SECTION 00 91 12
ADDENDUM NUMBER 2
PARTICULARS
| 1.01 | DATE: May 2, 2017 |
| 1.02 | PROJECT: TOUMEY NURSERY |
| 1.03 | OWNER'S PROJECT NUMBER: AG-569R-S-17-0028 |
| 1.04 | OWNER : NATIONAL FOREST SERVICE |
| 1.05 | CONTRACTING OFFICER : NATIONAL FOREST SERVICE |
TO: PROSPECTIVE BIDDERS :
| 2.01 | THIS ADDENDUM FORMS A PART OF THE CONTRACT DOCUMENTS AND MODIFIES THE ORIGINAL PROCUREMENT DOCUMENTS DATED April 5, 2017 , WITH AMENDMENTS AND ADDITIONS NOTED BELOW. |
| 2.02 | ACKNOWLEDGE RECEIPT OF THIS ADDENDUM IN THE SPACE PROVIDED IN THE BID FORM . FAILURE TO DO SO MAY DISQUALIFY THE BIDDER. |
CHANGES TO THE PROJECT MANUAL:
| 3.01 | GENERAL CLAIRIFICATION | |
| A. | Specifications references to permit fees throughout shall be deleted. No permits or inspection fees are required for this project. |
| 3.01 | Section 22 00 11 GENERAL CONDITIONS | |
| A. | Paragraph 1.01 Conditions of the Contract, A: |
1. Delete reference to Division 1.
B. Paragraph 1.06 Codes and Standards
2. Add the following paragraph:
a. Installing Contactor shall be Licensed to perform the work in his or her state. The contractor need not be licensed in the State of Michigan.
C. Paragraph 1.11Submittals, D Shop Drawings, paragraph 1:
3. Delete paragraph entirely.
| 3.02 | Section 22 10 05 PLUMBING PIPING | ||
| A. | Part 3 Execution, 3.03 Installation, P. Pipe Hangers and Supports, 5: | ||
| 1. | Change reference to from “State Plumbing Code.” to “International Pluming Code” |
| 3.02 | Section 22 30 00 PLUMBING EQUIPMENT | ||
| A. | Part 2 Products, 2.01 Water Softeners, B: | ||
| 1. | Add to this paragraph: “It is the Contractor’s responsibility to test the water conditions, and select an appropriate softener that meets or exceeds the flow and hardness criteria listed give the existing water condition.” | ||
| B. | Part 2 Products, 2.01 Water Softeners, A. Manufacturers, Substitutions: | ||
| 1. | Change reference to from “See Section 01 60 00 - Product Requirements.” to “See Section 22 00 11 General Provisions.” | ||
| C. | Part 3 Execution, 3.01 Installation, A: | ||
| 1. | Change sentence to read: “Install plumbing equipment in accordance with manufacturer’s instruction, and in compliance with code.” |
| 3.03 | Section 23 05 33 HEAT TRACING FOR HVAC PIPING | ||
| A. | Part 1 General, 1.03 Submittals, A: | ||
| 1. | Change reference to from “See Section 01 30 00 - Administrative Requirements, for submittal procedures.” to “See Section 23 00 11 General Provisions.” | ||
| B. | Part 2 Products, 2.01 Self Regulating Parallel Resistance Electric Heating Cable, A Manufacturers;, Substitutions: | ||
| 1. | Change reference to from “See Section 01 60 00 - Product Requirements.” to “See Section 23 00 11 General Provisions.” | ||
| C. | Part 3 Execution, 3.02 Installation, D: | ||
| 1. | Change reference to from “Comply with all national and local code requirements.” to “Comply with national electric code requirements..” |
| 3.04 | Section 23 22 14 STEAM AND CONDENSATE SPECIALTIES | ||
| A. | Part 1 General, 1.03 Submittals, A: | ||
| 1. | Change reference to from “See Section 01 30 00 - Administrative Requirements, for submittal procedures.” to “See Section 23 00 11 General Provisions.” |
| 3.05 | Section 23 51 00 BREECHING, CHIMNEYS AND STACKS | ||
| A. | Part 1 General, 1.04 Submittals, A: | ||
| 1. | Change reference to from “See Section 01 30 00 - Administrative Requirements, for submittal procedures.” to “See Section 23 00 11 General Provisions.” |
| 3.06 | Section 23 52 33 WATER-TUBE BOILERS | ||
