This is an Erosion and Sediment Control Plan prepared by Herbert, Rowland & Grubic, Inc. for Mercer County, Pennsylvania, associated with the Repairs of Bridge 1916 project located in Jefferson Township on Route T-547 (Hassel Road). The project involves repairs to bridge abutments and barriers, requiring comprehensive erosion and sediment control measures throughout the construction period. Key construction activities include installation of cofferdams, rip rap scour protection, wing wall tie-back anchors, concrete repairs, and site stabilization. The plan mandates a preconstruction meeting at least 7 days prior to earth disturbance activities, with notification to the Pennsylvania One Call System Inc. required at least 3 days before work begins. Temporary and permanent erosion control measures include compost filter socks, erosion control blankets, seeding with specific formulas and rates, mulching, and pumped water filter bags for dewatering. The contractor must maintain daily and weekly inspections of all best management practices (BMPs) with documentation of deficiencies and corrective actions. Permanent stabilization requires achievement of a minimum uniform 70% perennial vegetative cover before removal of temporary controls.

Fill material imported to the site must meet the Department of Environmental Protection's definition of clean fill, with contractors responsible for performing environmental due diligence. All construction waste must be removed from the site and recycled or disposed in accordance with Pennsylvania solid waste management regulations. Temporary seeding using annual rye (Formula E) is required for areas exposed to traffic, while permanent seeding uses tall fescue and other perennial species (Formula D) applied at specified rates between March 15 and October 15. Topsoil stockpiles shall not exceed 35 feet in height with slopes of 2H:1V or flatter, protected by compost filter socks. The contractor is responsible for street cleaning and preventing off-site sediment tracking, with sediment removal from BMPs disposed of on-site during construction or at approved facilities once stabilization is achieved. Violations of Pennsylvania Clean Streams Law provisions regarding E&S BMP installation and maintenance may result in civil penalties up to $10,000 per day or criminal penalties up to $25,000 for misdemeanors.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DISTRICT COUNTY ROUTE SECTION SHEET

OF

REV

NO

REVISIONS DATE BY APPD

D-9012 CADD (02-90) REVISED (04-17)

D

E C

:5

P

L O

T T

E D

CKD: MJA

HERBERT, ROWLAND & GRUBIC, INC.

220 WEST KENSINGER DRIVE

SUITE 100

CRANBERRY TOWNSHIP, PA. 16066

T-547

JEFFERSON TOWNSHIP

1-0

DES: EJT DWG: EJT

MERCER

EROSION AND SEDIMENT CONTROL NOTES

MJA

CLEAN FILL REQUIREMENTS

DETAILED ON THE APPROVED PLAN, WHETHER LOCATED WITHIN OR OUTSIDE OF THE CONSTRUCTION LIMITS.

SEPARATE EROSION AND SEDIMENTATION CONTROL PLAN FOR EACH SPOIL, BORROW OR OTHER WORK AREA NOT

THE CONTRACTOR MUST DEVELOP, AND HAVE APPROVED BY THE APPROPRIATE COUNTY CONSERVATION DISTRICT, A

APPLICABLE.

CHAPTER 287: RESIDUAL WASTE MANAGEMENT, OR CHAPTER 271: MUNICIPAL WASTE MANAGEMENT, WHICHEVER IS

MANAGED IN ACCORDANCE WITH DEP'S MUNICIPAL OR RESIDUAL WASTE REGULATIONS BASED ON 25 PA. CODE

FILL MATERIAL THAT DOES NOT QUALIFY AS CLEAN FILL IS REGULATED FILL. REGULATED FILL IS WASTE AND MUST BE

"MANAGEMENT OF FILL".

