Construction_RFP_ProspectRSWaterReplacementSystem.docx

DOCX document 5 MB Posted

Attached to
Prospect Ranger Station Water and Wastewater System Replacement
Solicitation number
AG-04N7-S-15-0016
Issued by

About this file

Solicitation

View the file

Other files

File Type Posted
Amendment_No.3_SF30.pdf PDF
AmendmentNo.3_Revised_Drawings.pdf PDF
AmendmentNo.3_Summary.docx DOCX document
Amendment_No.2_SF_30.pdf PDF
AmendmentNo.1Reviseddrawing_Sheet_C8.pdf PDF
AmendmentNo.1Revised_Specs.docx DOCX document
Amendment_No.1SF_30.pdf PDF
AmendmentNo.1SummaryofChanges.docx DOCX document
REVISED_DRAWINGS.pdf PDF
Specs.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION RFPSolicitation No. AG-04N7-S-15-0016
Rogue River-Siskiyou National Forest
Prospect RS Water and Waste Water System Replacement
PAGE 68 of 71

OMB APPROVAL NO. 2700-0042

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

AG-04N7-S-15-0016

2. TYPE OF SOLICITATION

|_| SEALED BID (IFB)

|X| NEGOTIATED (RFP)

3. DATE ISSUED

03/27/2015

PAGE OF PAGES

IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST NO. 737285

6. PROJECT NO.

7. ISSUED BYCODE
8. ADDRESS OFFER TO

USDA, Forest Service Medford Interagency Office Rogue River-Siskiyou National Forest 3040 Biddle Road Medford, Oregon 97504

USDA, Forest Service Rogue River-Siskiyou National Forest Attn: Contracting 3040 Biddle Road, Medford, Oregon 97504

9. FOR INFORMATION
CALL:
A. NAME

Eileen Northrop, Contracting Shanisha Reese, Technical Contact

B.TELEPHONE NO. (Include area code) (No Collect calls) 541-618-2017 541-618-2069

541-957-3441

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

Prospect RS Water and WasteWater Replacement System High Cascades Ranger District Rogue River-Siskiyou National Forest Jackson County, Oregon

THIS IS A TOTAL SMALL BUSINESS SET-ASIDE

Price Range: The Government's estimated price range is between $250,000 and $500,000

NOTE: Address/Mail/Deliver proposals to BLOCK 8 address. Bid guarantees must be received no later than the specified closing date.

Offerors shall be registered and active in the System for Award Management (SAM) data base prior to award. Information on registration may be obtained via the internet at: http://www.sam.gov All contractors and vendors must complete the electronic version of the Representations and Certifications in the SAM System.

11. The Contractor shall begin performance within 10 calendar days and complete project ready for use by 150 calendar days after receiving |_| award, |X| notice to proceed. This performance period is |X| mandatory, |_| negotiable. (See Section F.)

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12B.)

|_| YES|_| NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A.Sealed offers in original and 0 copies to perform the work required are due at the place specified in Item 8 by 4:30 p.m. (local time) on April 28, 2015. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offerors’ name and address, the solicitation number, and the date and time offers are due.
B.An offer guaranteeX is,|_| is not required.
C.All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D.Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-32121442-101STANDARD FORM 1442 (REV. 4-85)
Computer GeneratedPrescribed by GSA
FAR (48 CFR) 53.236-1(e)

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.

AMOUNTS PLACE AMOUNTS IN SECTION B.

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.
DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
|_| 10 U.S.C. 2304(c)( )|_| 41 U.S.C. 253(c)( )
26. ADMINISTERED BYCODE
27. PAYMENT WILL BE MADE BY

All invoices must be submitted electronically through the Invoice Processing Platform via www.ipp.gov (IPP)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

|_|28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.
|_|29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31A. NAME OF CONTRACTING OFFICER (Type or print)

EILEEN NORTHROP

30B. SIGNATURE

30C. DATE

31B. UNITED STATES OF AMERICA

BY

31C. AWARD DATE

Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)

CONSTRUCTION RFP

CONSTRUCTION RFPSolicitation No. AG-04N7-S-14-0041
Rogue River-Siskiyou National Forest
J. Herbert Stone Nursery Booster Station & Backflow Preventer

