ATTACHMENT #1 SPECIFICATIONS
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Additional_Pre_Bid_Q&A's_and_Clarifications.pdf | ||
| Amendment_0003_.pdf | ||
| Pre-bid_Meeting_Attendees_List.pdf | ||
| Amendment_0002_.pdf | ||
| Addendum_Number_2-May_4_2017.docx | DOCX document | |
| Addendum_Number_1-May_2017.docx | DOCX document | |
| Amendment_0001.pdf | ||
| J2_-_Drawings_Toumey_Steam_Room_Final.pdf | ||
| J3_-_Maps_JWToumeyNursery-SteamRmProj-VicinityAndProximityLocationMaps.pdf | ||
| J5_-_Technical_Evaluation_Form_-_Experience_Questionnaire_.docx | DOCX document | |
| J4_-_DB_Wage_Determination_MI120.txt | TXT text file | |
| AG-569R-S-17-0028_JW_TOUMEY_NURSERY_STEAM_ROOM_SOLICITATION.rtf | RTF text file |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
15037 / Toumey Nursery 22 00 11 - 1 GENERAL PROVISIONS
SECTION 22 00 11
GENERAL PROVISIONS
PART 1 GENERAL
1.01 CONDITIONS OF THE CONTRACT
A. The Conditions of the Construction Contract and applicable provisions of Division l - General Requirements, as well as these General Provisions, shall apply to all Sections of Division 22.
1.02 SCOPE
A. The work to be done under this Division of the Specifications shall include the furnishing of all labor, materials, equipment and services necessary for the proper completion of all of the mechanical work as shown on the drawings and herein specified.
B. In general, this shall include the furnishing and installing of all fire protection, plumbing, heating, refrigeration, ventilation, and temperature control systems, complete with auxiliaries, as may be required to make a complete and properly operating installation.
C. Only such items as are hereinafter specified or indicated on the drawings to be furnished by others, shall be considered to be furnished by others. All other items are to be considered as a part of this Contract, and shall be so bid.
D. The omission of specific reference to any parts necessary to, or reasonably incidental to, a complete installation shall not be construed as releasing the Contractor from furnishing and installing same.
E. Applicable provisions of the following sections shall apply to all sections for Mechanical Work.
1.03 DEFINITIONS
A. Provide: Under this Contract, Contractor shall furnish and install item or items specified.
Contractor shall perform all labor and furnish all materials and equipment necessary to that specified item or system will be complete and operational in every respect.
B. Furnish: Under this Contract, Contractor shall deliver to the site item(s) specified, as well as additional specialized materials and/or accessories necessary for the use and operation of item or items specified.
C. Install: Under this Contract, Contractor shall set in position, connect (including sub-assemblies furnished), and adjust for use. Contractor shall furnish miscellaneous specialty items such as hangers, valves, unions, piping, sheet metal, etc., as obviously necessary for a complete and operating installation.
1.04 DRAWINGS
A. In general, the drawings of the Mechanical Systems and Equipment are to scale, however, to determine exact locations of walls and partitions, the Contractor shall consult the Architectural and/or Structural Drawings which are dimensioned. Drawings shall not take precedence over field measurements. Plans of piping and ductwork, although shown on scale drawings, are diagrammatic only. They are intended to indicate the size and/or capacity where stipulated, approximate location and/or direction, and approximate general arrangement of one phase of work to another, but not the exact detail or exact arrangement of construction.
B. Where discrepancies are discovered after certain portions or phases of any Contract have been installed, the Contracting Officer reserves the right to have any or all Contractors make minor changes in pipe, duct, fixture or equipment locations or arrangements to avoid conflict with other work at no additional cost to the Owner.
C. Because the drawings are to a relatively small scale to show as large a portion as is practical, the fact that only certain features of the system are indicated does not mean that other similar or different features or details will not be required. Contractor shall furnish all incidental labor, materials, or equipment for the systems under his control, so that each system is a complete and operating one unless otherwise specifically stipulated in the detailed body of the Specifications.
15037 / Toumey Nursery 22 00 11 - 2 GENERAL PROVISIONS
D. The Contractor shall be responsible for determining all field measurements before commencing construction, giving due consideration to building design and other equipment to be installed.
Mechanical equipment not dimensioned on the drawings shall be field located, giving due consideration to the work of other trades. The Contractor shall verify all dimensions before proceeding with the work. Where cutting and patching is required, each Contractor shall be responsible for his own work.
E. Dimensions shall not be scaled from the drawings. If the Contractor discovers any discrepancy between actual measurements and those shown on the drawings which prevents good practice, good arrangement, or which is contrary to the intent of the drawings and specifications, he shall notify the Contracting Officer before proceeding with the work.
1.05 SITE INSPECTION
A. Before submitting a proposal for the work contemplated in these specifications and accompanying drawings, each bidder shall examine the site and familiarize himself with all the existing conditions and limitations, including the extent of demolition, cutting and patching to be done by the Contractor for Mechanical Work. No extras will be allowed because of the Contractor's misunderstanding as to the amount of work involved, or his lack of knowledge of any condition in connection with the work.
1.06 CODES AND STANDARDS
A. The entire project shall comply with any and all OSHA, along with latest version of the following codes: International Building Code (IBC), International Plumbing Code (IPC), International Mechanical Code (IMC), International Fuel/Gas Code (IFGC), National Fire Protection Association (NFPA), National Electrical Code, (NEC) and the ANSI/ASHRAE IES standard 90.1
B. Code requirements shall supersede details shown on the drawings or described in these specifications. Size of all pipe must conform to the requirements of all Codes except where larger sizes are shown on the drawings.
1.07 PRODUCT/ASSEMBLY/SYSTEM SUBSTITUTIONS
A. Where the Bid Documents stipulate a particular Product, substitutions will be considered by the Contracting Officer up to 7 days before receipt of bids.
