160629-Addendum001-GT_Septic_System.pdf
PDF 2 MB Posted
- Attached to
- Waste Water System Replacement Federal contract opportunity
- Solicitation number
- AG-63PX-S-16-0011
About this file
Drawing showing an alternate route and hook up location.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| NEW_SECTION_B.docx | DOCX document | |
| Addendum002-Final.docx | DOCX document | |
| Grey_Towers_Waste_Water.SigninSheet.pdf | ||
| RFQ_Waste_Water_System.docx | DOCX document | |
| GTSeptic_Specifications-_Final.docx | DOCX document | |
| GT_septic_systemALL.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE MANSION AREA DETAIL - SHEET C-2
INSTALL MANHOLE #2
SEE SAND MOUND AREA DETAIL
SHEET C-3
ABANDON SEPTIC TANK
ABANDON CLEANOUT
CUT 8" BELOW GRADE
AND COVER.
ABANDON SEWER LINE
ABANDON SEPTIC TANKS
ABANDON SEWER LINE
INSTALL SEWER LINE "E" 4" X 315'
FROM MANHOLE #2 TO SEPTIC TANK
BY TRENCHLESS CONSTRUCTION
OR CONVENTIONAL TRENCHING
USE TRENCHLESS CONSTRUCTION WITHIN 20 FEET
OF WALKWAY. AVOID ANY DISTURBANCE
OF WALKWAY. PROVIDE A TEMPORARY RAMP
FOR HEAVY EQUIPMENT TO CROSS WALKWAY.
INSTALL CLEANOUTS
AT APPROX. 100' SPACING
SEE DETAIL
INSTALL CLEANOUT
AT CHANGE IN GRADE
NEW HDD TRENCHLESS LINE
EXISTING SEWER DROP & LINE
IN BASEMENT
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
No.
Revision/Issue Date
NOTES
SEPTIC SYSTEM SITE PLAN
GREY TOWERS
NATIONAL HISTORIC SITE
GREG PORTER PE
R9 TST ENGINEERING
Grey Towers National Historic Site
SPF
C-1
1" = 60'
G. PORTER
4/2016
CONTOUR LINES ARE APPROXIMATE
AND MAY NOT REPRESENT THE
EXISTING GROUND ACCURATELY.
THERE ARE MANY BURIED UTILITIES
WITHIN THE PROJECT AREA. THIS
DRAWING INDICATES OWNER'S
KNOWLEDGE OF BURIED UTILITIES.
MANY UTILITIES ARE OWNED BY GREY
TOWERS AND ARE NOT UNDER THE PA
ONE CALL SYSTEM. CONTRACTOR
SHALL USE ALL APPROPRIATE
METHODS TO LOCATE AND AVOID ALL
BURIED UTILITIES.
FINAL MANHOLE LOCATIONS WILL BE
STAKED BY THE COR.
ALL GROUND DISTURBING ACTIVITIES
SHALL BE CAREFULLY CONTROLLED
AND KEPT TO A MINIMUM.
CONTRACTOR SHALL ACCESS THE
SITE USING THE HARDENED ACCESS
WAY, AND LIMIT EQUIPMENT AND
OPERATIONS TO THE AREA ALONG
THE PIPELINES AND AREAS BEING
CONSTRUCTED. DRILLING SLURRIES
SHALL BE CONTAINED WITHIN LINED
PITS OR TANKS, DRILL CUTTINGS
SHALL BE STOCKPILED ON TARPS AND
PROMPTLY REMOVED FROM THE SITE.
COORDINATE WITH THE COR TO KEEP
DISRUPTION OR NECESSARY
CLOSURE OF THE WASTEWATER
PRODUCING AND TREATMENT
FACILITIES TO A MINIMUM.
File details come from the government source that posted it. Updated .