OMB APPROVAL NO. 2700-0042

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

AG-0261-S-15-0112

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

08/07/2015

PAGE OF PAGES

IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST NO.

759156

6. PROJECT NO.

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SW Idaho-Nevada Acquisition Center ATTN: Karen Morthland 1249 South Vinnell Way, Suite 200 Boise ID 83709

SW Idaho-Nevada Acquisition Center ATTN: Karen Morthland 1249 South Vinnell Way, Suite 200 Boise ID 83709

9. TECHNICAL INFORMATION

CALL:

a. NAME DuWayne Kimball

b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

(208) 737-3207

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

Northfork Helibase Project 2015

Sawtooth National Recreation Area Ketchum, ID

Price Range The Government’s estimate is: Between $100,000 and $250,000.

11. The Contractor shall begin performance within 10 calendar days and complete it within 270 calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See Section F, Clause 52.211-10)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12b.)

YES NO

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and 4 copies to perform the work required are due at the place specified in Item 8 by 12:00 pm local time September 8, 2015. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

b. An offer guarantee is, is not required. (If “is required” see AGAR Clause 452.228-70)

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Computer Generated Prescribed by GSA FAR (48 CFR) 53.236-1(e)

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

Duns No. ______________________________________

TIN: ___________________________________________

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER

(Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

SW Idaho-Nevada Acquisition Center ATTN: Karen Morthland 1249 South Vinnell Way, Suite 200 Boise ID 83709

Submit invoice to COR for the work performed. Invoice will be reviewed and approved or rejected by the COR within 7 days of receipt of the invoice. Rejected invoices must be corrected and resubmitted. COR will forward the approved invoice to the CO who will submit to:

USDA, OCFO, COD, APB

PO Box 60075 New Orleans, LA 70160

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract.

The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31a. NAME OF CONTRACTING OFFICER (Type or print)

KAREN L. MORTHLAND

30b. SIGNATURE

30c. DATE

31b. UNITED STATES OF AMERICA

BY

31c. DATE

Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 3 of 54

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

SCHEDULE OF ITEMS

NORTH FORK HELIBASE CONSTRUCTION PROJECT

SAWTOOTH NATIONAL RECREATION AREA

ITEM

NO. DESCRIPTION

METHOD

OF MEAS UNIT QUANTITY

UNIT

PRICE

TOTAL

AMOUNT

BASE BID

000050-1

1600 SF Modular Building LSQ LS

1 $XXXXX $

TOTAL

BASE

OPTION ITEMS

000050-2

Additional Office Space A (120 sf of building square footage)

LSQ LS

1 $XXXXX $

000050-3

Additional Office Space B (240 sf of building square footage)

LSQ LS

$XXXXX $

000050-4

Concrete Pads, Ramps, Stairs, Sidewalks, and Steel Railings and Handrails

LSQ LS

1 $XXXXX $

000501-5

Installation of Central Forced Air Conditioning LSQ LS

1 $XXXXX $

OPTIONS $

BASE PLUS

OPTIONS $

If awarded, either option 000050-2 or option 000050-3 will be awarded at the time of the base award but not both. The other option items are independent of other option items being selected and may be awarded within 120 days of the base award date.

* Designated Method of Measurement: LSQ - Lump Sum Quantities

B.2 Payment for Bond Premiums

Note: Payment for bond premiums in accordance with FAR Clause 52.232-5, Payment Under Fixed-Price Construction Contracts, shall not be in addition to the contract price.

B.3 Basis For Payment

All items shown or noted on the drawings, which are not specifically bid items, are considered incidental items. The cost of furnishing and installing all incidental items will not be paid for separately, but shall be included in the unit price bid for other items unless noted otherwise.

Payment will be made upon completion and acceptance according to pay items listed in the Schedule of Items.

