2-ConstructionCostEstimateBreakdown_RevAmendment2.xlsx

XLSX spreadsheet 27 KB Posted

Attached to
Spring Mountain Visitor Gateway Project Federal contract opportunity
Solicitation number
AG-0261-S-12-0008
Issued by
Department of Agriculture Forest Service R4-Intermountain Region

About this file

2

View the file

Other files for this federal contract opportunity

Other files attached to Spring Mountain Visitor Gateway Project, newest first.
File Type Posted
Amend_003_-_AG-0261-S-12-0008.pdf PDF
4-Above_ground_rotor_head_installation.pdf PDF
12-C700_Sh45_RevAmendment2.pdf PDF
15-E101_Sh292_RevAmendment2.pdf PDF
11-A704_Sh254_RevAmendment2.pdf PDF
7-A221_Sh207_RevAmendment2.pdf PDF
Amend_002_-_AG-0261-S-12-0008.pdf PDF
18-ForestServiceGrading.pdf PDF
6-A114_Sh200_RevAmendment2.pdf PDF
13-C617_Sh182_RevAmendment2.pdf PDF
17-E800_Sh303_RevAmendment2.pdf PDF
9-A611_Sh248_RevAmendment2.pdf PDF
14-E002_Sh282_RevAmendment2.pdf PDF
3-096813_FL_-_TILE_CARPETING_RevAmendment2.pdf PDF
5-A101_Sh193_RevAmendment2.pdf PDF
10-A612_Sh249_RevAmendment2.pdf PDF
8-A320_Sh229_RevAmendment2.pdf PDF
16-E701_Sh302_RevAmendment2.pdf PDF
1-Schedule_of_Items_RevAmendment2.pdf PDF
Amend_001_-_AG-0261-S-12-0008.pdf PDF
Site_Visit_Attendees_List.PDF PDF
ATT_2.docx DOCX document
Informational_Purposes_Only.docx DOCX document
ATT_5_-_Spring_Mountain_Visitor_Gateway_Construction_Cost_Estimate_Breakdown.xlsx XLSX spreadsheet
01-31-2013_Spring_Mountain_Visitor_Solicitation.pdf PDF
ATT_1.docx DOCX document
ATT3_-_WD_NV4.pdf PDF
ATT_4_-_Past_Performance_Questionnaire.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACH 5 - Spring Mountain Visitor Gateway AG-0261-S-12-0008
CONSTRUCTION COST ESTIMATE BREAKDOWN