PART I—THE SCHEDULE

PART I—THE SCHEDULE OF ITEMS

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

PROSPECT RANGER STATION WATER AND WASTEWATER

SYSTEM REPLACEMENT

High Cascades Ranger District Rogue River – Siskiyou National Forest Jackson County, Oregon

ITEM NO.
DESCRIPTION
METHOD OF MEASURE
UNIT
ESTIMATED QUANTITY
UNIT PRICE
AMOUNT
1
Mobilization
LSQ
LS
1
2
Project Closeout/O&M Manuals/Record Drawings
LSQ
LS
1
3
Site Demolition
LSQ
LS
1
4
Site Preparation
LSQ
LS
1
5
Rock Excavation
AQ
CY
100
6
Erosion Control
LSQ
LS
1
7
Gravel Surface Restoration
DQ
SY
80
8
3/4-inch Water Line
DQ
LF
850
9
1-inch Water Line
DQ
LF
30
10
1-1/4-inch Water Line
DQ
LF
370
11
1-1/2-inch Water Line - Sch. 80 PVC
DQ
LF
110
12
2-inch Water Line - Sch. 80 PVC
DQ
LF
20
13
2-inch Water Line - Sch. 40 PVC
DQ
LF
1600
14
3-inch Water Line - Sch. 80 PVC
DQ
LF
40
15
3-inch Water Line - Sch. 40 PVC
DQ
LF
2100
16
Pumphouse Interior
LSQ
LS
1
17
Water System Gate Valves
AQ
EA
12
18
Pressure Gauge Assembly
AQ
EA
1
19
Sample Tap
AQ
EA
3
20
Pressure Relief Valve
AQ
EA
1
21
1-1/2-inch Silent Check Valve
AQ
EA
2
22
Residential Water Meter
AQ
EA
17
23
Flow Meter
AQ
EA
3
24
Reduced Pressure Backflow Assembly
AQ
EA
1
25
Blow-Off/ Flushing Hydrant
AQ
EA
5
26
Bollard
AQ
EA
5
27
Pressure Tanks
LSQ
LS
1
28
Concrete Pad
DQ
SF
50
29
Power Connection
LSQ
LS
1
30
Electrical Power and Lights for Building
LSQ
LS
1
31
Pump Control Panel
LSQ
LS
1
32
Motor Starter
LSQ
LS
1
33
Fiberglass RPBA Enclosure
AQ
EA
1
34
Conduit
DQ
LF
400
35
Handhole Pull Boxes
AQ
EA
4

TOTAL BASE ITEMS ___________________

SEWAGE SYSTEM - OPTION ITEM NO. 1

36
Mobilization
LSQ
LS
1
37
Project Closeout/O&M Manuals/Record Drawings
LSQ
LS
1
38
Erosion Control
LSQ
LS
1
39
Rock Excavation
AQ
CY
40
40
6-inch Sanitary Sewer
DQ
LF
120
41
4-inch Sanitary Sewer
DQ
LF
35
42
Sewer Manhole
AQ
EA
2
43
Sanitary Sewer Cleanouts
AQ
EA
6
44
2-inch Force Main
DQ
LF
300
45
Septic Tanks
AQ
EA
3
46
Effluent Treatment System
LSQ
LS
1
47
Septic Tank Demolition
AQ
EA
3
48
Distribution Box
AQ
EA
1
49
4-inch Drainfield Pipe
DQ
LF
320
50
Sanitary Sewer Lift Station
AQ
EA
2

TOTAL OPTION ITEMS ___________________

ASPHALT RESTORATION - OPTION ITEM NO. 2

51
Asphalt Surface Restoration
DQ
SY
1400

TOTAL OPTION ITEM ___________________

TOTAL AMOUNT ALL ITEMS ___________________

PART I - THE SCHEDULE (CONTINUED)

DUNS NUMBER:______________________________

TAX IDENTIFICATION NUMBER (TIN):____________________________

EMAIL:__________________________________________

B-2 - NOTES:

1) Bid Items: Offerors must bid on all items. If offeror does not intend to charge for an Item, a price of ”0” or “NO COST” should be shown

2) Bond Premiums: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts shall not be in addition to the contract price. Include bond payments under 15101 Mobilization.

3) A bid bond (20% of total base bid price) is required for this solicitation. A performance (100%) and payment bond (100%) are required within 10 days after contract award.