Duns: ______________________________________ TIN: ___________________________________________

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 4 of 54

PART I - THE SCHEDULE

SECTION C - DESCRIPTION/SPECIFICATIONS

C.1 Project Description

This project consists of designing, constructing, delivering, and installing a modular Helibase operations office building on the SNRA (Sawtooth National Recreation Area) Headquarters property. Designing and constructing a permanent concrete foundation for the proposed modular building, delivering and placing the building, and installing utilities that will be capped at 10’ from the building are included in the package. Except for the electricity utilities will be connected at a later date in a separate contract. This project includes completing required earthwork and finish grading to construct a level pad for the building and concrete foundation. Additional Building square footage, constructing access ramps, concrete pads, stairs, constructing concrete sidewalks, and completing final site grading up to 10’ away from the building boundaries are included as option items in the project.

C.2 Project Location

The existing SNRA Headquarters Property is located 8 miles north of Ketchum, Blaine County, Idaho just off State Highway 75.

C.3 Estimated Price Range

Government Cost Estimate, per FAR 36.204, is between $100,000 and $250,000.

C.4 Specifications

The project specifications for the Northfork Helibase Project 2015 are as follows:

ITEM NO. DESCRIPTION

Section 000050 - Modular Office Building Section 011250 - Measurement And Payment Section 013300 - Submittal Procedures Section 014100 - Quality Control Section 260500 - Common Work Results For Electrical Section 260519 - Low-Voltage Electrical Power Conductors And Cables Section 260526 - Grounding And Bonding For Electrical Systems Section 260533 - Raceways And Boxes For Electrical Systems Section 260553 - Identification For Electrical Systems Section 260923 - Lighting Control Devices Section 262726 - Wiring Devices Section 264313 - Surge Protection For Low-Voltage Electrical Power Circuits Section 265100 - Interior Lighting Section 270500 - Common Work Results For Communications Section 270526 - Grounding And Bonding For Communications Systems Section 270528 - Pathways For Communications Systems Section 271100 - Communications Equipment Room Fittings Section 271200 - Communications Copper Network Cabling

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 5 of 54

SECTION E - INSPECTION AND ACCEPTANCE

E.1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - https://www.acquisition.gov/far and the Agriculture Acquisition Regulations – www.usda.gov/procurement/policy/agar.html.

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

E.2 Inspection and Acceptance

Periodic field inspection will be made by the Contracting Officer’s Representative (COR) or the COR’s designated inspector. Work not completed to Contract specifications shall be reworked without additional compensation to the Contractor.

https://www.acquisition.gov/far http://www.usda.gov/procurement/policy/agar.html

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 6 of 54

SECTION F - DELIVERIES OR PERFORMANCE

F.1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition

52.242-14 Suspension of Work (APR 1984)

F.2 FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) Alternate I (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10-calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use within 270 Calendar Days. The time stated for completion shall include final cleanup of the premises.

ESTIMATED START DATE CONTRACT TIME

September 15, 2015 270 Calendar Days

F. 3 AGAR 452.236-75 Maximum Workweek--Construction Schedule (Nov 1996)

Within 3 calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in writing for approval:

(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and

(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposed to carry out the work.

The maximum workweek that will be approved is between the hours between 7:00 a.m. and 7:00 p.m.

Monday through Friday.

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 7 of 54

SECTION G – CONTRACT ADMINISTRATION DATA

G.1 Government-Furnished Materials

The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the “Government Property” FAR clause contained elsewhere in the contract. NONE

G.2 Measurement

Units of measurement shall be as indicated in the Schedules of Items.

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 8 of 54

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.236-72 Use of Premises (NOV 1996)

H.2 SITE INFORMATION AND LIMITATIONS

The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:

The site will be occupied during the construction period and the contractor’s operation shall not hinder use and occupancy by Forest Service employees. The contractor will be responsible for signing and limiting public and Forest Service access to the construction site.

There is existing electrical service for the site. Contractor shall have permission to use existing electrical services during construction. Contractor shall be aware of the use of electrical services, and shall limit the use of electrical services to the construction alone. Contractor is responsible for turning off all lights and power so as not to waste electricity. Contractor shall provide connections and extensions of services as required for construction operations.

There is water service on site. Contractor is to provide connections and extensions of services as required for construction operations.

Contractor and workers shall not have access to toilet facilities during construction. Contactor is to provide his own portable toilet facilities for the duration of construction.

All construction equipment shall be pressure washed before entering the Site. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required.

The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations. The contractor shall coordinate inspection of the equipment by the Forest Service prior to off-loading from the trailer.

