Attach_J.2_Specs_64_pages.pdf

PDF 2 MB Posted

Attached to
North Fork Lake Creek Bridge Replacement Federal contract opportunity
Solicitation number
AG-82BH-S-13-0029
Issued by
Department of Agriculture Forest Service R2-Rocky Mountain Region

About this file

Attach J.2 Specs

View the file

Other files for this federal contract opportunity

Other files attached to North Fork Lake Creek Bridge Replacement, newest first.
File Type Posted
Attach_Soils_Report__N_Fork_Lake_Creek_Bridge.pdf PDF
AG-82BH-S-13-0029_1442_pgs_1-3_rev_1.pdf PDF
Attach_Bid_Schedule_Fill_In.docx DOCX document
AG-82BH-S-13-0029_Rev_1_pgs_4-25.docx DOCX document
SF_30_Cont_pgs_2-5_Summary_of_Changes.docx DOCX document
AG-82BH-S-13-0029_Amend_000001_SF30_pg_1.pdf PDF
AG-82BH-S-12-0029_1442_pgs_1-3.pdf PDF
Attach_J.5_DOL_Wages.docx DOCX document
Attach_J.6_Fire_Control_Plan.docx DOCX document
Attach_J.1_Supplemental_C_2_pages.pdf PDF
AG-82BH-S-12-0029_Sol_Cont_pgs_4-25.docx DOCX document
Attach_J.4_Drawings_2-18.pdf PDF
Attach_J.3_Drawings_Title_Page_1.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

155 – Schedules for Construction Contracts

Replace Section 155 with the following.

155.01 This work consists of scheduling and monitoring all construction activities. See FAR Clause 52.236-15 Schedules for Construction Contracts.

155.02 Submit 3 copies of a construction schedule at least 14 days before work commences.

155.03 The below schedule represents an approximate timeline for the project, but is subject to revision upon mutual agreement between the Contractor and the Contracting Officer. Such changes may be reflected in the Contractor’s construction schedule, to be submitted as per Specification 155.

In order to avoid disruption of public access, the existing bridge shall not be removed, nor public access across the bridge denied, until approximately December 1, 2013.

Item/Task Completion Date

Issue Notice to Proceed. Conduct pre-work meeting. Sept. 9, 2013 Contractor submits construction schedule.

Submittal & review of all pertinent submittals, as outlined in the Oct. 18, 2013 List of Required Sumbittals section of Attachment J.2_SCR

Fabrication of Superstructure Feb. 28, 2014

Begin On-Site Demolition March 10, 2014

Final Inspection; Bridge Open to Public May 24, 2014