4) Within 14 days after award of the contract, the Contractor shall deliver to the Contracting Officer a completed Standard Form (SF) 1413, Statement and Acknowledgment, for each subcontract for construction within the United States, including the subcontractor’s signed and dated acknowledgment that the clauses set forth in paragraph (b) of this clause have been included in the subcontract (see FAR 52.222-11 Subcontracts).

5) Option Items: Offerors must bid on all items (all Base Items and all Options Items). See “Option for Increased Quantity – Separately Priced Line Items” in Section I, and “Evaluation of Options” in Section M.

6) If the Government elects to exercise the Option items, it will be for the total quantity of all payment items within the Option item. Exercise of Option Item may be made by the government within 120 days after contract award.

7) Electronic offers will not be accepted. An offer that is emailed to a government account will be rejected.

8) This is not a public bid opening. All offers submitted are considered confidential. The name of the contractor and the amount of the contract will be disclosed only after an award has been made.

9) Offerors must register in the System for Award Management (SAM) data base (See FAR clause 52.204-7). Information on registration may be obtained via the internet at: http://www.sam.gov All contractors and vendors must complete the electronic version of the Representations and Certifications in the SAM System.

10) Contractor must be enrolled in the Invoice Processing Platform in order to receive payment for services rendered. If you are not currently enrolled, please go to https://www.ipp.gov/ , and then Vendor Enrollment. If you experience any issues at the site, please contact customer support at the following: Customer Support at (866) 973-3131 or IPPCustomerSupport@fms.treas.gov.

11) Proposal Submission Documents: See Section L-4 for a list of required Proposal Submission Documents and other instructions. Unnecessarily elaborate submissions are neither required nor desired. Please do not bind or otherwise cover documents. Please staple documents at upper left hand corner. Please return only the documents specified in section L.

Offers should be mailed or hand delivered to:

Rogue River-Siskiyou National Forest
Attn: Contracting
3040 Biddle Road
Medford, Oregon 97504

Or fax to 541.618.2148. Please see L-6 for specific instructions regarding faxes.

Include the following on the sealed envelope:

RFP Number: AG-04N7-S-15-0016
Name of Project: Prospect RS Water and Waste Water System Replacement

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C-1 Scope of Contract

The project includes all labor, materials, equipment, supplies, supervision and incidentals necessary for the replacement of the existing water system at the Prospect Ranger Station. Work includes, but is not limited to: site work, installation of water lines and related valves and fittings, connections to existing service lines, site preparation for new precast building, installation of new flow meters, pressure tanks, pipes and appurtences, electrical connections to new precast building, and demolition of structures. Optional work includes site work, installation of septic tanks, effluent treatment system, pump system, asphalt work, and electrical connections.

C-2 Project Location

The project is located in Jackson County, Oregon, near the community of Prospect, on the High Cascades Ranger District, and may be reached by traveling from Medford, Oregon, north on State Highway 62 approximately 43 miles to the site. The address is 47201 Highway 62, Prospect, Oregon 97536-9724. (541) 560-3400.

C-3 Price Range

The magnitude of the Government's estimate is: between $250,000 and $500,000.

C-4 AGAR 452.211-72 Statement of Work/Specifications (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

C-5 AGAR 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

C-6 Reference Standards

AASHTO American Association of State Highway and Transportation Officials

ACI American Concrete Institute

ANSI American National Standards Institute

APIAmerican Petroleum Institute
APWAAmerican Public Works Association

ASLA American Society of Landscape Architects

ASTM American Society for Testing and Materials 100 Barr Harbor Drive

AWWA American Water Works Association

BAA Buy American Act

CFR Code of Federal Regulations

EPA Environmental Protection Agency

FAR Federal Acquisition Regulations

FHWA Federal Highway Administration

IEEE Institute of Electrical and Electronics Engineers

JCDS Jackson County Development Services

NACE National Association of Corrosion Engineers

NAPCA National Association of Pipe Coating Applicators

NEC National Electrical Code

NEMA National Electrical Manufacturers Association

NFPA National Fire Protection Association

NIOSH National Institute for Occupational Safety and Health

NIST National Institute of Standards and Technology

NSF National Sanitation Foundation

OAR Oregon Administrative Rules

ODEQ Oregon Dept. of Environmental Quality

ODOT Oregon Department of Transportation

OR-OSHA Oregon Occupational Safety and Health Administration

OSHA Occupational Safety and Health Administration

OSHD Oregon Department of Transportation, Oregon State Highway Division

PP Pacific Power

PCA Portland Cement Association

UL Underwriters Laboratories, Inc.

