Addendum Two - RFP Commissioning Services Maintenance Building Expansion.pdf
PDF 204 KB Posted
- Solicitation number
- BPM057517
- Issued by
- Wicomico County, Maryland
About this file
This is Addendum Two to a Request for Proposals issued by Wor-Wic Community College in Maryland for Commissioning Services related to a Maintenance Building Expansion project located at 32000 Campus Dr., Salisbury, MD 21804, specifically at the corner of Horsebridge Drive and Longridge Drive. The addendum addresses clarifications regarding proposer qualifications and project specifications. Questions were submitted on July 10, 2026, seeking clarification on whether annual volume should reflect only the commissioning department or the entire company (with the response indicating annual volume for the entire company should be provided, with qualifications specific to commissioning services), whether project size refers to square footage or price (with the response requiring both metrics), and confirmation of bonding requirements.
The addendum clarifies that a Bid Bond is not required for submissions. Performance, Labor & Materials Bonds are also not required. Liquidated Damages do not apply to bids submitted for this solicitation. These modifications represent significant reductions in financial guarantees and risk mitigation requirements for potential proposers, reducing the compliance burden for bidders interested in providing commissioning services for the maintenance building expansion project, which remains in the planning phase at the time of the addendum issuance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Answers
In the RFP in section 2.4 Profile of the Proposer, annual volume: Is this for the value of just our commissioning department, or the whole main office inclusive of MEP as well?
Please indicate the annual volume for the entire company. Qualifications and experience should be specific to commissioning services provided.
When asking for largest project size, does “size” mean square footage or price of the project?
Please indicate both square footage and price of the project.
3 Is the Bid Bond required? No.
Do Liquidated Damages apply to our bid? If so, how would this be applied and what are the terms?
No.
Is the Performance, Labor & Materials Bond required?
No.
ADDENDUM TWO
REQUEST FOR PROPOSALS
Commissioning Services for Maintenance Building Expansion
END OF ADDENDUM TWO
The following statements, questions and answers are hereby incorporated into and are considered to be an integral part of Wor-Wic Community College's Request for Proposals for Commissioning Services for the maintenance building expansion.
Questions
July 10, 2026