QUALIFIES AS CLEAN FILL. TESTING SHOULD BE PERFORMED IN ACCORDANCE WITH APPENDIX A OF DEP'S POLICY

BEEN AFFECTED BY A SPILL OR RELEASE OF A REGULATED SUBSTANCE, IT MUST BE TESTED TO DETERMINE IF IT

THE FILL MAY HAVE BEEN SUBJECTED TO A SPILL OR RELEASE OF A REGULATED SUBSTANCE. IF THE FILL MAY HAVE

DILIGENCE UNLESS VISUAL INSPECTION AND/OR REVIEW OF THE PAST LAND USE OF THE PROPERTY INDICATES THAT

TESTING, ENVIRONMENTAL ASSESSMENTS OR AUDITS. ANALYTICAL TESTING IS NOT A REQUIRED PART OF DUE

PROPERTY USE HISTORY, SANBORN MAPS, ENVIRONMENTAL QUESTIONNAIRES, TRANSACTION SCREENS, ANALYTICAL

VISUAL PROPERTY INSPECTIONS, ELECTRONIC DATA BASE SEARCHES, REVIEW OF PROPERTY OWNERSHIP, REVIEW OF

ENVIRONMENTAL DUE DILIGENCE IS DEFINED AS: INVESTIGATIVE TECHNIQUES, INCLUDING, BUT NOT LIMITED TO, RESIDENTIAL LIMITS IN TABLES FP-1A AND FP-1B FOR IN DEP'S POLICY "MANAGEMENT OF FILL".

THAT THE FILL MATERIAL CONTAINS CONCENTRATIONS OF REGULATED SUBSTANCES THAT ARE BELOW THE

SPILL OR RELEASE OF A REGULATED SUBSTANCE STILL QUALIFIES AS CLEAN FILL PROVIDED THE TESTING REVEALS

OR ON THE WATERS OF THE COMMONWEALTH UNLESS OTHERWISE AUTHORIZED. FILL MATERIALS AFFECTED BY A

THE TERM INCLUDES SOIL, ROCK, STONE, DREDGED MATERIAL. THE TERM DOES NOT INCLUDE MATERIALS PLACED IN

CLEAN FILL IS DEFINED AS: UNCONTAMINATED, NON-WATER SOLUBLE, NON-DECOMPOSABLE, INERT, SOLID MATERIAL.

FILL. CLEAN FILL CAN NOT BE PLACED IN OR ON WATERS OF THE COMMONWEALTH.

FILL IMPORTED TO THE SITE MEETS THE DEPARTMENT OF ENVIRONMENTAL PROTECTION'S (DEP) DEFINITION OF CLEAN

THE OPERATOR(S) WILL BE RESPONSIBLE TO PERFORM ENVIRONMENTAL DUE DILIGENCE AND DETERMINE THAT ALL

SEQUENCE OF CONSTRUCTION

PERMANENT CONTROL MEASURES

RESEEDED AS NECESSARY.

STAND OF VEGETATION IS ACHIEVED AND MAINTAINED. AREAS SHALL BE FERTILIZED AND

SEEDED AND VEGETATED AREAS SHALL BE CHECKED REGULARLY TO INSURE THAT A GOOD 1.

MAINTENANCE:

EROSION AND SEDIMENT POLLUTION CONTROL PLAN.

SEED MIX, REFER TO THE SEEDING NOTES AND SEEDING SCHEDULE TABLE PROVIDED ON THE

ON ALL NON-PAVED DISTURBED AREAS. WITH REGARD TO SOIL PREPARATION AND PERMANENT

FERTILIZING, SEEDING, AND MULCHING WILL BE USED AS A PERMANENT E&S CONTROL MEASURE 1.

INSTALLATION:

A. PERMANENT VEGETATIVE STABILIZATION

BE REMOVED AND PROPERLY DISPOSED.

STABILIZATION WILL BE A UNIFORM 70% PERENNIAL VEGETATIVE COVER) TEMPORARY CONTROL MEASURES CAN

12. ONCE THE SITE HAS BEEN STABILIZED (AS PER PERMANENT SEEDING SPECIFICATIONS, THE STANDARD FOR

INSTALL PERMANENT SEEDING FOR ALL DISTURBED AREAS.11.

OPERATIONS ON THE SITE.

CONTINUE TO SPREAD TOPSOIL ON ALL AREAS TO BE RE-SEEDED, OR RE-TREATED. BEGIN FINE GRADING 10.

PLACE CONCRETE FOR ABUTMENT/BARRIER REPAIRS.9.

STREAM IMMEDIATELY.

REMOVE CONCRETE TO PERFORM ABUTMENT AND BARRIER REPAIRS. REMOVE ANY DEBRIS THAT FALLS INTO THE 8.

INSTALL WING WALL TIE-BACK ANCHORS.7.

INSTALL RIP RAP SCOUR PROTECTION, REMOVE COFFERDAM, AND RESTORE FLOW.6.

SHALL BE REMOVED IMMEDIATELY. ANY DAMAGED SECTION OF COFFERDAM SHALL BE REPAIRED IMMEDIATELY.