B. The submission shall provide sufficient information to determine acceptability of such products.
C. When a request to substitute a Product is made, the Contracting Officer may approve the substitution and will issue an Addendum to known bidders.
D. The submission shall provide sufficient information to determine acceptability of such products.
E. Provide Products as specified unless substitutions are submitted in this manner and subsequently accepted.
F. The cost of any changes of other trades as a result of use of the substitution material or equipment must be borne by the Contractor submitting such material or equipment.
G. Email or fax requests for substitution are acceptable, provided they are received in the time period stated.
H. Those vendors wishing written approval shall include a return copy and a self-addressed stamped envelope with their request.
1.08 EQUIPMENT
A. All equipment shall be new and in first-class condition. Equipment shall not be used for purposes other than intended by the manufacturer.
B. Manufacturer's nameplate, name or trademark shall be permanently affixed to all equipment and material furnished under this Specification. Nameplate of Subcontractor or distributor will not be acceptable. Nameplate shall be masked prior to any painting. Remove masking after completion.
15037 / Toumey Nursery 22 00 11 - 3 GENERAL PROVISIONS
C. Equipment specified and furnished shall be of a type and manufacturer that has a local representative and a local replacement and service outlet to give complete coverage on parts and service at all times.
1.09 WARRANTY
A. The Contractor shall be held responsible for any and all defects in equipment and workmanship which appear for one (1) full year after the date of Substantial Completion. All such defects must be repaired or defective equipment promptly replaced by the Contractor at no expense to the Owner.
1.10 INSPECTIONS AND FEES
A. The Contractor shall obtain all permits and licenses required in connection with the work under Division 22. Cost for such shall be paid by the Contractor.
B. When application for utility service is the Owner's responsibility, the Contractor shall be responsible for all phases of the installation other than the application itself and shall coordinate the utility's work with his installation.
1.11 SUBMITTALS
A. Drawing Plan Backgrounds Available
1. Electronic drawing files may be available to the contractor for the purpose of preparing shop drawings or submittals.
B. List of Suppliers & Subcontractors:
1. The Contractor shall submit a list of suppliers, Subcontractors, and manufacturers for equipment installed under Division 22 for approval. Contractor shall make such submittal within 15 days after Notice to Proceed, prior to ordering any equipment. Approval of such list does not relieve the Contractor from submittal of shop drawings, nor shall it constitute final approval should the shop drawings be found not in agreement with the Specifications.
2. If a list of materials is not submitted, it shall be assumed that the Contractor has waived his option of equipment selection in favor of selection by the Contracting Officer.
C. Cost Breakdown:
1. Before submittal of the first Request for Payment, the Contractor shall submit to the Contracting Officer, an itemized cost breakdown, including separation of labor and material, for work under Division 22. The breakdown shall be divided in such detail as requested to aid in approval of Payment Requests based on work completed. Breakdown shall include, but not be limited to:
a. Special Mechanical Conditions (Bonds, Mobilization, etc.)
b. Insulation
c. Plumbing
D. Shop Drawings:
1. See Division 1 for submittals procedures. This section supplements the requirements of Division 1. In case of differences, the greater requirement applies.
2. Shop drawings shall be submitted for all major equipment under each Section of this Specification.
3. Shop drawings must first be checked by the Contractor for capacities and space conformance, and so stamped prior to submittal to the Contracting Officer.
4. Submit either electronic shop drawings in PDF file format or a minimum of eight (8) hard copies of shop drawings.
E. Test and Balance Reports:
1. Tabulated data shall be submitted to the Contracting Officer, certifying that all applicable tests have been made, and that heating and ventilating systems have been balanced as specified.
F. Systems Manuals (O&M's):
1. The Contractor Shall provide an electronic copy in Adobe PDF Portfolio format. The Portfolio shall contain:
15037 / Toumey Nursery 22 00 11 - 4 GENERAL PROVISIONS
a. Shop Drawings of all major mechanical components.
b. Parts lists for the same components.
c. Manufacturer's operating, maintenance and cleaning instructions.
d. List of materials recommended for maintenance.
e. Name and address of authorized service organization and parts depot.
f. A description of how the components of a given HVAC system interact within the large system. For example, circulating pumps, boilers, unit heaters are part of the "heating system".
g. A description of normal operating conditions for the system and its components.
h. A description of common symptoms of a malfunctioning system and likely causes.
i. File volume sizes should be restricted to 30Mb. Multiple volumes may be required.
2. The Systems manual shall have an electronic index and be broken up by individual systems such as "heating", "shop exhaust", "kitchen ventilation and exhaust", "chilled water", "administration ventilation".
3. In addition to the electronic version, the Contractor shall prepare two (2) hard copies of all systems manual. Information shall be submitted neatly folded to approximately 8-1/2" x 11" size and shall be bound in indexed looseleaf binders of adequate size to contain the material. Upon completion of these portfolios, the Contractor shall turn over the same to the Contracting Officer's Representative for approval and delivery to the Owner.
4. Where indicated in the Specifications, the Contractor shall provide the services of a factory trained representative to instruct the Owner's authorized personnel in the operation, control and maintenance of equipment.
G. Record Drawings:
1. The Contractor shall keep a complete set of all mechanical drawings in his job site office for purposes of showing "As-Built" installation of mechanical systems and equipment.
2. This set of drawings shall be used for no other purpose. Where any material, equipment or system components are installed different from that shown on the Drawings, such differences shall be clearly and neatly shown on this set of drawings using ink, or indelible pencil. The change notations shall be kept up-to-date on a daily basis for the duration of the project.
3. A complete set of these drawings shall be scanned at a resolution of 600dpi in color and saved in a Adobe PDF portfolio format with index to each sheet by name and burned to a non-volatile media. The electronic copy of the as-built drawings shall be transmitted to the Contracting Officer. After review and approval by the Contracting Officer's representative, the as-built drawings will be turned over to the Owner.