H.3 TEMPORARY ACCESS

Parking: Use designated areas for construction personnel or as approved by the Contracting Officer for parking.

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 9 of 54

Provide project signs as follows. Unauthorized signs are not permitted.

Temporary Signs: Provide other signs as indicated and as required informing public and individuals seeking entrance to Project.

Provide temporary, directional signs for construction personnel and visitors as required.

Maintain and touchup signs so they are legible at all times.

H.4 WASTE MANAGEMENT AND DISPOSAL

Processing waste material for salvage and recycling is encouraged.

The Contractor shall provide and maintain appropriate waste disposal containers or bins at the project site for the duration of the project construction. Verify with Contracting Office for placement of disposal containers and bins on the project site.

Waste material and debris shall be picked up and deposited in the waste disposal bins on a daily basis.

Containers must be emptied on a weekly basis unless more frequent emptying is needed.

Burning or burying of construction waste material on site will not be permitted. Material shall be disposed of in accordance with the Waste Material Disposal specification.

H.5 FIELD OFFICES, WORK CAMPS, STAGING AND STORAGE AREAS

Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers (work) on site. Overnight camping and housing on site will not be allowed.

H.6 INSPECTION OF WORKSITE

The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

H.7 FIRE CONTROL

(a) Contractor's Responsibility for Contractor-Caused Fires. The Contractor, whether or not directed by the Forest Service, shall immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by Contractor's employees, whether set directly or indirectly as a result of Contractor operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or resulting from contract operations.

(b) Other Fires. For the purpose of fighting forest fires on or in the vicinity of the project which are not caused by the Contractor or the Contractor’s employees, the Contractor when requested by the Contracting Officer shall place the employees and equipment temporarily at the disposal of the Forest Service. Payment for such services will be made by the Government at not less than the current rate for fire-fighting services established by the Forest Service in the area concerned.

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 10 of 54

Any employees and equipment furnished will be relieved from fire fighting as soon as the Forest Service finds that it is practicable to employ other labor and equipment adequate for the protection of the area.

An equitable adjustment in contract time may be made for this period.

(c) Fire Protection Requirements - Fire Plan. At all times during closed fire season period, as specified by State law, the Contractor shall comply with each of the following provisions to the extent applicable to the Contractor’s operation under the contract.

(1) Fire Tools. The Contractor will provide for each employee in the contract area at least one approved handtool of a type appropriate in the contract area, such as shovel, pulaski, or ax. Tools required and furnished under (2) and (4) below, shall count toward fulfillment of the above requirement. Where additional tools, beyond those required under (2) and (4) below, are to be provided, the Contractor shall seal such tools in one or more boxes painted red and marked "Tools for Fire Only." All tools required herein shall be kept sharp and in good serviceable condition and maintained at locations to be designated by the Forest Service.

(2) Fire Extinguishers and Tools on Mobile or Stationary Equipment. Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:

One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with 4 BC or higher rating.

One - shovel, round point #0 lady or equal.

One - ax, 2 pounds or over, 26-inch minimum length, or one pulaski.

One - water container (at least 1-gallon capacity), not required with stationary equipment.

(3) Spark Arresters. Each internal combustion engine shall be provided with a spark arrester or spark arresting device approved by the Forest Service. Exceptions where the Forest Service may approve mufflers, or other equipment in lieu of spark arresters qualified and rated under Forest Service Standard 5100-1a are: (a) small multiposition engines, such as chain saws, shall meet Society of Automotive Engineers J335b standards; (b) passenger-carrying vehicles and light trucks may have baffle-type mufflers with tail pipe; (c) heavy-duty trucks may have a vertical stack exhaust system and muffler, provided the exhaust stack extends above the cab of the vehicle. An exhaust-driven turbocharger is considered to be a satisfactory spark arrester. Internal combustion engine exhaust systems, arresters, and other devices must be properly installed and maintained.

(4) Powersaws. For each powersaw used in connection with this contract, the following will be provided:

One - shovel, round point #0 lady or equal. Shovel must be immediately available for use.

One - Fire extinguisher, containing not less than 8 ounces of extinguisher fluid, or a dry chemical powder-type of not less than 1-pound capacity. The extinguisher must be immediately accessible to the saw operator at all times.

