adobe.com), Bluebeam PDF Revu
(www.bluebeam.com), or other similar PDF review software for applying electronic stamps and comments.
Attachment J.1. AG-82X9-S-15-0006 Page 29 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 013300-4
PART 2 – PRODUCTS
2.1 ACTION SUBMITTALS
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
B. Product Data: Collect information into a single submittal for each element of con-struction and type of product or equipment. Submit product data through electronic submittal process.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are ap-plicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Compliance with recognized trade association standards.
g. Compliance with recognized testing agency standards.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams: Differentiate between manufacturer installed and field installed wiring. Show field-installed wiring, including power, signal, and control wiring.
f. Notation of dimensions established by field measurement.
D. Samples: Submit three (3) sets of Samples. The CO will return one set marked with action taken. Samples include partial sections of manufactured or fabricated compo-nents, cuts or containers of materials, color range sets, and swatches showing color, texture and pattern.
1. Mount, display or package samples in the manner to facilitate review of qualities indicated. Include the following:
Attachment J.1. AG-82X9-S-15-0006 Page 30 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 013300-5
a. Specification Section number and reference.
b. Generic description of the Sample.
c. Sample source.
d. Product name or name of the manufacturer.
e. Compliance with recognized standards.
f. Availability and delivery time.
2. Refer to Divisions 2 through 33 Sections for specific Sample requirements that illustrate workmanship, fabrication, techniques, details of assembly, connec-tions, operation and similar construction characteristics.
3. Submit a full set of choices where Samples are submitted for selection of color, pattern, texture or similar characteristics from a range of standard choices.
4. Maintain sets of Samples, as returned, at the Project Site, for quality compari-sons throughout the course of construction.
a. Unless noncompliance with the Contract Document provisions is ob-served, the submittal may serve as the final submittal.
b. Sample sets may be used to obtain final acceptance of the construction as-sociated with each set.
E. Requests for Information (RFI’s): Immediately on discovery of the need for addition-al information or interpretation of the Contract Documents, prepare and submit an RFI in the form specified.
1. RFI’s submitted by entities other than the Contractor shall not be accepted.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Con-tractor's work or work of subcontractors.
3. Content of the RFI: Utilize forms provided by the Contracting Officer. Include a detailed, legible description of item needing information or interpretation and the following:
a. Project name.
b. Project number.
c. Date.
d. Name of Contractor.
e. Name of Contracting Officer.
f. RFI number, numbered sequentially.
g. RFI subject.
h. Specification Section number and title and related paragraphs, as appro-priate.
i. Drawing number and detail references, as appropriate.
j. Field dimensions and conditions, as appropriate.
k. Contractor's suggested resolution. If Contractor's solution(s) impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the
RFI.
l. Contractor's signature.
Attachment J.1. AG-82X9-S-15-0006 Page 31 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 013300-6
m. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
n. Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
1) Include dimensions, thicknesses, structural grid references, and de-tails of affected materials, assemblies, and attachments on attached sketches.
4. CO's Action: CO will review each RFI, determine action required, and respond.
Allow seven (7) working days for CO's response for each RFI. RFIs received by CO after 1:00 p.m. will be considered as received the following working day.
a. The following RFIs will be returned without action:
1) Requests for approval of submittals.
2) Requests for approval of substitutions.
3) Requests for coordination information already indicated in the Con-tract
4) Documents.
5) Requests for adjustments in the Contract Time or the Contract Sum.
6) Requests for interpretation of CO's actions on submittals.
7) Incomplete RFIs or inaccurately prepared RFIs.
b. CO's action may include a request for additional information, in which case CO's time for response will date from time of receipt of additional in-formation.
c. CO's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Pro-posal according to Contracting Section "Contract Modification Proce-dures."
1) If Contractor believes the RFI response warrants change in the Con-tract Time or the Contract Sum, notify CO in writing within 10 days of receipt of the RFI response.
5. On receipt of CO's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify CO within seven days if Contractor disagrees with response.
6. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly. Include the following:
a. Project name.
b. Name and address of Contractor.
c. Name and address of Contracting Officer.
d. RFI number including RFIs that were dropped and not submitted.
Attachment J.1. AG-82X9-S-15-0006 Page 32 of 316
LAKE GEORGE WORK CENTER OFFICE EXPANSION 013300-7
e. RFI description.
f. Date the RFI was submitted.
g. Date CO's response was received.
h. Identification of related Minor Change in the Work, Construction Change
Directive, and Proposal Request, as appropriate.
i. Identification of related Field Order, Work Change Directive, and Pro-posal Request, as appropriate.
F. Contractor Quality Control Submittals: Provide Quality Control submittals, including design data, certifications, manufacturer's instructions, manufacturer's field reports, and other quality-control submittals as required under other Sections of the Specifica-tions.
1. Certifications: Where other Sections of the Specifications require certification that a product, material or installation complies with specified requirements, submit a notarized certification from the manufacturer certifying compliance with specified requirements.
a. Signature: Signed by an officer of the manufacturer or other individual authorized to sign documents on behalf of the company.
2. Inspection and Test Reports: Requirements for submittal of inspection and test reports from independent testing agencies are specified in Division 1 Section “Quality Requirements."
G. Contractor Quality Control Plan: Comply with…