PART 2 - PRODUCTS - NOT USED.
PART 3 - EXECUTION
3.01 WORKMANSHIP
A. Workmanship shall be first-class in every respect. Standard accepted practice in the various trades shall be considered as minimum. The Contracting Officer reserves the right to reject any workmanship not in accordance with the specifications, either before or after installation of equipment.
3.02 COORDINATION
A. The Contractor shall coordinate locations and arrangements of his equipment with other Contractors and subcontractors working on the project. Before starting work, the Contractor shall examine the Architectural, Structural and Electrical drawings and specifications, as well as shop and vendor drawings, for all divisions, to ascertain locations, levels, arrangements and dimensions of other work and shall confer and cooperate with all other Contractors or subcontractors to avoid all interferences. He shall also provide Contractors for other trades with information regarding locations, arrangements and dimensions of his equipment. He shall also coordinate his own cutting and patching requirements with those of other Contractors, so that it will not be necessary for any Contractor to remove or re-do work improperly scheduled.
15037 / Toumey Nursery 22 00 11 - 5 GENERAL PROVISIONS
B. In cases of interferences between various items of equipment or between equipment and building members, if simplified construction is made possible by the relocation of certain equipment, changes in arrangements may be made only if authorized by the Contracting Officer's Representative.
C. Interferences between the work of different divisions which cannot be resolved by the parties involved shall be submitted to the Contracting Officer's representative who shall decide upon final location and arrangement without respect to which work was installed first.
3.03 JOB INSPECTION
A. Periodic job site observations will be made throughout the construction to review applications for payment, observe methods and materials of construction, and review requirements of the Bid Documents.
B. Contractor shall notify the Contracting Officer, and arrange for observation of installation prior to backfill or concealing of systems. Contractor shall, to the maximum practical extent, schedule work to allow for the observation of systems' installation in groups rather than individually.
C. Upon completion of all work, and submittal and approval of Test Reports, Systems Manuals and Record Drawings, the Contractor shall notify the A/E and shall make arrangements for a Substantial Completion inspection.
D. After the inspection is made, the Contractor will receive a list of items requiring adjustment, correction, replacement or completion.
E. The Contractor shall promptly comply completely with all the listed requirements. Should the Contractor fail to perform promptly, the Contracting Officer reserves the right to have the work completed by others and the cost deducted from the contract price.
3.04 INSTRUCTION
A. Complete operating instructions composed of charts, diagrams, installation instructions, service instructions and wiring diagrams, shall be prepared for each system and its components requiring adjustment or maintenance. Instructions shall be filed with the Systems Manuals and in specific cases, framed and mounted near the equipment for reference.
B. The Contractor shall instruct the Owner's personnel in the operation and maintenance procedures of all systems and components. This instruction shall be completed on-site with the equipment in question and with the aid of the approved Systems Manuals. Coordinate instruction with the Owner.
C. Video document the instruction session, index and save in digital format (avi, mpg, m1v, mp2, mpeg)
D. The Contractor shall provide the Contracting Officer's Representativer with written documentation with the Owner's Representative signature that they have received instruction to his satisfaction in the operation of all systems. This documentation shall be received and acknowledged by the Contracting Officer's Representative before final inspection (and warranted period) shall be be completed.
3.05 REMODELING
A. Relocation of existing equipment and piping systems, which of necessity must provide continuous uninterrupted service, shall be accomplished in the least possible time. Work shall be scheduled so as to minimize down time for the respective systems involved. This will require for existing services being revamped and/or relocated, that all interconnecting portions of these systems shall be installed as complete as practicable prior to actual shutdown for final connections.
B. Locate existing piping and make connection where required and/or where shown on the drawings. Do not cut into existing services without first ascertaining to the satisfaction of the Owner and Contracting Officer's Representative that the pipe involved is the desired service. In any area where work performed under Division 22 is the only work involved, restore the area to its original condition upon completion of the work.
15037 / Toumey Nursery 22 00 11 - 6 GENERAL PROVISIONS
C. All existing services and equipment shall be maintained unless otherwise indicated on the drawings.
D. Work that interrupts any service (this includes cutting into existing lines for new connection), shall be performed at times (usually nights or weekends) to cause least interference to the normal operation of the building. Anticipate scheduling work at periods which will result in additional construction costs, such as nights or weekends, and include cost in the proposal.
E. The Owner shall be fully informed in advance of any shut-off which will occur and which will be affected for a specific period of time. Only after the Owner is fully informed and has agreed to the schedule of cut-offs, can the work then proceed accordingly.
F. Provide temporary bracing, shoring, underpinning and support during demolition, cutting, remodeling and related new construction as necessary for the execution of the Work and the protection of persons and property.
G. Provide protective coverings and enclosures necessary to prevent damage to existing work to remain. Protect temporary openings in exterior walls and roofs so as to prevent damage from water and the elements and prevent excessive heat loss from the existing building.
H. Demolish and remove existing construction to be removed. Where new Work is to be installed in or adjacent to existing construction or existing work is to be replaced, remove or cut the existing construction to the extent necessary to install or join the new Work to the existing construction as necessary to complete the Work of the Project.
I. Clean demolition areas and remove debris, waste and rubbish from the building at the conclusion of each day's work. Transport debris and rubbish in such a manner as to prevent the spread of dust. Remove debris, waste and rubbish promptly from the site. Do not burn debris, waste and rubbish on the site.
J. Owner shall have first rights to salvage existing equipment not indicated to be reused. All existing materials not designated to be reused or to remain the property of the Owner, shall become the property of the Contractor and shall be removed from the site.