| A. | Part 1 General, 1.03 Submittals, A: | ||
| 1. | Change reference to from “See Section 01 30 00 - Administrative Requirements, for submittal procedures.” to “See Section 23 00 11 General Provisions.” | ||
| B. | Part 3 Execution, 3.04 Field Quality Control, A: | ||
| 1. | Change reference to from “See Section 01 40 00 - Quality Requirements, for additional requirements.” to “See Section 23 00 11 General Provisions.” |
| 3.07 | Section 26 00 11 BASIC MATERIALS AND METHODS | ||
| A. | Part 1 General, 1.01 Conditions Of The Contract, B: | ||
| 1. | Change reference to from “All installations shall meet all Local, State and National Codes” to “All installations shall meet National Electric Code and ICC Codes.” |
| 3.08 | Section 26 27 26 WIRING DEVICES | ||
| A. | Part 1 General, 1.03 Submittals, A: | ||
| 1. | Change reference to from “See Section 01 30 00 - Administrative Requirements, for submittal procedures.” to “See Section 26 00 11 Basic Materials and Methods.” |
| 3.09 | Section 26 29 13 ENCLOSED CONTROLLERS | ||
| A. | Part 1 General, 1.03 Submittals, A: | ||
| 1. | Change reference to from “See Section 01 30 00 - Administrative Requirements, for submittal procedures.” to “See Section 26 00 11 Basic Materials and Methods.” |
| 3.10 | Section 26 51 00 INTERIOR LIGHTING | ||
| A. | Part 2 General, 1.04 Submittals, A: | ||
| 1. | Change reference to from “See Section 01 30 00 - Administrative Requirements, for submittal procedures” to “See Section 26 00 11 Basic Materials and Methods.” | ||
| A. | Part 2 General, 2.01 Luminaire types B, Substitutions: | ||
| 1. | Change reference to from “See Section 01 60 00 - Product Requirements…” to “See Section 26 00 11 Basic Materials and Methods.” |
CHANGES TO THE DRAWINGS:
| 4.01 | Drawing M2 - OVERALL FLOOR PLAN - MECHANICAL | |
| A. | Clarification: Electric panel identified on drawing as source of power is full, circuit shall be provided in Panel #1 which is approximately 30 feet further away. Include necessary additional conductor, conduit, fittings, installation. | |
| B. | Clarification: SEMCO, the gas utility company shall be responsible for supplying a new meter and regulator, this Contractor shall coordinate and install. | |
| C. | Clarification: Drawing note indicates providing 2# regulator at each appliance. Existing service provides natural gas at inches of water column. The service pressure will be increased to 2 pounds. The contractor must provide a step-down regulator from two pounds to the service pressure required for the appliance. | |
| D. | No asphalt patching is assumed in this project. The services upgrade is likely to involve a new meter and regulator and meter. We do not anticipate a new line to the building. If such work is required, it is outside of the scope of this contract. | |
| E. | With regard to gas piping installation. The contractor’s work shall be in accordance with the international plumbing code and international fuel gas code. Existing work that is not in compliance shall be brought to the attention of the Engineer and Owner/Contracting Officer but any corrective measures are not part of this contract. | |
| 4.02 | Drawings - General | |
| A. | Clarification: No bumper shall be provided for the steam piping in steam room under this contract. | |
| 4.01 | Drawing M2 - OVERALL FLOOR PLAN - MECHANICAL | |
| A. | Clarification: SEMCO, the gas utility company shall be responsible for supplying a new meter and regulator, this Contractor shall coordinate and install. |
END OF ADDENDUM NUMBER 2