DEWATER THE WORK AREA WITH A PUMPED WATER FILTER BAG. ANY WATER THAT ENTERS THE WORKZONE 5.

ACCORDANCE WITH LOCAL, STATE, AND FEDERAL REGULATIONS.

EXCAVATE AS REQUIRED FOR INSTALLATION OF RIP RAP SCOUR PROTECTION AND DISPOSE OF MATERIAL IN 4.

DETAILS.

INSTALL COFFERDAM AT THE LOCATION SHOWN ON THE PLAN DRAWINGS AND IN ACCORDANCE WITH THE 3.

WASHOUT, AT ALL LOCATIONS INDICATED ON THE PLAN.

INSTALL COMPOST FILTER SOCKS, INCLUDING COMPOST FILTER SOCKS FOR STOCKPILE AND CONCRETE 2.

FIELD MARK LIMITS OF DISTURBANCE AND ESTABLISH SURVEY BENCHMARKS AND REFERENCE POINTS.1.

ACCORDANCE WITH THE STANDARD DETAIL AND THE MANUFACTURER'S RECOMMENDATIONS.

COFFERDAMS SHALL BE INSTALLED IN CAUSED BY CONSTRUCTION ACTIVITY. TEMPORARY

TEMPORARY COFFERDAMS WILL BE USED TO PROTECT IMPOUNDED WATER FROM THE TURBIDITY

E. TEMPORARY COFFERDAM

MANUFACTURER'S RECOMMENDATIONS.

WATER FILTER BAGS SHALL BE INSTALLED IN ACCORDANCE WITH THE STANDARD DETAIL AND THE

PROVIDE A PRETREATMENT FILTRATION OF THE WATER BEFORE IT LEAVES THE SITE. PUMPED WILL

PUMPED WATER FILTER BAGS WILL BE USED TO CLEAN EQUIPMENT AND CONTAMINATED WATER AND

D. PUMPED WATER FILTER BAGS

RESEEDED AS NECESSARY.

STAND OF VEGETATION IS ACHIEVED AND MAINTAINED. AREAS SHALL BE FERTILIZED AND

SEEDED AND VEGETATED AREAS SHALL BE CHECKED REGULARLY TO ENSURE THAT A GOOD 1.

MAINTENANCE:

TO SEEDING NOTES.

TO THE SEEDING SCHEDULE TABLE; WITH REGARD TO SOIL PREPARATION AND SEEDING, REFER

INCLUDING STOCKPILED SOIL MATERIALS. WITH REGARD TO THE TEMPORARY SEED MIX, REFER

TRAFFIC, SHALL NOT REMAIN UNSEEDED OR COVERED BY MULCH FOR MORE THAN FOUR DAYS,

ON ALL NON-PAVED DISTURBED AREAS. EXPOSED SOILS, NOT SUBJECT TO CONSTRUCTION

FERTILIZING, SEEDING, AND MULCHING WILL BE USED AS A TEMPORARY E&S CONTROL MEASURE 1.

INSTALLATION:

C. TEMPORARY VEGETATIVE STABILIZATION

ALL DAMAGED SECTIONS OF THE EROSION CONTROL BLANKET SHALL BE REPLACED.1.

MAINTENANCE:

RECOMMENDATIONS.

USE STAPLE PATTERN D FOR ALL BLANKET INSTALLATIONS AS PER THE MANUFACTURER'S 2.

WITH THE MANUFACTURER'S RECOMMENDATIONS.

INSTALL THE EROSION CONTROL BLANKETS IN TEN FOOT VERTICAL INCREMENTS IN ACCORDANCE 1.

INSTALLATION:

ACCORDANCE WITH THE STANDARD DETAIL.

ON ALL SLOPES GREATER THAN 3:1 AND IN THE LOCATIONS SHOWN ON THE PLAN AND IN INSTALLED

THE NORTH AMERICAN GREEN C125BN EROSION CONTROL BLANKET OR APPROVED EQUAL SHALL BE

B. EROSION CONTROL BLANKET

DUE TO WEATHERING.

ADHERE TO ANY MANUFACTURER'S RECOMMENDATIONS FOR REPLACING COMPOST FILTER SOCK 3.

SOIL DISTURBANCE.