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 11 of 54

Any fueling or refueling of a powersaw shall only be done in an area which has first been cleared or is free of all material capable of carrying fire; powersaw shall be moved at least 10 feet from place of fueling before starting.

(5) Blasting. Fuse or prima cord shall not be used unless authorized in writing by the COR with special precautions stated.

(6) Smoking. Smoking shall not be permitted within the contract area except on surfaced or dirt roads, at landings, within closed vehicles, in camps, or at other posted places, and shall never be allowed while working or traveling on foot.

(7) Storage of Petroleum and Other Highly Flammable Products. Gasoline, oil, grease, or other highly flammable material will be stored either in a separate building used exclusively for such storage, or at a site where all combustible debris and vegetation is cleared away within a radius of 25 feet. Fire extinguishers and/or sand barrels may be required at such locations specified by the Forest Service when unusually hazardous conditions exist.

(8) Debris Burning and Warming Fires. Burning permits will be required for all debris burning fires. Lunch and warming fires may be allowed in fireproofed areas during periods of low fire danger if and as specified in the fire plan. Such fires must not be left burning unattended.

(9) Precautions for Stoves. Stovepipes on all temporary buildings, trailers, and tents using wood burning stoves, will be equipped with roof jacks and serviceable spark arresters of mesh with openings no larger than 5/8 inch.

All stovepipes, inside and out, will not be closer than 2 feet from any wood or other flammable material or 1 foot if the combustible material is protected by a metal or asbestos shield.

(10) Welding. Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all material capable of carrying fire. Flammable debris and vegetation must be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon standard backpack water container (filled) with handpump attached, shall be immediately available for use in the event of a fire start.

(11) Fire Plan. Prior to initiating work on the contract area, during the closed fire season period, a fire prevention and suppression plan will usually be prepared. The Contractor and the Forest Service will jointly prepare this plan. Such plan shall include a detailed list of men and equipment at the Contractor's disposal for implementing the plan. The fire plan shall also specify additional measures and/or special requirements, such as Hoot Owl restrictions, necessary during periods of critical fire weather conditions.

When Hoot Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:

(i) All high fire risk operations could be terminated at 1300 local time.

(ii) All burning could be stopped, including debris burning fires.

(iii) Patrolman may be required for a period of 2 hours after high fire risk operations and 1 hour after end of work shift. The Contractor shall provide the patrolman unless the contract is for equipment rental, in which case the Government will provide the patrolman.

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 12 of 54

(12) Pump and Trailer.

(13) Burning. Before starting any open burning, the Contractor shall comply with the following:

(i) Submit a burning plan, subject to approval by the Contracting Officer, designed to minimize the impact on air quality and to lessen any fire damage.

(ii) Obtain a burning permit from the District Ranger.

(iii) Use weather forecasts as far as possible in scheduling burning for more favorable dispersal of smoke.

(iv) Fuel shall be reasonably free of dirt and piled to facilitate rapid and complete combustion. Piles shall be tended during burning operations to maintain combustion and to eliminate unnecessary smudges. Piles shall be patrolled during off-work hours to avoid wildfires.

(v) Unless fire season controls dictate otherwise, burning shall be scheduled, as far as practicable, for the most favorable conditions during the burning period.

(vi) Under certain atmospheric conditions, smoke accumulations may become excessive and in these cases, the Regional Forester may, at his/her discretion, prohibit all open burning for definite periods within specific areas of the National Forest.

H.8 AGAR 452.236-77 EMERGENCY RESPONSE (NOV 1996)

(a) Contractor’s Responsibility for Fire Fighting.

(1) The Contractor, under the provisions of FAR clause 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements, shall immediately extinguish all fires on the work site other than those fires in use as a part of the work.

(2) The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor’s agents or employees.

(b) Contractor’s Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.

(c) Contractor’s Responsibility for Responding to Emergencies. When directed by the Contracting Officer, the Contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to be restricted to firefighting). An equitable adjustment for the temporary use of employees and equipment will be made under the Changes Clause, FAR 52.243-4.