K. Existing materials indicated on the drawings to be reused shall be stored on the site and protected until reuse.
L. All cutting and patching of existing construction shall be by the Contractor requiring same.
M. Prior to making any cuts, verify exact locations and sizes with the Contracting Officer's Representative to confirm that no structural members will be cut. Where required, Contractor shall provide reinforcing lintels, angles, supports, etc., as necessary to maintain structural integrity at penetrations of existing partitions, slabs, etc.
N. Patch existing construction to match. All painting shall comply with the specifications laid out in the General Contractor's portion of the specifications. Examine existing surfaces where existing surfaces are to be patched before proceeding with the work. Report all conditions where existing materials, colors, and finishes cannot be matched to the Contracting Officer's Representative, and do not proceed until the Contracting Officer's Representative has issued instructions. Existing construction that has been damaged as a result of the work shall be repaired to an extent and as required to match adjacent undamaged construction. Contractor shall notify Contracting Officer's Representative when patching is complete and receive Contracting Officer's Representative approval of patching and finish
O. Where duct and/or piping is removed from existing partitions which are to remain, it is this Contractor's responsibility to patch voids to match existing construction.
END OF SECTION
15037 / Toumey Nursery 22 07 19 - 1 PIPING INSULATION
SECTION 22 07 19
PIPING INSULATION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Piping insulation.
B. Jackets and accessories.
1.02 REFERENCE STANDARDS
A. ASTM B209 - Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate; 2014.
B. ASTM B209M - Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate [Metric]; 2014.
C. ASTM C195 - Standard Specification for Mineral Fiber Thermal Insulating Cement; 2007 (Reapproved 2013).
D. ASTM C547 - Standard Specification for Mineral Fiber Pipe Insulation; 2015.
E. ASTM C795 - Standard Specification for Thermal Insulation for Use in Contact with Austenitic Stainless Steel; 2008 (Reapproved 2013).
F. ASTM E84 - Standard Test Method for Surface Burning Characteristics of Building Materials;
2015a.
G. ASTM E96/E96M - Standard Test Methods for Water Vapor Transmission of Materials; 2014.
H. UL 723 - Standard for Test for Surface Burning Characteristics of Building Materials;
Underwriters Laboratories Inc.; Current Edition, Including All Revisions.
PART 2 PRODUCTS
2.01 REGULATORY REQUIREMENTS
A. Surface Burning Characteristics: Flame spread index/Smoke developed index of 25/50, maximum, when tested in accordance with ASTM E84 or UL 723.
2.02 GLASS FIBER
A. Manufacturers:
1. Knauf Insulation: www.knaufusa.com.
2. Johns Manville Corporation: www.jm.com.
3. Owens Corning Corp: www.owenscorning.com.
4. CertainTeed Corporation: www.certainteed.com.
B. Insulation: ASTM C547 and ASTM C795; semi-rigid, noncombustible, end grain adhered to jacket.
1. 'K' value: ASTM C177,.27 at 75 degrees F. (R 3.7/inch)
2. Maximum Service Temperature: 650 degrees F.
3. Maximum Moisture Absorption: 0.2 percent by volume.
C. Vapor Barrier Jacket: White Kraft paper with glass fiber yarn, bonded to aluminized film;
moisture vapor transmission when tested in accordance with ASTM E96/E96M of 0.02 perm-inches.
D. Tie Wire: 0.048 inch stainless steel with twisted ends on maximum 12 inch centers.
E. Vapor Barrier Lap Adhesive: Compatible with insulation.
1. Compatible with insulation.
F. Insulating Cement/Mastic: ASTM C195; hydraulic setting on mineral wool.
1. ASTM C195; hydraulic setting on mineral wool.
G. Indoor Vapor Barrier Finish:
1. Cloth: Untreated; 9 oz/sq yd weight.
2. Vinyl emulsion type acrylic, compatible with insulation, white color.
15037 / Toumey Nursery 22 07 19 - 2 PIPING INSULATION
2.03 JACKETS
A. PVC Plastic.
1. Manufacturers:
a. Johns Manville Corporation: www.jm.com.
2. Jacket: One piece molded type fitting covers and sheet material, off-white color.
a. Minimum Service Temperature: 0 degrees F.
b. Maximum Service Temperature: 150 degrees F.
c. Moisture Vapor Permeability: 0.002 perm inch, maximum, when tested in accordance with ASTM E96/E96M.
d. Thickness: 10 mil.
e. Connections: Brush on welding adhesive.
3. Covering Adhesive Mastic: Compatible with insulation.
a. Compatible with insulation.
B. Aluminum Jacket: ASTM B209 (ASTM B209M) formed aluminum sheet.
1. Thickness: 0.016 inch sheet.
2. Finish: Smooth.
3. Joining: Longitudinal slip joints and 2 inch laps.
4. Fittings: 0.016 inch thick die shaped fitting covers with factory attached protective liner.
5. Metal Jacket Bands: 3/8 inch wide; 0.010 inch thick stainless steel.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that piping has been tested before applying insulation materials.
B. Verify that surfaces are clean and dry, with foreign material removed.
3.02 INSTALLATION
A. Install in accordance with manufacturer's instructions.
B. Install in accordance with NAIMA National Insulation Standards.
C. Exposed Piping: Locate insulation and cover seams in least visible locations.
D. Insulated pipes conveying fluids below ambient temperature: Insulate entire system including fittings, valves, unions, flanges, strainers, flexible connections, pump bodies, and expansion joints.
E. Glass fiber insulated pipes conveying fluids below ambient temperature:
1. Provide vapor barrier jackets, factory-applied or field-applied. Secure with self-sealing longitudinal laps and butt strips with pressure sensitive adhesive. Secure with outward clinch expanding staples and vapor barrier mastic.
2. Insulate fittings, joints, and valves with molded insulation of like material and thickness as adjacent pipe. Finish with glass cloth and vapor barrier adhesive or PVC fitting covers.
