Amendment 3 - more RFI questions revised wage rates in attachment A to this amendment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| amendment_4_8.11.10.doc | DOC document | |
| Attachment_M9.1_amend_4_baldmtn_plans.pdf | ||
| Attachment_A_amendment_3_wage_rate.docx | DOCX document | |
| amendment_2_8.4.10.doc | DOC document | |
| Attachment_A_amendment_2_rev_found_detail.pdf | ||
| Amendment_1_bald_mtn.docx.docm | DOCM document | |
| return_forms_bald_mtn.doc | DOC document | |
| Attachment_3_baldmtn_CSIspecs.pdf | ||
| Attachment_2_baldmtn_plans.pdf | ||
| AG-0281-S-10-0022_complete.doc | DOC document | |
| Attachment_1_wage_rates.docx | DOCX document | |
| attachment_4_Idaho_wrk_comp_cert_.doc | DOC document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
| 1. CONTRACT ID CODE |
| PAGE OF PAGES |
| 1 |
| 2 |
| 2. AMENDMENT/MODIFICATION NO. |
| 3. EFFECTIVE DATE |
| 4. REQUISITION/PURCHASE REQ. NO. |
| 5. PROJECT NO. (If applicable) |
| Three (3) |
| 8.05.2010 |
| 6. ISSUED BY |
| CODE |
| 7. ADMINISTERED BY (If other than Item 6) |
| CODE |
USDA-Forest Service Idaho Montana Acquisition Zone
3815 Schreiber Way
Coeur d’Alene, ID 83815 Same as block 6
| 8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) |
| (X) |
| 9A. AMENDMENT OF SOLICITATION NO. |
FORMCHECKBOX
AG-02RC-S-10-0022 bald mtn. reptr.
9B. DATED (SEE ITEM 11)
7.09.2010
FORMCHECKBOX
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
| CODE |
| FACILITY CODE |
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FORMCHECKBOX
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers FORMCHECKBOX is extended, FORMCHECKBOX is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
| (X) |
| A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN |
THE CONTRACT ORDER NO. IN ITEM 10A.
FORMCHECKBOX
FORMCHECKBOX
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
FORMCHECKBOX
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
FORMCHECKBOX
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor FORMCHECKBOX is not, FORMCHECKBOX is required to sign this document and return 1 copy to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
Some additional questions from an RFI on attached page.
And, new revised wage rate is in effect with this amendment. See Attachment B to this amendment. General Decision Number: ID100001 07/16/2010 ID1
Superseded General Decision Number: ID20080001
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
| 15A. NAME AND TITLE OF SIGNER (Type or print) |
| 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print) |
| 15B. CONTRACTOR/OFFEROR |
| 15C. DATE SIGNED |
| 16B. UNITED STATES OF AMERICA |
| 16C. DATE SIGNED |
| William Standley |
(Signature of person authorized to sign)
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
| 30-105 |
| STANDARD FORM 30 (REV. 10-83) |
Prescribed by GSA
FAR (48 CFR) 53.243
Amendment Three– AG-02RC-S-10-0022
There is a discrepancy in the plans. Drawing A5.1 Detail 16 specifies 6" metal studs. Drawing S1.0 Detail 20 specifies 4" metal studs. It is my assumption that the 4" metal studs are the intended material. If so, I am assuming the R-19 insulation specified also will be the intended material. Please confirm.
4” Studs will suffice.
The amount of retarder needed for concrete placement is going to exceed 3 1/2 hours, quite possibly 5 hours from batch plant to placement. Will this be acceptable?
Yes.
If ledge is encountered at excavation site for new addition to repeater building reference Drawing A5.1, Detail 9 & 18, will the requirement for structural fill be waived?
This is acceptable.
End of amendment 3