H.9 LOSS, DAMAGE, OR DESTRUCTION

(a) Equipment furnished with operator. The Government shall not be liable for loss, damage, or destruction of equipment furnished under this contract except for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) while acting within the scope of their employment.

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 13 of 54

All claims arising under this clause will be submitted to the Contracting Officer.

H.10 INCIDENTAL PAYMENT ITEMS

The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.

H.11 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.

H.12 SAMPLES, TESTS, CITED SPECIFICATIONS

Reference made in the contract to specifications, standards, or test methods adopted by AASHTO, ASTM, GSA, or other recognized National technical associations, shall mean specifications, standards, or test methods (including interim or tentative issues) which are in effect on the date of the solicitation.

H.13 BARRICADES, WARNING SIGNS, AND OTHER DEVICES

The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.

H.14 LANDSCAPE PRESERVATION

(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material, which falls outside of these limits, shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

(b) Operation shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 14 of 54

Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Wash water or waste water from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.

H.15 PREWORK CONFERENCE

Prior to commencement of work, the Contracting Officer will arrange a meeting with the Contractor to discuss the contract terms and work performance requirements. Also at this meeting such things as work progress schedule and fire prevention and suppression plans shall be developed and established in writing.

H.16 STATE OF IDAHO’S NOTICE TO OFFEROR

(a) Prior to award of any contract subject to Idaho Workers' Compensation Laws, the contractor must provide (1) evidence that they have the required workers' compensation coverage or, (2) documentation from the State of Idaho exempting the contractor from such coverage. See Section J.4 for Workers’ Compensation Form. This certificate of verification shall be fully executed by the contractor and signed by the Industrial Commission Compliance Officer prior to award of the contract.

(b) Contractors should obtain and complete a State of Idaho Certificate of Verification of Workers' Compensation Insurance as documentation of insurance coverage or exemption. These certificates may be obtained from and returned to the Employee Compliance Division of the Idaho Industrial Commission at the following offices:

North Idaho Southwest Idaho 1221 Ironwood Street, Suite 100 317 Main Street Coeur d'Alene, ID 83814 P.O. Box 83720

(208) 769-1565 Boise, ID 83720-0041 Fax No. (208) 769-1465 (208) 334-6032

(800) 950-2110 Fax No. (208) 334-5145 Southeast Idaho 1070 Hiline, Suite 300 Pocatello, ID 83201

(208) 236-6366 Fax No. (208) 236-6040

(c) This certificate of verification shall be fully executed by the contractor and signed by the Industrial Commission Compliance Officer prior to award of the contract.

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 15 of 54

PART II - CONTRACT CLAUSES

SECTION I - CONTRACT CLAUSES

I.1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition

52.202-1 Definitions (NOV 2013) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (APR 1984) 52.203-7 Anti-Kickback Procedures (OCT 2010) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (JAN

1997) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (JAN 1997) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY 2011) 52.204-10 Reporting Executive Compensation And First-Tier Subcontract Awards (Jul 2013) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (AUG 2013) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (DEC 2014) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2011) 52.219-8 Utilization of Small Business Concerns (JAN 2011) 52.219-14 Limitations on Subcontracting (NOV 2011) 52.222-3 Convict Labor (JUNE 2003) 52.222-4 Contract Work Hours and Safety Standards Act--Overtime Compensation (JULY 2005) 52.222-6 Davis-Bacon Act (JULY 2005) 52.222-7 Withholding of Funds (FEB 1988) 52.222-8 Payrolls and Basic Records (JUNE 2010) 52.222-9 Apprentices and Trainees (JULY 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (JULY 2005) 52.222-12 Contract Termination - Debarment (FEB 1988) 52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (FEB 1988) 52.222-21 Prohibition of Segregated Facilities (FEB 1999) 52.222-26 Equal Opportunity (MAR 2007) 52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999) 52.222-35 Equal Opportunity for Veterans (SEP 2010) 52.222-36 Affirmative Action for Workers with Disabilities (OCT 2010) 52.222-37 Employment Reports on Veterans (SEP 2010) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (DEC 2010)

