155 – Schedules for Construction Contracts

Replace Section 155 with the following.

155.01 This work consists of scheduling and monitoring all construction activities. See FAR Clause 52.236-15 Schedules for Construction Contracts.

155.02 Submit 3 copies of a construction schedule at least 14 days before work commences.

155.03 The below schedule represents an approximate timeline for the project, but is subject to revision upon mutual agreement between the Contractor and the Contracting Officer. Such changes may be reflected in the Contractor’s construction schedule, to be submitted as per Specification 155.

In order to avoid disruption of public access, the existing bridge shall not be removed, nor public access across the bridge denied, until approximately December 1, 2013.

Item/Task Completion Date

Issue Notice to Proceed. Conduct pre-work meeting. Sept. 9, 2013 Contractor submits construction schedule.

Submittal & review of all pertinent submittals, as outlined in the Oct. 18, 2013 List of Required Sumbittals section of Attachment J.2_SCR

Fabrication of Superstructure Feb. 28, 2014

Begin On-Site Demolition March 10, 2014

Final Inspection; Bridge Open to Public May 24, 2014