USDA U.S. Department of Agriculture

USFS U.S. Forest Service

SECTION D--PACKAGING AND MARKING

{For this Solicitation, there are NO clauses in this Section}

SECTION E--INSPECTION AND ACCEPTANCE

E-1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

Clause Number
Title
Date
52.246-12
Inspection of Construction
AUG 1996

E-2 Inspection and Acceptance (AGAR 452.246-70) (FEB 1988)

(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.

(b) Inspection and acceptance will be performed at the project site.

E-3 Inspection and Testing Performed By Government

The Government will perform sampling, testing and inspection of work in progress where these responsibilities are not expressly assigned to the Contractor by the Forest Service specifications or by the Special Project Specifications.

E-4 Conformity with Drawings and Specifications

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions and material requirements shown on the drawings, indicated in the specifications or designated on the ground. “Reasonably close conformity” is in compliance with reasonable and customary manufacturing and construction tolerances.

SECTION F--DELIVERIES OR PERFORMANCE

F-1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

Clause Number
Title
Date
52.242-14
Suspension of Work
APR 1984

F-2 FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) Alternate I (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 150 calendar days for base items, and 60 calendar days for option items after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.

Performance time for the Option Items (if exercised) will run consecutively. Performance time is 60 calendar days regardless if one or both options are exercised.

F-3 Project Coordination/Other Work in the Area

Contractor will be required to coordinate with District staff as needed to obtain access keys, coordinate access as well as parking and storage needs, etc. The project site will need to remain open and accessible to the public as well as district staff for the duration of the project. The contractor will need to coordinate with the district staff to a certain extent as it relates to other logistical needs (see Drawings and Specifications for further information).

Construction activity may be allowed on weekends with prior approval of the CO. Weekends are considered to begin at 5 pm on Fridays and end at 7 am on Mondays. Project activities shall not disrupt normal functions (domestic water service, road access, electrical service, etc.) without a minimum of seventy two (72) hours’ notice and shall be limited to six (6) hours per occurrence.

SECTION G--CONTRACT ADMINISTRATION DATA

G-1 AGAR 452.215-73 Post Award Conference (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled and held after the date of contract award. The conference will be held at a mutually agreed upon location.

G-2 Government-Furnished Property (Materials) (USDA 452.245-70)(FEB 1988)

The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This shall be used and maintained by the Contractor in accordance with provisions of the "Government Property" FAR clause contained elsewhere in the contract.

Property to be FurnishedDelivery PointTime of Delivery
Estimated
Pumphouse BuildingProject SiteAugust 1 – August 15

G-3 Contracting Officer's Representative

A Contracting Officer's Representative (COR) will be designated after the contract award. The Contractor will be notified by letter of the name and duties of the COR.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H-1 FAR 52.236-4 Physical Data (APR 1984)

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by USFS.

(b) Weather conditions suitable for performance of work are normally expected year around with weather delays typically expected in the Medford area.

(c) Wildlife restrictions – No special restrictions are applicable.

H-2 Use of Premises

(a) The project site is accessed by Forest Roads that are to remain open for public use during performance of work under this contract except in the immediate project area which may be closed by contractor during construction activity. Contractor shall conduct work in such a manner as to protect the public.

(b) Contractor shall coordinate with Nursery staff as entrance gate may be locked during evenings and weekends as well as potential periodic shut downs of the site. Nursery operating hours are 7:00 – 4:30.

(c) Unless provided otherwise, the Contractor shall dispose of solid waste in accordance with applicable Federal, State, and local regulations. Use of Forest Service waste disposal facilities is not allowed.

(d) Contractor is allowed to use existing restroom facilities near the project site. The Government reserves the right to discontinue use of this privilege at its discretion if the Contractor leaves the toilets in an untidy condition. The Contractor shall install a portable toilet if the right to use the existing facilities is denied by the Government. This does not release the contractor from having to provide temporary restroom facilities were necessary as outlined in Section 01500 – 3.B.2.

(e) Camping: No camping will be permitted at the site.

(d) Fuel storage is not allowed within the project site unless noted elsewhere.