ORIGINAL ONE TO CREATE MORE SEDIMENT STORAGE CAPACITY WITHOUT SLIGHTLY BEHIND THE

FILTER SOCK. ALTERNATELY, A SECOND COMPOST FILTER SOCK CAN BE PLACED ON TOP OF AND

ACCUMULATION HAS REACHED ONE-HALF (1/2) OF THE EFFECTIVE HEIGHT OF THE COMPOST

REMOVE SEDIMENT AT THE BASE OF THE UPSLOPE SIDE OF THE COMPOST FILTER SOCK WHEN 2.

NECESSARY REPAIRS WILL BE MADE IMMEDIATELY.

THE COMPOST FILTER SOCK SHALL BE INSPECTED AFTER EVERY PRECIPITATION EVENT. ANY 1.

MAINTENANCE:

SEDIMENT RETENTION.FILTRATION AND

FILLING IN THE SEAM BETWEEN THE SOIL SURFACE AND THE DEVICE, WHICH WILL IMPROVE

LOOSE COMPOST MUST BE BACKFILLED ALONG THE UPSLOPE OF THE COMPOST FILTER SOCK, 2.

DEPTH BELOW THE GROUND SURFACE AT THE SPECIFIED INTERVALS.REQUIRED

SUPPORT STAKES WILL BE DRIVEN INTO THE CENTER OF THE COMPOST FILTER SOCK AT THE 1.

INSTALLATION:

ACCORDANCE WITH THE STANDARD DETAIL.

COMPOST FILTER SOCK SHALL BE INSTALLED AT THE LOCATION SHOWN ON THE PLAN AND IN

A. COMPOST FILTER SOCKS

MAINTAIN RECORDS OF ALL INSPECTIONS.

MANUFACTURER'S RECOMMENDATIONS AND THE STANDARD DETAIL. THE CONTRACTOR SHALL

REPLACE ANY DAMAGED SECTIONS OF THE EROSION CONTROL BLANKETS IN ACCORDANCE WITH THE 8.

NECESSARY.

OF VEGETATION IS ACHIEVED AND MAINTAINED. AREAS SHALL BE FERTILIZED AND RESEEDED AS

SEEDED AND VEGETATED AREAS SHALL BE CHECKED REGULARLY TO ENSURE THAT A GOOD STAND 7.

STREETS IN A CLEAN AND DUST-FREE CONDITION.

MUD. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO CLEAN STREETS OF MUD AND KEEP THE

ALL SITE ENTRANCE AND EXIT POINTS SHALL BE INSPECTED FOR EVIDENCE OF OFF-SITE TRACKING OF 6.

SHALL BE DISPOSED OFFSITE AT A PADEP APPROVED FACILITY.

ESTABLISHED AND THE TEMPORARY E&S CONTROLS ARE REMOVED, ALL ACCUMULATED SEDIMENTS

DISPOSED OF BY SPREADING IT ONSITE. ONCE A UNIFORM 70% PERENNIAL VEGETATIVE COVER IS

DURING CONSTRUCTION, SEDIMENT REMOVED FROM THE EROSION CONTROL DEVICES SHALL BE 5.

CONTROLS. ADDITIONAL CONTROL MEASURES SHALL BE IMPLEMENTED AS NEEDED.

ALL DISCHARGE LOCATIONS SHALL BE INSPECTED TO ASCERTAIN THE EFFECTIVENESS OF THE 4.

ALL SLOPES SHALL BE CHECKED FOR SIGNS OF EROSION AND/OR SEDIMENTATION.3.

BACKFILL MATERIAL.

FILTER SOCK. ANY EROSION OR UNDERCUTTING WILL BE REPAIRED IMMEDIATELY WITH COMPACTED

WHERE ACCUMULATIONS HAVE REACHED ONE-HALF (1/2) THE ABOVE GROUND HEIGHT OF THE

COMPOST FILTER SOCK ACCUMULATED SEDIMENTS SHALL BE REMOVED, AS REQUIRED, IN ALL CASES 2.

REPLACED BY THE END OF THE WORKING DAY.

EVENT TO MAINTAIN THEIR EFFECTIVENESS. ANY DAMAGED CONTROLS SHALL BE REPAIRED OR

ALL TEMPORARY E&S CONTROL MEASURES SHALL BE INSPECTED DAILY AND AFTER EACH RUNOFF 1.