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED CONTRACT PRICE

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

MATERIAL COSTLABOR COSTS
UNITOTHER
LINEITEMOFQUANTITYUNITTOTALMANHOURAVERAGETOTALDIRECTLINE
NOMEASUREMANDAYSRATECOSTSTOTAL
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)
1MobilizationLS1
2Visitor Services Building (including associated Geothermal Slinky Loop system)LS1
3Education Building (including associated Geothermal Slinky Loop system)LS1
4Incorporated ArtLS1
5Prefabricated Multi-User Restroom BuildingEA1
6Pre-manufactured Picnic Shelters - 32'x36'EA2
7Pre-manufactured Shade Structure - 13'x20'EA1
8Surveying and StakingLS1
9CMU Retaining WallsLF300
Site Prep and Demolition (NOT USED - COMPLETED BY OTHERS)N/AN/AXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
10Earthwork, Rough Grading. Fine Grading, and storm drain pipingLS1
11Gabions and RiprapLS1
12Bituminous Pavement, Aggregate Base Course, Concrete Curbs, StripingSY16253
13Site Domestic water, Fire DistributionLS1
14Complete Sewer System, Septic Tanks, Leach Fields, Manholes, DistributionLS1
15Parking Gravel PavingSY2423
16Parking curb stops - installedEA123
17Traffic and Parking signageLS1
18Site Concrete (everything outside of buildings) plain gray concrete, decorative concrete paving, curbs, walls, slabs, walks, trench drains, joint sealantLS1
19Pedestrian Bridges (concrete)EA8
20Steel Railings, Pedestrian Bridge Rail, Steel Deck Rail, Steel Pipe Entry Gates, Vehicular Drive Rails, Weathered Steel at 7 Stones Plaza, USDA Forest Service Shield signs at Pedestrian BridgesLS1
21BollardsEA24
22Sandblasting decorative patterns in concreteLS1
23Flagstone pavingSF615
24Stone seats at upper Amphitheater includes Boulder retaining wall and boulder seatwallsLS1
25Vehicular drive - guardrails, retaining wall, box culvertLS1
26Trash Enclosures, structure, gates (concrete slabs under site concrete)EA2
27Site Electrical, telecomLS1
28Site LightingLS1
29IrrigationLS1
30Planting (turfs, grasses, plants, seeds), Soil PrepLS1
31GrasspaveSF5195
32Rocks, boulders, stepping stones, Boulder wallLS1
33Crusher Fines PavingSF85187
34Site Furnishings, Exterior Drinking FountainsLS1
OPTIONAL ITEMS
1BID OPTION (ALTERNATE) 1 - Lower parking lot asphalt pavingSY2416
2BID OPTION (ALTERNATE) 2 - AmphitheaterLS1
3aBID OPTION (ALTERNATE) 3a - EQUESTRIAN TRAILHEAD PARKING - 2-unit vault pre-manufactured toilet building and 3 panel Kiosk ONLY - NO ADDITIONAL PARKING AREALS1
4BID OPTION (ALTERNATE) 4 - East Entrance GatewayLS1
6BID OPTION (ALTERNATE) 6 - Prefabricated Single-User Restroom with Mechanical/Storage (2 Unit Flush Toilet at Valley Trail) including associated utilites and lift stationLS1

REISSUED CONSTRUCTION COST ESTIMATE BREAKDOWN PER AMENDMENT 2

INSTRUCTIONS FOR COMPLETING CONSTRUCTION COST ESTIMATE BREAKDOWN
Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit
itemizing of all direct costs.
Col 2 Units of Measure. Description of the unit in which each item is to be estimated (examples - square yards - SY, cubic yards - CY, square feet - SF,
linear feet - LF, board feet - BF, each - EA, pound - LB).
Col 3 Quantity. Contractor's estimate of quantity required in terms of unit of measure (column 2). Items and units of measure will be furnished by the
Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise,
the contractor is responsible for determining quantity estimates.
Col 4 and 5 Material Costs. Enter unit cost (Col 4) of the material to be supplied and total cost (col 5); for item listed in column 1.
Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1.
Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1) which are special to the contract and of
significant dollar value.
Col 10 Line Total. Self-explanatory.
NOTE:In addition to other totals derived on various pages, the grand total of column 10, plus overhead and profit will be shown on the last
page as follows
BASE ITEMSOPTIONAL ITEMS
TOTAL MATERIAL COSTS$TOTAL MATERIAL COSTS$

TOTAL LABOR COSTS $ TOTAL LABOR COSTS $

TOTAL OTHER DIRECT COSTS $ TOTAL OTHER DIRECT COSTS $

TOTAL DIRECT COSTS $ TOTAL DIRECT COSTS $

OVERHEAD % $ OVERHEAD % $

SUBTOTAL $ SUBTOTAL $

PROFIT % $ PROFIT % $

TOTAL BASE PRICE $ TOTAL OPTIONAL ITEM PRICE $

DATE FIRM NAME

TITLEBY
(Signature)
INSTRUCTIONS TO OFFERORS
1.The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and
estimated costs (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from
this proposal the offeror may be required to submit a certificate of current cost or pricing data
2.In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit with this
form any additional data, supporting schedules, or substantiation which are reasonable required for the conduct of an appropriate review and
analysis in the light of the specific facets of this procurement. For effective negotiations, it is essential that there be a clear understanding of
a.The existing, verifiable data.
b.The judgmental factors applied in projecting from known data to the estimate, and
c.The contingencies used by the offeror in his proposed price.
In short, the offeror's estimating process itself needs to be disclosed.
3.When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate),
and made available to the contracting officer his authorized representative upon request.
4.By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the
purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate
evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection
with any negotiations prior to contract award.

Sheet1