AmendmentNo.1SummaryofChanges.docx
DOCX document 20 KB Posted
- Solicitation number
- AG-04N7-S-15-0016
About this file
Amendment No. 1 - Summary of Changes
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_No.3_SF30.pdf | ||
| AmendmentNo.3_Revised_Drawings.pdf | ||
| AmendmentNo.3_Summary.docx | DOCX document | |
| Amendment_No.2_SF_30.pdf | ||
| AmendmentNo.1Reviseddrawing_Sheet_C8.pdf | ||
| AmendmentNo.1Revised_Specs.docx | DOCX document | |
| Amendment_No.1SF_30.pdf | ||
| Construction_RFP_ProspectRSWaterReplacementSystem.docx | DOCX document | |
| REVISED_DRAWINGS.pdf | ||
| Specs.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROSPECT RANGER STATION
WATER AND WASTEWATER SYSTEM REPLACEMENT
Solicitation # AG-04N7-S-15-0016 Summary of Amendment 1
Find the following items providing clarification, revisions, or supplement information to the original solicitation documents:
1. Schedule of Items - The schedule of items for the sewage system option items has been revised:
· Removed 6-inch Sanitary Sewer line item (previously item #40)
· Revised the estimated quantity for Sewer Manhole from 2 to 1 (item #41)
· Revised the estimated quantity for Sanitary Sewer Cleanouts from 6 to 3 (item #42)
· Revised the estimated quantity for 2-inch Force Main from 300 LF to 360 LF (item #43)
· Revised the estimated quantity for Septic Tanks from 3 to 1, and included the size of the tank in the description (item #44)
· Inserted line item #45, Dual Chamber Septic Tanks (1500 Gal.)
· Revised line item for Effluent Treatment System to include additional description (item #46)
· Revised line item for Sanitary Sewer Lift Station to include additional description (item #50)
2. Drawing Sheet 11 – Revised the Septic System Plan, see drawing C8 Revision 1. Eliminated one manhole, 6” sanitary sewer line, and two external pump stations. Extended two of the 2” force mains, and replaced two septic tanks with dual chamber septic tanks with ¾ HP pump.
3. Specifications - The following specifications have been revised:
· Section 00301 Definition of Bid Items
· Section 01010 Summary of Work
· Section 02531 Sanitary Sewer Manholes, Frames and Covers
· Section 02540 Sanitary Sewage Treatment System
· Section 02543 Septic Tanks
· Section 02661 Polyvinyl Chloride Pipe
· Section 11311 Pump Lift Station