SEEDING SCHEDULE

8/1 TO 10/15

AND

3/15 TO 6/1

1000 SY

800LBS./

1 BELOW

SEE NOTE

5 LBS./1000 SY%

15 LBS./100 SY%

30 LBS./1000 SY%

10%

30%

60%

FESCUE

RED FESCUE, OR CHEWING

TALL FESCUE, CREEPING

FORMULA D)

(PENNDOT

PERMANENT

3/15 TO 10/15

1000 SY

413 LBS./

1000 SY

207 LBS./

5-5-5 AT

10 LBS./1000 SY100%ANNUAL RYE

FORMULA E

(PENNDOT

TEMPORARY

SEEDING DATELIMING RATEFERTILIZERAPPLICATION RATE

WEIGHT

% BY

SPECIESAPPLICATION

COMPLETED IN WORK AREAS. MULCH SHALL NOT BE USED UNDER FABRIC.

EQUAL. EROSION CONTROL FABRIC SHALL BE INSTALLED IMMEDIATELY AFTER SEEDING OPERATIONS HAVE BEEN

CONTROL FABRIC OR APPROVED COVER SEEDED SLOPES WHERE THE GRADE IS 3:1 OR GREATER WITH EROSION 5.

TOPSOIL. ALL AREAS RECEIVING SEEDING SHALL HAVE A MINIMUM OF 6" OF ORGANIC 4.

S.Y.), MULCH TO BE ANCHORED WITH WOOD CELLULOSE FIBER AT 750 LBS./AC. OR EQUAL.

LBS./AC. (1240 LBS./1000 ALL SEEDED AREAS SHALL BE MULCHED WITH STRAW APPLIED AT A RATE OF 6000 3.

SPECIFICATION ITEMS OBTAINED USING PENNDOT PUBLICATION NO. 4082.

31-0-0 IBDU FERTILIZER AT 61 LBS./1000 S.Y. C.

OR

LBS./1000 S.Y.32-0-0 TO 38-0-0 SULFUR COATED UREA FERTILIZER AT 59-50 B.

OR

38-0-0 UREA FORM FERTILIZER AT 50 LBS./1000 S.Y.

AND

10-20-20 ANALYSIS COMMERCIAL FERTILIZER AT 140 LBS./1000 S.Y. A.

SHALL BE APPLIED AS FOLLOWS:

ABSENCE OF A SOIL TEST, FERTILIZER FERTILIZER SHALL BE APPLIED IN ACCORDANCE WITH A SOIL TEST. IN THE 1.

SEEDING NOTES

OF TRAVEL). MAKE MULTIPLE PASSES WITH THE CRIMPER AS NECESSARY TO SECURE THE STRAW.

USE A CRIMPER DISK (A SPECIFICALLY-DESIGNED HEAVY DISK WITH NO OFFSET TO THE DIRECTION B.

WITH A HYDROSEEDER OVER THE STRAW; OR,

APPLY 750 TO 800 POUNDS PER ACRE APPLICATION OF WOOD CELLULOSE FIBER MULCHA.

POUNDS PER ACRE. PROMPTLY TACK STRAW INTO PLACE USING ON OF THE FOLLOWING METHODS:

BALE-BUSTER OR USING A WOOD CELLULOSE FIBER (NOT PAPER PULP) HYDROMULCH AT A RATE OF 750

PROMPTLY AND EVENLY APPLY STRAW (NOT HAY) MULCH AT A RATE OF 3 TONS PER ACRE USING A 5.

PLACEMENT, USE HYDROSEEDING TECHNIQUES.

MAY BE CONSIDERED COMPLETE. IF SLOPES ARE TOO STEEP TO PERMIT SEED PREPARATION AND

AND TECHNIQUE THAT MINIMIZES RUTTING OF THE SURFACE. IF A BRILLION SEEDER IS USED, THIS STEP

LIGHTLY CULTIPACK TO PRESS SEED INTO SEEDBED USING EQUIPMENT (SUCH AS A LIGHT TRACTOR) 4.

STEP MAY BE SKIPPED.

RUN DOZER SO TRACK MARKS ARE PARALLEL TO SITE CONTOURS. IF A BRILLION SEEDER IS USED, THIS

LIGHT TRACTOR) AND TECHNIQUE THAT MINIMIZES RUTTING OF THE SURFACE. IF TRACKING IS DONE, PREPARE SEEDBED BY CULTIPACKING OR TRACKING WITH A DOZER USING EQUIPMENT (SUCH AS A3.

FERTILIZERS FOR MORE THAN ONE HOUR.