H-3 Utilities

(a) Sewer: Not available

(b) Water: Available in reasonable quantities

(c) Electrical: Not available

H-4 Hazardous Conditions Safety Plan Certification

The following conditions have been identified as inherently hazardous to a degree that failure to take the proper precautions could lead to serious injury or loss of life. This listing shall not be construed as all inclusive. The Contractor shall certify that his/her Safety Plan conforms to the requirements of OSHA. The Safety Plan certification shall be submitted prior to commencing work on the project. Appropriate actions shall be taken by the Contractor to implement this plan during performance and to take any and all other necessary steps to mitigate the dangers from hazard.

Confined space entry

x
Temporary excavation/deep trenching/slope stability

Tree felling

Fall hazard from work heights exceeding six feet

Blasting

Traffic control on limited visibility roads

x
Heavy equipment operation
x
Suspended loads

Tree climbing and/or tower climbing

x
Fire hazards

Hazardous materials handling

x
Electrical hazard
x
Hydraulic and/or pneumatic and/or high pressure hazards

Steep slopes and/or downed logs

x
Insects

H-5 Product Substitution, Shop Drawings and Material Certification

(a) Product Substitution. Any modification of other items, designs, materials, products or equipment (including Government Furnished Property or Government Furnished Material), made necessary because of a substitution, shall be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.

(b) Shop Drawings and Submittals. The following submittals shall be submitted for approval within 10 calendar days after Notice to Proceed as required by the clause or specification unless noted elsewhere or alternative arrangements are made in advance with the project Contracting Officer:

BasicDetailedNumberGovernment
ReferenceRequirementsof CopiesApproval for
Brief TitleSectionSectionTo SubmitSubmittal__
Construction ScheduleIFAR 52.236-15114 days
Quality Control003011.2314 days
Closeout Submittals017701.2314 days
O&M Manual017851.2314 days
Utility Shut-off022201.23N/A
Backfill Materials023181.2314 days
Sanitary Sewer025301.2314 days
Manholes025311.2314 days
Sewage Treatment Syst.025401.2314 days
Septic Tanks025431.3314 days
Drainfield025471.2314 days
Water Distribution026601.3314 days
PVC Piping026611.2314 days
Cast-In-Place Concrete033001.3314 days
Pumphouse103061.3314 days
Pump Station113111.3314 days

General Electrical

Requirements160101.5314 days
Electrical Materials160501.3314 days

Specialized Electrical

Materials161151.3314 days
Transclosure161151.2314 days
Conduit162001.4314 days
Power Distribution164001.4314 days
Lighting165001.3314 days
Controls169001.7314 days

Certified Payroll Record

WH-347 (submit weekly)IFAR 52.222-81N/A
Safety Plan CertificationH-4 Hazardous Conditions1N/A
SPCC Plan (> 1320 Gal.)H-7 Landscape Preservation1N/A
Fire PlanSection J Fire Protection and1N/A
Suppression

Government has 14 calendar days to review packet of submittals unless noted elsewhere such as in the specifications. Ommission from this list doesn’t releave the Contractor from submitting documentation as required by the specifications.

H-6 Permits and Responsibilities

Contractor is responsible for obtaining DEQ permits (layout approval, inspections and certificate of satisfactory completion) for Septic System, State Electrical Inspection Permit and for having the inspections performed. DEQ site evluation for septic system has been completed. All other permits (unless noted elsewhere) are not required to be obtained by the Contractor due to project’s Federal status. The lack of permits will not have negative impacts to the Contractor’s license and ability to work within the city in the future. Contractor is responsible, as noted above, to comply with all codes, laws and regulations applicable to this work.

H-7 Landscape Preservation

(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

(b) Prevention of Oil Spills. If the Contractor maintains storage facilities for oil or oil products onsite, appropriate preventive measures shall be taken to insure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual States. Servicing of all equipment shall be done only in the area approved by the Contracting Officer. If the total oil or oil products storage exceeds 5000 liters (1,320 gallons) or if any single container exceeds a capacity of 2500 liters (660 gallons), the Contractor shall prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer. The Contractor will be required to make reasonable attempts to preserve the scenic and natural environment along this construction project.

