Blasting specifications.pdf

PDF 109 KB Posted

Attached to
AZURITE MINE ACCESS - ROAD CONSTRUCTION
Solicitation number
AG-05G1-S-10-0035
Issued by

About this file

Blasting Specifications Amendment 003

View the file

Other files

File Type Posted
amendment-005.pdf PDF
amendment-004.pdf PDF
R6 Br Overload Permit Form —
02_azurite_mine_access-vicmap.pdf PDF
05_culvert construction details.pdf PDF
06_Rd Structure Detail.pdf PDF
acrow-bridge-specifications-revised.pdf PDF
R34786-10.pdf PDF
01_Title Sheet.pdf PDF
R34786-9.pdf PDF
amendment-003.pdf PDF
04_Culvert Listing-Construction Detail.pdf PDF
07_Typical Gate Detail.pdf PDF
03_Typical Road Template.pdf PDF
R34786-8.pdf PDF
amendment-002.pdf PDF
amendment-001.pdf PDF
01_Azurite_Mine_Access_Title_Page.pdf PDF
09_R34786-3 S. Fk. Slate.pdf PDF
05_Typical Road Structure Details.pdf PDF
03_typical road template details.pdf PDF
Attach-001-Specs.pdf PDF
07_R34786-1 S. Fk. Slate.pdf PDF
02_azurite_mine_access-vicmap.pdf PDF
Attachments-2-thru-5.pdf PDF
04_Culvert Listing-Construction Detail.pdf PDF
08_R34786-2 S. Fk. Slate.pdf PDF
RFP-azurite-mine.pdf PDF
06_Typical Gate Detail.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table of Contents

Table of Contents

205 - Rock Blasting

205.03 Regulations

205.06 Preblast condition survey and vibration monitoring and control

205.07 Test Blasting

205.08 Blasting

205 - Rock Blasting

205.02_nat_us_05_13_2004

205.03 Regulations

Add the following:

(e) Forest Service Manual (FSM) 6745 Explosives and Blasting Materials.

205.06_nat_us_05_12_2004

205.06 Preblast condition survey and vibration monitoring and control.

Add the following:

Limit blasting induced vibrations in saturated soils or on steep slopes as designated or as directed by the CO.

Notify the owners of nearby utilities at least 24 hours before blasting.

205.07_nat_us_05_12_2004

205.07 Test Blasting.

Add the following:

Test blast at all new sources, when rock type changes, and when blast layout changes due to slope or other changes.

205.08_nat_us_05_12_2004

205.08 Blasting.

Delete the following:

Place a stake next to each hole with hole number and total depth drilled.

Do not stem the hole with drill cuttings.

Add the following:

(8) Halt blasting operations when any of the following conditions exist:

Precipitation exceeds 1 inch in any 24 hour period.

Precipitation exceeds 3 inches in any 96 hour period.

Precipitation exceeds 4 inches in any 144 hour period.

A landslide occurs within 300 feet of a blast site under any precipitation conditions.