MULCH USING A HYDRO SEEDER AS LONG AS SEED AND INOCULANT IS NOT IN A SLURRY WITH

PREPARATION. ON EXTREMELY STEEP SLOPES, AMENDMENTS MAY BE APPLIED WITH THE SEED AND

SLOPES DO NOT PERMIT TILLAGE, TRACK SLOPE WITH A DOZER AS DESCRIBED UNDER SEEDBED

WHERE SLOPES PERMIT, PROMPTLY DISK ALL AMENDMENTS UNDER A 3 TO 6-INCH DEPTH. WHERE 2.

REFER TO THE SEEDING SCHEDULE FOR APPLICABLE SOIL AMENDMENTS.1.

AS FOLLOWS:

SOIL PREPARATION AND SEEDING PROCEDURES, TO BE APPLIED IN THE ORDER PRESENTED, ARE

TEMPORARY CONTROL MEASURES MAINTENANCE PROGRAM 1 5

12/18/2025

REV

NO

REVISIONS DATE BY APPD

D-9012 CADD (02-90) REVISED (04-17)

D

E C

:0

P

L O

T T

E D

CKD: MJA

HERBERT, ROWLAND & GRUBIC, INC.

220 WEST KENSINGER DRIVE

SUITE 100

CRANBERRY TOWNSHIP, PA. 16066

T-547

JEFFERSON TOWNSHIP

1-0

DES: EJT DWG: EJT

MERCER

EROSION AND SEDIMENT CONTROL NOTES

MJA

GENERAL EROSION & SEDIMENT CONTROL NOTES

RECYCLING & DISPOSAL OF WASTE MATERIAL

USED AS CLEAN FILL.

STUMPS AND VEGETATIVE MATERIAL IF THEY ARE SEPARATE FROM OTHER WASTE AND ARE

WASTE FROM LAND CLEARING, GRUBBING AND EXCAVATION, INCLUDING TREES, BRUSH,

UNCONTAMINATED SOIL, ROCK, STONE, GRAVEL, BRICK, BLOCK, CONCRETE, USED ASPHALT,

SUBSTANCES, BRICKS, BLOCK AND UNSEGREGATED CONCRETE. THIS DOES NOT INCLUDE:

STRUCTURES, INCLUDING, BUT NOT LIMITED TO: WOOD, PLASTER, METALS, ASPHALTIC

WASTE RESULTING FROM THE CONSTRUCTION OR DEMOLITION OF BUILDINGS OR OTHER

REGULATIONS § AT 25 PA. CODE 260.1 ET. SEQ., § 287.1 ET. SEQ. THIS INCLUDES SOLID

OR DISPOSED IN ACCORDANCE WITH THE DEPARTMENT'S SOLID WASTE MANAGEMENT

ALL CONSTRUCTION/DEMOLITION WASTE MUST BE REMOVED FROM THE SITE AND RECYCLED

1. ALL EARTH DISTURBANCES, INCLUDING CLEARING AND GRUBBING AS WELL AS CUTS AND FILLS

SHALL BE DONE IN ACCORDANCE WITH THE APPROVED E&S PLAN. A COPY OF THE APPROVED

DRAWINGS MUST BE AVAILABLE AT THE PROJECT SITE AT ALL TIMES.

2. AT LEAST 7 DAYS PRIOR TO STARTING ANY EARTH DISTURBANCE ACTIVITIES, INCLUDING CLEARING

AND GRUBBING, THE OWNER AND/OR OPERATOR SHALL INVITE ALL CONTRACTORS, THE

LANDOWNER, APPROPRIATE MUNICIPAL OFFICIALS, AND THE E&S PLAN PREPARER, TO AN ON-SITE

PRECONSTRUCTION MEETING.

3. AT LEAST 3 DAYS PRIOR TO STARTING ANY EARTH DISTURBANCE ACTIVITIES, OR EXPANDING INTO

AN AREA PREVIOUSLY UNMARKED, THE PENNSYLVANIA ONE CALL SYSTEM INC. SHALL BE NOTIFIED

AT 1-800-242-1776 FOR THE LOCATION OF EXISTING UNDERGROUND UTILITIES.

4. ALL EARTH DISTURBANCE ACTIVITIES SHALL PROCEED IN ACCORDANCE WITH THE SEQUENCE

PROVIDED ON THE PLAN DRAWINGS.

