A13_Q&A_4.28.2017.docx
DOCX document 17 KB Posted
- Attached to
- Multiple Construction Projects - Pine Knot Job Corps Center Federal contract opportunity
- Solicitation number
- AG-82A7-S-17-0051
About this file
Questions and Answers Document
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF-30_Amend_000002_-_AG-82A7-S-17-0051.pdf | ||
| A13_Q&A_5.22.2017.pdf | ||
| SF-30_Amendment_000001_-_AG-82A7-S-17-0051.pdf | ||
| Attachment_10_-_BuildingDescs_PineKnot-FireAlarm.pdf | ||
| Attachment_4_-_Drawing_-_Misc._Building_Exterior_Repairs.pdf | ||
| Attachment_7_-_DB_-_Pine_Knot_-_Residential.pdf | ||
| Attachment_9_-_Proposal_Submission_Package.pdf | ||
| Attachment_3_-_Project_Specifications_-_Misc._Building_Exterior_Repairs.pdf | ||
| Attachment_2_-_Drawings_-_Culinary_Arts_Buildout.pdf | ||
| Attachment_5_-_Project_Specifications_and_Drawing_-_Fire_Detection_System.pdf | ||
| Attachment_1_-_Project_Specifications_-_Culinary_Arts_Buildout.pdf | ||
| Attachment_8_-_DB_-_Pine_Knot_-_Building.pdf | ||
| Attachment_6_-_Walkin_Refrigerator_and_Freezer_Specifications.pdf | ||
| Solicitation_-_AG-82A7-S-17-0051.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AG-82A7-S-17-0052
RFQ Q&A Doc for Blackwell Lighting Upgrades
QUESTIONS & ANSWERS REGARDING:
SOLICITATION/REQUEST FOR PROPOSALS NO. AG-82A7-S-17-0051
Amendment 000001
For Miscellaneous CRA/Construction Projects
Pine Knot Job Corps Civilian Conservation Center
QUESTIONS RECEIVED AS OF 4/28/2017:
1. I need some more information in order to design the fire alarm systems for some of these buildings. Do you know how many air handling units and what cfm they may be? I need to know this so I can get an accurate count of how many duct smoke detectors to provide.
ANSWER: See Attachment 10
2. Do you want us to provide monitoring for the fire alarm systems?
ANSWER: No monitoring required.
3. Can we just provide pricing for the fire alarm system for the culinary arts building?
ANSWER: No – contractor is required to provide pricing for all items included in solicitation (refer to Page 66 – A. General and Section M.
4. Can you provide a list of electrical contractors that are going to be providing a bid to you on this project?
ANSWER: No as they are not available yet, contractors are encourage to enter their information as an interested party for particular products and services you can provide.