(c) Trash and Refuse - Contractor shall remove all of his own trash and refuse from the contract area. Material to be removed includes, but is not limited to; used engine oil, oil filters, oil cans, grease cartridges, camp refuse such as tin cans, paper, garbage, etc. This material must be removed to a State, County, or Municipality-designated solid waste disposal area.

(d) Erosion Prevention and Control - Contractors operations shall be conducted reasonably to minimize soil erosion. Equipment shall not be operated when ground conditions are such that excessive damage will result. The kinds and intensity of erosion control work done by the Contractor shall be adjusted to ground and weather conditions and the need for controlling runoff. Erosion control work shall be kept current immediately proceeding expected seasonal periods of precipitation or runoff.

If the Contractor fails to do seasonal erosion control work prior to any seasonal period of precipitation or runoff, the Government may (1) by contract or otherwise, perform erosion control work and charge to the Contractor any cost incurred by the Government that is directly related to the performance of such erosion control work or (2) terminate the contract for default.

H-8
Payments for Incidental Items

The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with plans, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered indirect to and included in the payment for items shown.

H-9

Performance and Payment Bond Amounts with Option Items

The Contracting Officer, based on the contract clause entitled “Additional Bond Security (FAR 52.228-2) may require an increase in the penal sum of the bond if the option item(s) is (are) exercised after the initial award. The increase, if any, will be based on an amount no greater than the total contract price, as modified. The Contracting Officer reserves the right to maintain the penal sums based on the original contract amounts if Option Item additions are minimal, or if Base item performance completion is substantial.

H-10
Release of Performance and Payment Bonds

Performance and payment security furnished under this contract must be retained by the Government for a minimum of one year after acceptance of all work under the contract including any applicable warranty period. Performance and payment security other than corporate or individual surety bonds will be returned to the Contractor one year after completion of work if no claims against these bonds have been filed at that time.

H-11 AGAR 452.228-71 Insurance Coverage (NOV 1996)

Pursuant to FAR clause 52.228-5, Insurance – Work on a government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:

(a) Workers Compensation and Employer’s Liability. The Contractor is required to comply with applicable Federal and State worker’s compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer’s liability section of the insurance policy, except when contract operations are so commingled with a Contractor’s commercial operations that it would not be practical to require this coverage. Employer’s liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker’s compensation to be written by private carriers.

(b) General Liability. The Contractor shall have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence.

(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.

(End of Clause)

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I-1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.202-1Definitions (NOV 2013)
52.203-3Gratuities (APR 1984)
52.203-5Covenant Against Contingent Fees (APR 1984)
52.203-6Restrictions on Subcontractor Sales to the Government (SEP 2006)
52.203-7Anti-Kickback Procedures (OCT 2010)

52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity

(MAY 2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014)

52.203-12Limitation on Payments to Influence Certain Federal Transactions (OCT 2010)
52.203-17Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights (APR 2014)
52.204-4Printed or Copied Double-Sided on Recycled Paper (MAY 2011)
52.204-10Reporting Executive Compensation and First-Tier Subcontract Awards (JUL 2013)
52.204-13System for Award Management Maintenance (JUL 2013)

52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (AUG 2013)