5. AREAS TO BE FILLED ARE TO BE CLEARED, GRUBBED AND STRIPPED OF TOPSOIL TO REMOVE TREES, VEGETATION, ROOTS AND OTHER OBJECTIONABLE MATERIAL.

6. TOPSOIL REQUIRED FOR THE ESTABLISHMENT OF VEGETATION SHALL BE STOCKPILED AT THE

LOCATION(S) SHOWN ON THE PLAN MAPS(S) IN THE AMOUNT NECESSARY TO COMPLETE THE FINISH

GRADING OF ALL EXPOSED AREAS THAT ARE TO BE STABILIZED BY VEGETATION. EACH STOCKPILE

SHALL BE PROTECTED IN THE MANNER SHOWN ON THE PLAN DRAWINGS. STOCKPILE HEIGHTS

SHALL NOT EXCEED 35 FEET. STOCKPILE SLOPES SHALL BE 2H:1V OR FLATTER.

7. IMMEDIATELY UPON DISCOVERING UNFORESEEN CIRCUMSTANCES POSING THE POTENTIAL FOR

ACCELERATED EROSION AND/OR SEDIMENT POLLUTION, THE OPERATOR SHALL IMPLEMENT

APPROPRIATE BEST MANAGEMENT PRACTICES TO MINIMIZE THE POTENTIAL FOR EROSION AND

SEDIMENT POLLUTION AND NOTIFY THE LOCAL CONSERVATION DISTRICT AND/OR THE REGIONAL

OFFICE OF THE PA DEPARTMENT OF ENVIRONMENTAL PROTECTION.

8. ALL OFF-SITE WASTE AND BORROW AREAS MUST HAVE AN E&S PLAN APPROVED BY THE LOCAL

CONSERVATION DISTRICT OR THE DEPARTMENT FULLY IMPLEMENTED PRIOR TO BEING ACTIVATED.

9. THE CONTRACTOR IS RESPONSIBLE FOR ENSURING THAT ANY MATERIAL BROUGHT ON SITE IS CLEAN

FILL. FORM FP-001 MUST BE RETAINED BY THE PROPERTY OWNER FOR ANY FILL MATERIAL

AFFECTED BY A SPILL OR RELEASE OF A REGULATED SUBSTANCE BUT QUALIFYING AS CLEAN FILL

DUE TO ANALYTICAL TESTING.

10. UNTIL THE SITE IS STABILIZED, ALL EROSION AND SEDIMENT BMPS SHALL BE MAINTAINED PROPERLY.

MAINTENANCE SHALL INCLUDE INSPECTIONS OF ALL EROSION AND SEDIMENT BMPS AFTER EACH

RUNOFF EVENT AND ON A WEEKLY BASIS. ALL PREVENTATIVE AND REMEDIAL MAINTENANCE WORK, INCLUDING CLEAN OUT, REPAIR, REPLACEMENT, REGRADING, RESEEDING, REMULCHING AND

RENETTING MUST BE PERFORMED IMMEDIATELY. IF THE E&S BMPS FAIL TO PERFORM AS EXPECTED, REPLACEMENT BMPS, OR MODIFICATIONS OF THOSE INSTALLED WILL BE REQUIRED.

11. A LOG SHOWING DATES THAT E&S BMPS WERE INSPECTED AS WELL AS ANY DEFICIENCIES FOUND

AND THE DATE THEY WERE CORRECTED SHALL BE MAINTAINED ON THE SITE AND BE MADE

AVAILABLE TO REGULATORY AGENCY OFFICIALS AT THE TIME OF INSPECTION.

12. SEDIMENT TRACKED ONTO ANY PUBLIC ROADWAY OR SIDEWALK SHALL BE RETURNED TO THE

CONSTRUCTION SITE BY THE END OF EACH WORK DAY AND DISPOSED IN THE MANNER DESCRIBED

IN THIS PLAN. IN NO CASE SHALL THE SEDIMENT BE WASHED, SHOVELED, OR SWEPT INTO ANY

ROADSIDE DITCH, STORM SEWER, OR SURFACE WATER.

13. ALL SEDIMENT REMOVED FROM BMPS SHALL BE DISPOSED OF IN THE MANNER DESCRIBED ON THE

PLAN DRAWINGS.

14. ALL FILLS SHALL BE COMPACTED AS REQUIRED TO REDUCE EROSION, SLIPPAGE, SETTLEMENT, SUBSIDENCE OR OTHER RELATED PROBLEMS. FILL INTENDED TO SUPPORT BUILDINGS, STRUCTURES

AND CONDUITS, ETC. SHALL BE COMPACTED IN ACCORDANCE WITH THE CONTRACT DOCUMENTS.