F. Glass fiber insulated pipes conveying fluids above ambient temperature:
1. Provide standard jackets, with or without vapor barrier, factory-applied or field-applied.
Secure with self-sealing longitudinal laps and butt strips with pressure sensitive adhesive.
Secure with outward clinch expanding staples.
2. Insulate fittings, joints, and valves with insulation of like material and thickness as adjoining pipe. Finish with glass cloth and adhesive or PVC fitting covers.
G. Continue insulation through walls, sleeves, pipe hangers, and other pipe penetrations. Finish at supports, protrusions, and interruptions. At fire separations, refer to Section 07 84 00.
H. Pipe Exposed in Public Spaces (less than 7 feet above finished floor). Use alternate heavy density insulating material suitable for the planned temperature range. Insualation to avoid crushing.
I. Exterior Applications: Provide vapor barrier jacket. Insulate fittings, joints, and valves with insulation of like material and thickness as adjoining pipe, and finish with glass mesh reinforced
15037 / Toumey Nursery 22 07 19 - 3 PIPING INSULATION vapor barrier cement. Cover with aluminum jacket with seams located on bottom side of horizontal piping.
J. Heat Traced Piping: Insulate fittings, joints, and valves with insulation of like material, thickness, and finish as adjoining pipe. Size large enough to enclose pipe and heat tracer.
Cover with aluminum jacket with seams located on bottom side of horizontal piping.
3.03 SCHEDULES
A. Plumbing Systems:
1. Domestic Cold Water:
a. Glass Fiber Insulation:
1) Runouts up to 1 inch pipe.
(a) Thickness: 2 inch.
15037 / Toumey Nursery 22 10 05 - 1 PLUMBING PIPING
SECTION 22 10 05
PLUMBING PIPING
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Pipe, pipe fittings, valves, and connections for piping systems.
1. Domestic water.
2. Gas.
3. Flanges, unions, and couplings.
4. Pipe hangers and supports.
1.02 REFERENCE STANDARDS
A. ASME B16.3 - Malleable Iron Threaded Fittings: Classes 150 and 300; The American Society of Mechanical Engineers; 2011.
B. ASME B16.18 - Cast Copper Alloy Solder Joint Pressure Fittings; The American Society of Mechanical Engineers; 2012 (ANSI B16.18).
C. ASME B16.22 - Wrought Copper and Copper Alloy Solder-Joint Pressure Fittings; The American Society of Mechanical Engineers; 2013.
D. ASME B16.26 - Cast Copper Alloy Fittings for Flared Copper Tubes; The American Society of Mechanical Engineers; 2013.
E. ASME B31.1 - Power Piping; The American Society of Mechanical Engineers; 2014
(ANSI/ASME B31.1).
F. ASME B31.9 - Building Services Piping; The American Society of Mechanical Engineers; 2014
(ANSI/ASME B31.9).
G. ASME BPVC-IX - Boiler and Pressure Vessel Code, Section IX - Welding, Brazing, and Fusing Qualifications; The American Society of Mechanical Engineers; 2013.
H. ASTM A53/A53M - Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless; 2012.
I. ASTM A234/A234M - Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and High Temperature Service; 2015.
J. ASTM B32 - Standard Specification for Solder Metal; 2008 (Reapproved 2014).
K. ASTM B88 - Standard Specification for Seamless Copper Water Tube; 2014.
L. ASTM B88M - Standard Specification for Seamless Copper Water Tube (Metric); 2013.
M. MSS SP-58 - Pipe Hangers and Supports - Materials, Design, Manufacture, Selection, Application, and Installation; Manufacturers Standardization Society of the Valve and Fittings Industry, Inc.; 2009.
N. MSS SP-80 - Bronze Gate, Globe, Angle and Check Valves; Manufacturers Standardization Society of the Valve and Fittings Industry, Inc.; 2013.
O. MSS SP-110 - Ball Valves Threaded, Socket-Welding, Solder Joint, Grooved and Flared Ends;
Manufacturers Standardization Society of the Valve and Fittings Industry, Inc.; 2010.
P. NFPA 58 - Liquefied Petroleum Gas Code; National Fire Protection Association; 2014.
Q. NSF 61 - Drinking Water System Components - Health Effects; 2014 (Errata 2015).
R. NSF 372 - Drinking Water System Components - Lead Content; 2011.
1.03 QUALITY ASSURANCE
A. Perform work in accordance with applicable codes.
B. Valves: Manufacturer's name and pressure rating marked on valve body.
C. Welding Materials and Procedures: Conform to ASME BPVC-IX and applicable state labor regulations.
15037 / Toumey Nursery 22 10 05 - 2 PLUMBING PIPING
D. Welder Qualifications: Certified in accordance with ASME BPVC-IX.
1.04 DELIVERY, STORAGE, AND HANDLING
A. Provide temporary protective coating on cast iron and steel valves.
B. Provide temporary end caps and closures on piping and fittings. Maintain in place until installation.
1.05 FIELD CONDITIONS
A. Do not install underground piping when bedding is wet or frozen.
PART 2 PRODUCTS
2.01 GENERAL REQUIREMENTS
A. Potable Water Supply Systems: Provide piping, pipe fittings, and solder and flux (if used), that comply with NSF 61 and NSF 372 for maximum lead content; label pipe and fittings.
2.02 DOMESTIC WATER PIPING, ABOVE GRADE
A. Copper Tube: ASTM B88 (ASTM B88M), Type K (A), Drawn (H).
1. Fittings: ASME B16.18, cast copper alloy or ASME B16.22, wrought copper and bronze.
2. Joints: ASTM B32, alloy Sn95 solder up to 1 1/2.
3. Joints: Grooved mechanical couplings.
4. Mechanical Press Sealed Fittings: Double pressed type, NSF 61 and NSF 372 approved or certified, utilizing EPDM, non toxic synthetic rubber sealing elements.
a. Manufacturers:
1) Anvil Products, a Tyco Business: www.grinnell.com.