52.209-9Updates of Publicly Available Information Regarding Responsibility Matters (JUL 2013)
52.211-18Variation in Estimated Quantity (APR 1984)
52.215-2Audit and Records -- Negotiation (OCT 2010)
52.219-6Notice of Total Small Business Set-Aside (NOV 2011)
52.219-8Utilization of Small Business Concerns (OCT 2014)
52.219-14Limitations on Subcontracting (NOV 2011)
52.222-3Convict Labor (JUN 2003)
52.222-4Contract Work Hours and Safety Standards Act -- Overtime Compensation (MAY 2014)
52.222-6Construction Wage Rate Requirements (May 2014)
52.222-7Withholding of Funds (MAY 2014)
52.222-8Payrolls and Basic Records (MAY 2014)
52.222-9Apprentices and Trainees (JUL 2005)
52.222-10Compliance with Copeland Act Requirements (FEB 1988)
52.222-11Subcontracts (Labor Standards) (MAY 2014)
52.222-12Contract Termination - Debarment (MAY 2014)
52.222-13Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014)
52.222-14Disputes Concerning Labor Standards (FEB 1988)
52.222-15Certification of Eligibility (MAY 2014)
52.222-21Prohibition of Segregated Facilities (FEB 1999)
52.222-26Construction Wage Rate Requirements (May 2014)
52.222-27Affirmative Action Compliance Requirements for Construction (FEB 1999)
52.222-35Equal Opportunity for Veterans (JUL 2014)
52.222-36Equal Opportunity for Workers with Disabilities (Jul 2014)
52.222-37Employment Reports on Veterans (JUL 2014)
52.222-40Notification of Employee Rights under the National Labor Relations Act (DEC 2010)
52.222-50Combating Trafficking in Persons (MAR 2015)
52.223-2Affirmative Procurement of Biobased Products under Service and Construction Contracts (SEP 2013)
52.223-5Pollution Prevention and Right-to-Know Information (MAY 2011)
52.223-6Drug-Free Workplace (MAY 2001)
52.223-18Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011)
52.225-13Restrictions on Certain Foreign Purchases (JUN 2008)
52.227-1Authorization and Consent (DEC 2007)
52.227-2Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007)
52.227-4Patent Indemnity -- Construction Contracts (DEC 2007)
52.228-2Additional Bond Security (OCT 1997)
52.228-11Pledges of Assets (JAN 2012)
52.228-12Prospective Subcontractor Requests for Bonds (MAY 2014)
52.228-14Irrevocable Letter of Credit (NOV 2014)
52.228-15Performance and Payment Bonds – Construction (OCT 2010)
52.229-3Federal, State, and Local Taxes (FEB 2013)
52.232-5Payments under Fixed-Price Construction Contracts (MAY 2014)
52.232-17Interest (MAY 2014)
52.232-23Assignment of Claims (MAY 2014)

52.232-27 Prompt Payment for Construction Contracts (MAY 2014)

52.232-33Payment by Electronic Funds Transfer – System for Award Management (JUL 2013)
52.232-39Unenforceability of Unauthorized Obligations (JUN 2013)
52.232-40Providing Accelerated Payments to Small Business Subcontractors (DEC 2013)
52.233-1Disputes (MAY 2014)
52.233-3Protest after Award (AUG 1996)
52.233-4Applicable Law for Breach of Contract Claim (OCT 2004)
52.236-2Differing Site Conditions (APR 1984)
52.236-3Site Investigation and Conditions Affecting the Work (APR 1984)
52.236-5Material and Workmanship (APR 1984)
52.236-6Superintendence by the Contractor (APR 1984)

52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984)

52.236-13Accident Prevention (NOV 1991)
52.236-14Availability and Use of Utility Services (APR 1984)
52.236-15Schedules for Construction Contracts (APR 1984)
52.236-17Layout of Work (APR 1984)
52.236-21Specifications and Drawings for Construction (FEB 1997)

Alternate I (APR 1984)

52.236-26Preconstruction Conference (FEB 1995)
52.242-13Bankruptcy (JUL 1995)
52.243-4Changes (JUN 2007)
52.244-6Subcontracts for Commercial Items (MAR 2015)
52.245-1Government Property (APR 2012)
52.246-21Warranty of Construction (MAR 1994)

Alternate I (APR 1984)

52.248-3Value Engineering – Construction (OCT 2010)
52.249-2Termination for Convenience of the Government (Fixed-Price) (APR 2012)--Alternate I (SEP 1996)
52.249-10Default (Fixed-Price Construction) (APR 1984)
52.253-1Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.232-70Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996)
452.236-71Prohibition Against the Use of Lead-Paint (NOV 1996)
452.236-72Use of Premises (NOV 1996)
452.236-73Archeological or Historic Sites (FEB 1988)
452.236-74Control of Erosion, Sedimentation and Pollution (NOV 1996)
452.236-76Samples and Certificates (FEB 1988)
452.236-77Emergency Response (NOV 1996)

I-2 52.204-7 System for Award Management (JUL 2013)

(a) Definitions. As used in this provision— “Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.

“Data Universal Numbering System +4 (DUNS+4) number” means the DUNS number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional System for Award Management records for identifying alternative Electronic Funds Transfer (EFT) accounts (see the FAR at Subpart 32.11) for the same concern.

