019116 Electrical Systems Commissioning Requirements Maint Bldg Expan.pdf

PDF 99 KB Posted

Attached to
RFP - Commissioning Services for Maintenance Building Expansion
Solicitation number
BPM057517
Issued by
Wicomico County, Maryland

About this file

This is a specification document for electrical systems commissioning requirements for the Wor-Wic Community College Maintenance Building Expansion project located at 32000 Campus Dr., Salisbury, Maryland. The scope of work encompasses commissioning services for the electrical system and its subsystems, including normal power supply systems (distribution panelboards, branch panelboards, and low-voltage transformers) and lighting control systems (occupancy/vacancy sensors, daylight sensors, wall switches/control stations, and plug-load controls). The Electrical Contractor is responsible for providing certified and calibrated measuring instruments, logging devices, and data acquisition equipment to record test data throughout the complete testing range and required test period. The Commissioning Authority must develop comprehensive test checklists for all electrical systems, subsystems, and equipment, including sensor calibration, control sequences, power quality measurements, and responses to control signals under various operating conditions. Testing preparation requires certification that all electrical systems have been completed, calibrated, and are operating according to contract documents before formal testing commences, with verification of each operating cycle in steady-state conditions and inspection of all devices and interlocks identified on checklists.

Testing procedures must verify performance of the entire electrical installation from incoming service through distribution systems to each space, measuring voltages, currents, and operational and control functions across all operating modes, interlocks, and emergency conditions. The Commissioning Authority must submit detailed testing plans, procedures, and checklists, certificates of readiness and completion, test and inspection reports, and corrective action documents. Testing reports shall include measured data, data sheets with sign-offs from testing personnel, and comprehensive summaries describing system operations at the time of testing. If deficiencies are identified outside the electrical system scope, they must be documented and reported to the owner for resolution by appropriate parties before test rescheduling. Seasonal testing requirements must be noted, with initial performance tests completed and documented, and additional tests scheduled as needed.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WOR-WIC COMMUNITY COLLEGE

MAINTENANCE BUILDING EXPANSION

COMMISSIONING SERVICES

ELECTRICAL COMMISSIONING REQUIREMENTS 019116-1

SECTION 019116 – ELECTRICAL SYSTEMS COMMISSIONING REQUIREMENTS

PART 1 - GENERAL

1.1. RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections, apply to this Section.

1.2. SUMMARY

A. This Section includes requirements for commissioning the electrical system and its subsystems and equipment. This Section supplements the general requirements specified in Division 01 Section "General Commissioning Requirements."

B. Related Sections include the following:

1. Division 01 Section "General Commissioning Requirements" for general requirements for commissioning processes that apply to this Section.

C. The following systems and/or equipment shall be commissioned:

1. Normal Power Supply System

a. Distribution panelboard

b. Branch panelboards

c. Low-voltage transformers

2. Lighting Control System (s)

a. Occupancy/vacancy sensors

b. Daylight sensors

c. Wall switches/control stations

d. Plug-load controls

1.3. DEFINITIONS

A. Engineer: Includes Engineer identified in the Contract for Construction between Owner and Contractor, plus consultant/design professionals responsible for design of electrical systems, electrical, communications, and other related systems.

B. CxA: Commissioning Authority.

C. Systems, Subsystems, and Equipment: Where these terms are used together or separately, they shall mean "as-built" systems, subsystems, and equipment.

1.4. CONTRACTOR'S RESPONSIBILITIES

A. The following responsibilities are in addition to those specified in Division 01 Section

"General Commissioning Requirements."

B. Electrical Contractor:

1. Provide certified and calibrated measuring instruments and logging devices to record test data, and data acquisition equipment to record data for the complete

ELECTRICAL COMMISSIONING REQUIREMENTS 019116-2

range of testing for the required test period.

ELECTRICAL COMMISSIONING REQUIREMENTS 019116-3

C. Electrical Contractor:

1. With the Mechanical Contractor, coordinate installations and connections between and among electrical and HVAC systems, subsystems, and equipment.

2. Attend TAB verification testing.

1.5. COMMISSIONING DOCUMENTATION

A. The following are in addition to documentation specified in Division 01 Section "General

Commissioning Requirements."

B. Test Checklists: CxA with assistance of Contractor shall develop test checklists for electrical systems, subsystems, and equipment, including interfaces and interlocks with other systems. CxA shall prepare separate checklists for each mode of operation and provide space to indicate whether the mode under test responded as required. In addition to the requirements specified in Division 01 Section "General Commissioning

Requirements," checklists shall include, but not be limited to, the following:

1. Calibration of sensors and sensor function.

2. Testing conditions under which test was conducted, including (as applicable) ambient conditions, set points, override conditions, and status and operating conditions that impact the results of test.

3. Control sequences for electrical and emergency generator systems.

4. Strength of control signal for each set point at specified conditions.

5. Responses to control signals at specified conditions.

6. Sequence of response(s) to control signals at specified conditions.

7. Electrical demand or power input at specified conditions.

8. Power quality and related measurements.

9. Expected performance of systems, subsystems, and equipment at each step of test.

10. Narrative description of observed performance of systems, subsystems, and equipment. Notation to indicate whether the observed performance at each step meets the expected results.