2) Viega LLC: www.viega.com.
2.03 GAS PIPING, ABOVE GRADE
A. Steel Pipe: ASTM A53/A53M Schedule 40 black.
1. Fittings: ASME B16.3, malleable iron, or ASTM A234/A234M, wrought steel welding type.
2. Joints: NFPA 58, threaded or welded to ASME B31.1.
B. Copper Tube: ASTM B88 (ASTM B88M), Type K (A) annealed.
1. Fittings: ASME B16.26, cast bronze.
2. Joints: Flared.
2.04 FLANGES, UNIONS, AND COUPLINGS
A. Flanges for Pipe Size Over 1 Inch:
1. Ferrous pipe: Class 150 malleable iron threaded or forged steel slip-on flanges;
preformed neoprene gaskets.
2. Copper tube and pipe: Class 150 slip-on bronze flanges; preformed neoprene gaskets.
2.05 PIPE HANGERS AND SUPPORTS
A. Provide hangers and supports that comply with MSS SP-58.
1. If type of hanger or support for a particular situation is not indicated, select appropriate type using MSS SP-58 recommendations.
2. Overhead Supports: Individual steel rod hangers attached to structure or to trapeze hangers.
a. Cold and Hot Pipe Sizes 6 Inches and Over: Double hangers.
3. Trapeze Hangers: Welded steel channel frames attached to structure.
B. Horizontal Piping Support:
1. Horizontal piping shall be supported at sufficiently close intervals to keep in in alignment and prevent sagging.
2. Cast-iron soil pipe, five foot intervals except where ten foot lengths are used, ten foot intervals between supports are acceptable.
3. Threaded pipe, 12-foot intervals
4. Copper tubing 1-1/4 inch or less, 6-foot intervals.
5. Copper tube 1-1/2 inch or over, ten foot intervals.
15037 / Toumey Nursery 22 10 05 - 3 PLUMBING PIPING
2.06 VALVES
A. Valve Manufacturers:
1. Conbraco Industries; www.conbraco.com
2. Milwaukee Valve Company; www.milwaukeevalve.com
3. Nibco, Inc.; www.nibco.com
4. Tyco Flow Control; www.tycoflowcontrol.com
B. Ball Valves
1. Construction, 4 Inches and Smaller: MSS SP-110, Class 150, 300 psi CWP, bronze body, 304 stainless steel ball, regular port, teflon seats and stuffing box ring, blow-out proof stem, lever handle, solder or threaded ends.
C. Swing Check Valves
1. Up to 2 Inches:
a. MSS SP-80, Class 125, bronze body and cap, bronze swing disc with rubber seat, solder ends.
D. Gas Pressure Reducing Valves
1. Manufacturers:
a. Maxitrol. Similar to Model 325 (for 2 pound to 7 or 10 inch applications)
b. Rockwell International.
c. Full lock-up with vent limiters to vented to the outside. Sized for the appliance(s) served.
d. High leverage valve linkage assembly to deliver positive dead-end lock-up.
E. Strainers
1. Manufacturers:
a. Armstrong International, Inc: www.armstronginternational.com.
b. Green Country Filter Manufacturing: www.greencountryfilter.com.
c. Mueller
d. WEAMCO: www.weamco.com.
2. Size 2 inch and Under:
a. Threaded brass body for 175 psi CWP, Y pattern with 1/32 inch stainless steel perforated screen, self cleaning.
b. Class 150, threaded bronze body 300 psi CWP, Y pattern with 1/32 inch stainless steel perforated screen.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that excavations are to required grade, dry, and not over-excavated.
3.02 PREPARATION
A. Ream pipe and tube ends. Remove burrs. Bevel plain end ferrous pipe.
B. Remove scale and dirt, on inside and outside, before assembly.
C. Prepare piping connections to equipment with flanges or unions.
3.03 INSTALLATION
A. Install in accordance with manufacturer's instructions.
B. Provide non-conducting dielectric connections wherever jointing dissimilar metals.
C. Route piping in orderly manner and maintain gradient. Route parallel and perpendicular to walls.
D. Install piping to maintain headroom, conserve space, and not interfere with use of space.
E. Group piping whenever practical at common elevations.
F. Provide a minimum of two 90 degree changes in direction at each branch connection.
15037 / Toumey Nursery 22 10 05 - 4 PLUMBING PIPING
G. Install piping to allow for expansion and contraction without stressing pipe, joints, or connected equipment.
1. Where required by piping installation, provide an expansion loop to relieve piping stress.
All expansion loops required by this project shall be included in contractors cost. Contact Engineer for assistance in sizing expansion loops.
2. Braze fittings of expansion loop in copper systems.
H. Provide clearance in hangers and from structure and other equipment for installation of insulation and access to valves and fittings.
I. Provide access where valves and fittings are not exposed.
J. Electrical equipment:
1. Do not route piping above electrical panels.
2. In general, avoid routing piping through electrical or communications closets.
K. Where pipe support members are welded to structural building framing, scrape, brush clean, and apply one coat of zinc rich primer to welding.
L. Install valves with stems upright or horizontal, not inverted.
M. Provide valve handle extensions where pipe insulation interferes with valve handle
N. Gas Piping Installation:
1. Weld gas piping in ceiling spaces used as an air plenum.
2. Gas vent piping shall increase in size as distance from regulator increase, per manufacturers recommendations.
3. Pipe vents from gas pressure reducing valves to outdoors and terminate in weather proof hood.
O. Install water piping to ASME B31.9.
P. Pipe Hangers and Supports:
1. Install in accordance with ASME B31.9.
2. Install hangers to provide minimum 1/2 inch space between finished covering and adjacent work.
3. Place hangers within 12 inches of each horizontal elbow.
4. Use hangers with 1-1/2 inch minimum vertical adjustment. Design hangers for pipe movement without disengagement of supported pipe.