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 16 of 54

52.222-50 Combating Trafficking in Persons (FEB 2009) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011) 52.224-1 Privacy Act Notification (APR 1984) 52.225-13 Restrictions on Certain Foreign Purchases (JUNE 2008) 52.228-2 Additional Bond Security (OCT 1997) 52.228-11 Pledges of Assets (JAN 2012) 52.228-12 Prospective Subcontractor Requests for Bonds (OCT 1995) 52.228-14 Irrevocable Letter of Credit (DEC 1999) 52.229-3 Federal, State, and Local Taxes (APR 2003) 52.232-5 Payments Under Fixed-Price Construction Contracts (SEPT 2002) 52.232-9 Limitation on Withholding of Payments (APR 1984) 52.232-17 Interest (OCT 2010) 52.232-23 Assignment of Claims (JAN 1986) 52.232-27 Prompt Payment for Construction Contracts (OCT 2008) 52.232-33 Payment by Electronic Funds Transfer—System Award Management (JULY 2013) 52.233-1 Disputes (JULY 2002) Alternate I (DEC 1991) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

(APR 1984)

52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.236-26 Preconstruction Conference (FEB 1995) 52.242-13 Bankruptcy (JULY 1995) 52.243-4 Changes (JUNE 2007) 52.244-6 Subcontracts for Commercial Items (APR 2015) 52.245-1 Government Property (APR 2012) Alternate I (APR 2012) 52.245-9 Use and Charges (APR 2012) 52.246-21 Warranty of Construction (MAR 1994) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012) Alternate I

(SEPT 1996)

52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.224-70 Confidentiality of Information (FEB 1988) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988)

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 17 of 54

I.2 FAR 52.219-28 Post-Award Small Business Program Representation (JUL 2013)

(a) Definitions. As used in this clause—

Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts—

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.

(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the rerepresentation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other http://www.sba.gov/content/table-small-business-size-standards

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 18 of 54 data in SAM, as necessary, to ensure that they reflect the Contractor’s current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:

The Contractor represents that it is, is not a small business concern under NAICS Code ______________ assigned to contract number ______________.

[Contractor to sign and date and insert authorized signer’s name and title].

I.3 FAR 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts (SEP 2013)

(a) In the performance of this contract, the contractor shall make maximum use of biobased products that are United States Department of Agriculture (USDA)-designated items unless—

(1) The product cannot be acquired—

(i) Competitively within a time frame providing for compliance with the contract performance schedule;

(ii) Meeting contract performance requirements; or

(iii) At a reasonable price.

(2) The product is to be used in an application covered by a USDA categorical exemption (see 7 CFR 3201.3(e)). For example, all USDA-designated items are exempt from the preferred procurement requirement for the following:

(i) Spacecraft system and launch support equipment.

(ii) Military equipment, i.e., a product or system designed or procured for combat or combat-related missions.

(b) Information about this requirement and these products is available at http://www.biopreferred.gov .

(c) In the performance of this contract, the Contractor shall—

(1) Report to http://www.sam.gov , with a copy to the Contracting Officer, on the product types and dollar value of any USDA-designated biobased products purchased by the Contractor during the previous Government fiscal year, between October 1 and September 30; and

(2) Submit this report not later than— http://www.biopreferred.gov/ http://www.sam.gov/

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 19 of 54

(i) October 31 of each year during contract performance; and

(ii) At the end of contract performance.

I.4 FAR 52.225-9 Buy American Act--Construction Materials (MAY 2014)

(a) Definitions. As used in this clause--

“Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is--

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, ad defined in section 3 of the Shipping Act of 1984 (46 U.S.C.

App. 1702), such as agricultural products and petroleum products.

"Component" means any article, material, or supply incorporated directly into construction materials.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

"Cost of components" means--

(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the end product (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

"Domestic construction material" means--

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 20 of 54

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

"Foreign construction material" means a construction material other than a domestic construction material.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements the Buy American Act (41 U.S.C. 10a - 10d) by providing a preference for domestic construction material. In accordance with 41 U.S.C. 431, the component test of the Buy American Act is waived for construction material that is a COTS item (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: NONE

(3) The Contracting Officer may add other foreign construction material to the list in paragraph

(b)(2) of this clause if the Government determines that--

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United

States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American Act.

(1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

AG-0261-S-15-0112 Northfork Helibase Project 2015 Page 21 of 54

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why…