11. Interaction of auxiliary equipment.

12. Issues log.

1.6. SUBMITTALS

A. The following submittals are in addition to those specified in Division 01 Section "General

ELECTRICAL COMMISSIONING REQUIREMENTS 019116-4

Commissioning Requirements."

B. Testing Procedures: CxA shall submit detailed testing plan, procedures, and checklists for each series of tests. Submittals shall include samples of data reporting sheets that will be part of the reports.

C. Certificate of Readiness: CxA shall compile certificates of readiness from Contractor certifying that systems, subsystems, equipment, and associated controls are ready for testing.

D. Certificate of Completion of Installation, Prestart, and Startup: CxA shall certify that installation, prestart, and startup activities have been completed.

E. Test and Inspection Reports: CxA shall compile and submit test and inspection reports and certificates, and shall include them in systems manual and commissioning report.

F. Corrective Action Documents: CxA shall submit corrective action documents.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1. TESTING PREPARATION

A. Prerequisites for Testing:

1. Certify that electrical systems, subsystems, and equipment have been completed, calibrated, and started; are operating according to the Contract Documents; and that Certificates of Readiness are signed and submitted.

2. Certify that electrical instrumentation and control systems have been completed and calibrated; are operating according to the Contract Documents; and that pretest set points have been recorded.

3. Test systems and intersystem performance after approval of test checklists for systems, subsystems, and equipment.

4. Set systems, subsystems, and equipment into operating mode to be tested (e.g., normal shutdown, normal auto position, normal manual position, unoccupied cycle, emergency power, and alarm conditions).

5. Verify each operating cycle after it has been running for a specified period and is operating in a steady-state condition.

6. Inspect and verify the position of each device and interlock identified on checklists.

Sign off each item as acceptable, or failed. Repeat this test for each operating cycle that applies to system being tested.

7. Check safety cutouts, alarms, and interlocks with life-safety systems during each

ELECTRICAL COMMISSIONING REQUIREMENTS 019116-5

mode of operation.

8. Annotate checklist or data sheet when a deficiency is observed.

9. Verify proper responses of monitoring and control system controllers and sensors to include the following:

a. For each controller or sensor, record the indicated monitoring and control system reading and the test instrument reading. If initial test indicates that the test reading is outside of the control range of the installed device, check calibration of the installed device and adjust as required. Retest malfunctioning devices and record results on checklist or data sheet.

b. Report deficiencies and prepare an issues log entry.

3.2. TESTING

A. Test systems and intersystem performance after test checklists for systems, subsystems, and equipment have been approved.

B. Perform tests using design conditions whenever possible.

1. Simulate conditions by imposing an artificial load when it is not practical to test under design conditions and when written approval for simulated conditions is received from CxA. Before simulating conditions, calibrate testing instruments.

Set and document simulated conditions and methods of simulation. After tests, return settings to normal operating conditions.

C. Scope of Electrical Contractor Testing:

1. Testing scope shall include entire electrical installation, from incoming service through distribution systems to each space. It shall include measuring voltages and currents and effectiveness of operational and control functions.

2. Test all operating modes, interlocks, control responses, responses to abnormal or emergency conditions, and verify proper response of building automation system controllers and sensors.

D. Detailed Testing Procedures: CxA, with Electrical Contractor shall prepare detailed testing plans, procedures, and checklists for electrical systems, subsystems, and equipment.

E. Electrical System Testing: Electrical Contractor shall prepare a testing plan to verify performance of systems identified in “Summary” paragraph of this section. Plan shall include the following:

1. Sequence of testing and testing procedures for each item of equipment and section of wiring to be tested, identified by identification marker. Markers shall be keyed to Drawings for each wiring sector showing the physical location of each item of equipment and electrical wiring test section. Drawings shall be formatted to allow each item of equipment and section of wiring to be physically located and identified when referred to in the system testing plan.

ELECTRICAL COMMISSIONING REQUIREMENTS 019116-6

2. Tracking checklist for managing and ensuring that all wiring systems have been tested.

F. Deferred Testing:

1. If tests cannot be completed because of a deficiency outside the scope of the electrical system, the deficiency shall be documented and reported to Owner.

Deficiencies shall be resolved and corrected by appropriate parties and test rescheduled.

2. If the testing plan indicates specific seasonal testing, appropriate initial performance tests shall be completed and documented and additional tests scheduled.

G. Testing Reports:

1. Reports shall include measured data, data sheets, and a comprehensive summary describing the operation of systems at the time of testing.

2. Include data sheets for each electrical systems to verify proper operation of the electrical systems, the system it serves, the service it provides, and its location.

Provide space for testing personnel to sign off on each data sheet.

3. Prepare a preliminary test report. Deficiencies will be evaluated by Engineer to determine corrective action. Deficiencies shall be corrected and test repeated.

END OF SECTION 019116