5. Install in accordance with the State Plumbing Code.
6. Support gas piping in accordance with International Fuel Gas Code.
7. Where several pipes can be installed in parallel and at same elevation, provide multiple or trapeze hangers.
8. Provide copper plated hangers and supports for copper piping.
9. Prime coat exposed steel hangers and supports. Hangers and supports located in crawl spaces, pipe shafts, and suspended ceiling spaces are not considered exposed.
10. Provide hangers adjacent to motor driven equipment with vibration isolation; refer to Section 22 05 48.
11. Support cast iron drainage piping at every joint.
Q. Valves:
1. Install valves with stem vertical. When this is not possible, they may be installed rotated but never less than horizontal.
2. Install isolation valves staggered where they come out from a pipe shaft so they are completely and conveniently accessible.
3. Install valves with adequate room to permit removal of the bonnet, disk, and trim without removing the valve from the line.
4. Provide valve tags where destination is not visible.
3.04 APPLICATION
A. Install unions downstream of valves and at equipment or apparatus connections.
15037 / Toumey Nursery 22 10 05 - 5 PLUMBING PIPING
B. Provide ball type isolation valves at each branch run-out from main.
C. Provide plug valves in propane gas systems for shut-off service immediately inside building.
D. Exterior Applications:
1. For exterior, above grade gas piping, use galvanized steel pipe and fittings in lieu of black iron. If not galvanized, provide two coats of rustoleum type paint in battleship grey to make weather resistant. all supports and fasteners to be either galvanized or stainless steel to prevent corrosion.
3.05 TOLERANCES
A. Water Piping: Slope at minimum of 1/32 inch per foot and arrange to drain at low points.
3.06 TESTING OF PLUMBING SYSTEM
A. Test plumbing system in accordance with State Plumbing Code.
B. Test fuel gas system in accordance with State Fuel Gas Code.
15037 / Toumey Nursery 22 30 00 - 1 PLUMBING EQUIPMENT
SECTION 22 30 00
PLUMBING EQUIPMENT
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Water softeners.
1.02 REFERENCE STANDARDS
A. ASME BPVC-VIII-1 - Boiler and Pressure Vessel Code, Section VIII, Division 1 - Rules for Construction of Pressure Vessels; The American Society of Mechanical Engineers; 2013.
1.03 QUALITY ASSURANCE
A. Manufacturer Qualifications: Company specializing in manufacturing the type of products specified in this section, with minimum three years of documented experience.
B. Identification: Provide pumps with manufacturer's name, model number, and rating/capacity identified by permanently attached label.
C. Performance: Ensure pumps operate at specified system fluid temperatures without vapor binding and cavitation, are non-overloading in parallel or individual operation, operate within 25 percent of midpoint of published maximum efficiency curve.
1.04 CERTIFICATIONS
A. Water Tanks over 120 gallon capacity: ASME labeled, to ASME (BPV VIII, 1).
B. Products Requiring Electrical Connection: Listed and classified by Underwriters Laboratories Inc., as suitable for the purpose specified and indicated.
PART 2 PRODUCTS
2.01 WATER SOFTENERS
A. Manufacturers:
1. Culligan International Company: www.culligan.com.
2. Sterling Water Systems, LLC: www.goodwaterco.com.
3. Viqua, a Trojan Technologies Company: www.viqua.com.
4. Aquapure, 3M Purification, Inc: www.aquapure.com.
5. Substitutions: See Section 01 60 00 - Product Requirements.
B. Contractor to test available water supply to determine grains of softening capacity at 3 gpm.
C. Softener Tank:
1. Glassfiber reinforced plastic tank.
2. Size: adequate to support continuous flow of 5 gpm.
D. Brine Tank:
1. Glassfiber reinforced plastic tank.
2. Size: adequate to support continuous flow of 5 gpm.
E. Microprocessor Based Control: Brass control valve cycled to regenerate from one to twelve day period.
F. Target Water Condition: Iron: 0.100, Copper 0.050, Total Hardness 0.300, Silica 150, Total Alkalinity 700, Conductivity 7000. Total Alkalinity must not exceed 10% of Conductivity.
G. Phosphate treatment guidelines: OH-Alkalinity 100-600ppm, Phosphate 30-50ppm, Silica 200, Total dissolved solids 2000-3000ppm
PART 3 EXECUTION
3.01 INSTALLATION
A. Install plumbing equipment in accordance with manufacturer's instructions, as required by code, and complying with conditions of certification, if any.
15037 / Toumey Nursery 22 30 00 - 2 PLUMBING EQUIPMENT
B. Provide 3 inch concrete housekeeping pad for floor mounted equipment.
15037 / Toumey Nursery 23 00 11 - 1 GENERAL PROVISIONS
SECTION 23 00 11
GENERAL PROVISIONS
PART 1 GENERAL
1.01 CONDITIONS OF THE CONTRACT
A. The Conditions of the Construction Contract and applicable provisions of Division l - General Requirements, as well as these General Provisions, shall apply to all Sections of Division 23.
1.02 SCOPE
A. The work to be done under this Division of the Specifications shall include the furnishing of all labor, materials, equipment and services necessary for the proper completion of all of the mechanical work as shown on the drawings and herein specified.
B. In general, this shall include the furnishing and installing of all fire protection, plumbing, heating, refrigeration, ventilation, and temperature control systems, complete with auxiliaries, as may be required to make a complete and properly operating installation.
C. Only such items as are hereinafter specified or indicated on the drawings to be furnished by others, shall be considered to be furnished by others. All other items are to be considered as a part of this Contract, and shall be so bid.
D. The omission of specific reference to any parts necessary to, or reasonably incidental to, a complete installation shall not be construed as releasing the Contractor from furnishing and installing same.