“Registered in the System for Award Management (SAM) database” means that—

(1) The offeror has entered all mandatory information, including the DUNS number or the DUNS+4 number, the Contractor and Government Entity (CAGE) code, as well as data required by the Federal Funding Accountability and Transparency Act of 2006 (see Subpart 4.14) into the SAM database;

(2) The offeror has completed the Core, Assertions, and Representations and Certifications, and Points of Contact sections of the registration in the SAM database;

(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS). The offeror will be required to provide consent for TIN validation to the Government as a part of the SAM registration process; and

(4) The Government has marked the record “Active”.

(b)(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the SAM database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.

(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation “DUNS” or “DUNS +4” followed by the DUNS or DUNS +4 number that identifies the offeror’s name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the SAM database.

(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.

(1) An offeror may obtain a DUNS number—

(i) Via the Internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or

(ii) If located outside the United States, by contacting the local Dun and Bradstreet office. The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.

(2) The offeror should be prepared to provide the following information:

(i) Company legal business.

(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.

(iii) Company Physical Street Address, City, State, and ZIP Code.

(iv) Company Mailing Address, City, State and ZIP Code (if separate from physical).

(v) Company Telephone Number.

(vi) Date the company was started.

(vii) Number of employees at your location.

(viii) Chief executive officer/key manager.

(ix) Line of business (industry).

(x) Company Headquarters name and address (reporting relationship within your entity).

(d) If the Offeror does not become registered in the SAM database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.

(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering. Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.

(f) Offerors may obtain information on registration at https://www.acquisition.gov .

(End of clause)

I-3 AGAR 452.209-71 Assurance Regarding Felony Convictions or Tax Delinquent Status for Corporate Applicants (FEB 2012) Alternate I (FEB 2012)

(a) This award is subject to the provisions contained in sections 433 and 434 of the Consolidated Appropriations Act, 2012 (P.L. No. 112-74), Division E, as amended and/or subsequently enacted, regarding corporate felony convictions and corporate federal tax delinquencies. Accordingly, by accepting this award the contractor acknowledges that it –

(1) does not have a tax delinquency, meaning that it is not subject to any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, and

(2) has not been convicted (or had an officer or agent acting on its behalf convicted) of a felony criminal violation under any Federal law within 24 months preceding the award, unless a suspending and debarring official of the United States Department of Agriculture has considered suspension or debarment of the awardee, or such officer or agent, based on these convictions and/or tax delinquencies and determined that suspension or debarment is not necessary to protect the interests of the Government.

(b) If the awardee fails to comply with these provisions, the Forest Service may terminate this contract for default and may recover any funds the awardee has received in violation of sections 433 or 434.

I-4 52.217-7 Option for Increased Quantity—Separately Priced Line Item. (Mar 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 120 days after contract award. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

I-5 FAR 52.219-28 Post-Award Small Business Program Representation (JUL 2013)

(a) Definitions. As used in this clause—

Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts—

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.

(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the rerepresentation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its data in SAM, as necessary, to ensure that they reflect the Contractor’s current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in ORCA for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:

The Contractor represents that it is, is not a small business concern under NAICS Code ______________ assigned to contract number ______________.

[Contractor to sign and date and insert authorized signer’s name and title].

I-6 52.222-54 Employment Eligibility Verification

Employment Eligibility Verification (Aug 2013)

(a) Definitions. As used in this clause— “Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply that is—

(i) A commercial item (as defined in paragraph (1) of the definition at 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products. Per 46 CFR 525.1 (c)(2), “bulk cargo” means cargo that is loaded and carried in bulk onboard ship without mark or count, in a loose unpackaged form, having homogenous characteristics. Bulk cargo loaded into intermodal equipment, except LASH or Seabee barges, is subject to mark and count and, therefore, ceases to be bulk cargo.

“Employee assigned to the contract” means an employee who was hired after November 6, 1986 (after November 27, 2009 in the Commonwealth of the Northern Mariana Islands), who is directly performing work, in the United States, under a contract that is required to include the clause prescribed at 22.1803. An employee is not considered to be directly performing work under a contract if the employee—

(1) Normally performs support work, such as indirect or overhead functions; and

(2) Does not perform any substantial duties applicable to the contract.

“Subcontract” means any contract, as defined in 2.101, entered into by a subcontractor to furnish supplies or services for performance of a prime contract or a subcontract. It includes but is not limited to purchase orders, and changes and modifications to purchase orders.

“Subcontractor” means any supplier, distributor, vendor, or firm that furnishes supplies…