E. Applicable provisions of the following sections shall apply to all sections for Mechanical Work.
1.03 DEFINITIONS
A. Provide: Under this Contract, Contractor shall furnish and install item or items specified.
Contractor shall perform all labor and furnish all materials and equipment necessary to that specified item or system will be complete and operational in every respect.
B. Furnish: Under this Contract, Contractor shall deliver to the site item(s) specified, as well as additional specialized materials and/or accessories necessary for the use and operation of item or items specified.
C. Install: Under this Contract, Contractor shall set in position, connect (including sub-assemblies furnished), and adjust for use. Contractor shall furnish miscellaneous specialty items such as hangers, valves, unions, piping, sheet metal, etc., as obviously necessary for a complete and operating installation.
1.04 DRAWINGS
A. In general, the drawings of the Mechanical Systems and Equipment are to scale, however, to determine exact locations of walls and partitions, the Contractor shall consult the Contracting Officer’s Representative and/or Structural Drawings which are dimensioned. Drawings shall not take precedence over field measurements. Plans of piping and ductwork, although shown on scale drawings, are diagrammatic only. They are intended to indicate the size and/or capacity where stipulated, approximate location and/or direction, and approximate general arrangement of one phase of work to another, but not the exact detail or exact arrangement of construction.
B. Where discrepancies are discovered after certain portions or phases of any Contract have been installed, the Contracting Officer’s Representative reserves the right to have any or all Contractors make minor changes in pipe, duct, fixture or equipment locations or arrangements to avoid conflict with other work at no additional cost to the Owner.
C. Because the drawings are to a relatively small scale to show as large a portion as is practical, the fact that only certain features of the system are indicated does not mean that other similar or different features or details will not be required. Contractor shall furnish all incidental labor, materials, or equipment for the systems under his control, so that each system is a complete and operating one unless otherwise specifically stipulated in the detailed body of the Specifications.
15037 / Toumey Nursery 23 00 11 - 2 GENERAL PROVISIONS
D. The Contractor shall be responsible for determining all field measurements before commencing construction, giving due consideration to building design and other equipment to be installed.
Mechanical equipment not dimensioned on the drawings shall be field located, giving due consideration to the work of other trades. The Contractor shall verify all dimensions before proceeding with the work. Where cutting and patching is required, each Contractor shall be responsible for his own work.
E. Dimensions shall not be scaled from the drawings. If the Contractor discovers any discrepancy between actual measurements and those shown on the drawings which prevents good practice, good arrangement, or which is contrary to the intent of the drawings and specifications, he shall notify the Contracting Officer’s Representative before proceeding with the work.
1.05 SITE INSPECTION
A. Before submitting a proposal for the work contemplated in these specifications and accompanying drawings, each bidder shall examine the site and familiarize himself with all the existing conditions and limitations, including the extent of demolition, cutting and patching to be done by the Contractor for Mechanical Work. No extras will be allowed because of the Contractor's misunderstanding as to the amount of work involved, or his lack of knowledge of any condition in connection with the work.
1.06 CODES AND STANDARDS
A. The entire project shall comply with any and all OSHA, along with latest version of the following codes: International Building Code (IBC), International Plumbing Code (IPC), International Mechanical Code (IMC), International Fuel/Gas Code (IFGC), National Fire Protection Association (NFPA), National Electrical Code, (NEC) and the ANSI/ASHRAE IES standard 90.1
B. Code requirements shall supersede details shown on the drawings or described in these specifications. Size of all pipe must conform to the requirements of all Codes except where larger sizes are shown on the drawings.
1.07 PRODUCT/ASSEMBLY/SYSTEM SUBSTITUTIONS
A. Where the Bid Documents stipulate a particular Product, substitutions will be considered by the Contracting Officer up to 7 days before receipt of bids.
B. The submission shall provide sufficient information to determine acceptability of such products.
C. When a request to substitute a Product is made, the Contracting Officer may approve the substitution and will issue an Addendum to known bidders.
D. The submission shall provide sufficient information to determine acceptability of such products.
E. Provide Products as specified unless substitutions are submitted in this manner and subsequently accepted.
F. The cost of any changes of other trades as a result of use of the substitution material or equipment must be borne by the Contractor submitting such material or equipment.
G. Email or fax requests for substitution are acceptable, provided they are received in the time period stated.
H. Those vendors wishing written approval shall include a return copy and a self-addressed stamped envelope with their request.
1.08 EQUIPMENT
A. All equipment shall be new and in first-class condition. Equipment shall not be used for purposes other than intended by the manufacturer.
B. Manufacturer's nameplate, name or trademark shall be permanently affixed to all equipment and material furnished under this Specification. Nameplate of Subcontractor or distributor will not be acceptable. Nameplate shall be masked prior to any painting. Remove masking after completion.
15037 / Toumey Nursery 23 00 11 - 3 GENERAL PROVISIONS
C. Equipment specified and furnished shall be of a type and manufacturer that has a local representative and a local replacement and service outlet to give complete coverage on parts and service at all times.
1.09 WARRANTY
A. The Contractor shall be held responsible for any and all defects in equipment and workmanship which appear for one (1) full year after the date of Substantial Completion. All such defects must be repaired or defective equipment promptly replaced by the Contractor at no expense to the Owner.
1.10 INSPECTIONS AND FEES
A. The Contractor shall obtain all permits and licenses required in connection with the work under Division 23. Cost for such shall be paid by the Contractor.
B. When application for utility service is the Owner's responsibility, the Contractor shall be responsible for all phases of the installation other than the application itself and shall coordinate the utility's work with his installation.
1.11 SUBMITTALS
A. Drawing Plan Backgrounds Available
1. Electronic drawing files may be available to the contractor for the purpose of preparing shop drawings or submittals.
B. List of Suppliers &…