15. FILL MATERIALS SHALL BE FREE OF FROZEN PARTICLES, BRUSH, ROOTS, SOD, OR OTHER FOREIGN

OR OBJECTIONABLE MATERIALS THAT WOULD INTERFERE WITH OR PREVENT CONSTRUCTION OF

SATISFACTORY FILLS.

16. FROZEN MATERIALS OR SOFT, MUCKY, OR HIGHLY COMPRESSIBLE MATERIALS SHALL NOT BE

INCORPORATED INTO FILLS.

17. FILL SHALL NOT BE PLACED ON SATURATED OR FROZEN SURFACES.

18. SEEPS OR SPRINGS ENCOUNTERED DURING CONSTRUCTION SHALL BE HANDLED IN ACCORDANCE

WITH THE STANDARD AND SPECIFICATION FOR SUBSURFACE DRAIN OR OTHER APPROVED METHOD.

19. ALL GRADED AREAS SHALL BE PERMANENTLY STABILIZED IMMEDIATELY UPON REACHING FINISHED

GRADE. CUT SLOPES IN COMPETENT BEDROCK AND ROCK FILLS NEED NOT BE VEGETATED. SEEDED

AREAS WITHIN 50 FEET OF A SURFACE WATER, OR AS OTHERWISE SHOWN ON THE PLAN DRAWINGS, SHALL BE BLANKETED ACCORDING TO THE STANDARDS OF THE PLAN.

20. PERMANENT STABILIZATION IS DEFINED AS A MINIMUM UNIFORM, PERENNIAL 70% VEGETATIVE

COVER OR OTHER PERMANENT NON-VEGETATIVE COVER WITH A DENSITY SUFFICIENT TO RESIST

ACCELERATED EROSION. CUT AND FILL SLOPES SHALL BE CAPABLE OF RESISTING FAILURE DUE TO

SLUMPING, SLIDING, OR OTHER MOVEMENTS.

21. E&S BMPS SHALL REMAIN FUNCTIONAL AS SUCH UNTIL ALL AREAS TRIBUTARY TO THEM ARE

PERMANENTLY STABILIZED OR UNTIL THEY ARE REPLACED BY ANOTHER BMP APPROVED BY THE

LOCAL CONSERVATION DISTRICT OR THE PA DEPARTMENT OF ENVIRONMENTAL PROTECTION.

22. FAILURE TO CORRECTLY INSTALL E&S BMPS, FAILURE TO PREVENT SEDIMENT-LADEN RUNOFF FROM

LEAVING THE CONSTRUCTION SITE, OR FAILURE TO TAKE IMMEDIATE CORRECTIVE ACTION TO

RESOLVE FAILURE OF E&S BMPS MAY RESULT IN ADMINISTRATIVE, CIVIL, AND/OR CRIMINAL

PENALTIES BEING INSTITUTE BY THE DEPARTMENT AS DEFINED IN SECTION 602 OF THE

PENNSYLVANIA CLEAN STREAMS LAW. THE CLEAN STREAMS LAW PROVIDES FOR UP TO $10,000

PER DAY IN CIVIL PENALTIES, UP TO $10,000 IN SUMMARY CRIMINAL PENALTIES, AND UP TO

$25,000 IN MISDEMEANOR CRIMINAL PENALTIES FOR EACH VIOLATION.

23. CONCRETE WASH WATER SHALL BE HANDLED IN THE MANNER DESCRIBED ON THE PLAN DRAWINGS.

IN NO CASE SHALL IT BE ALLOWED TO ENTER ANY SURFACE WATERS OR GROUNDWATER SYSTEMS.

24. ALL CHANNELS SHALL BE KEPT FREE OF OBSTRUCTIONS INCLUDING BUT NOT LIMITED TO FILL, ROCKS, LEAVES, WOODY DEBRIS, ACCUMULATED SEDIMENT, EXCESS VEGETATION, AND

CONSTRUCTION MATERIAL/WASTES.

25. UNDERGROUND UTILITIES CUTTING THROUGH ANY ACTIVE CHANNEL SHALL BE IMMEDIATELY

BACKFILLED AND THE CHANNEL RESTORED TO ITS ORIGINAL CROSS-SECTION AND PROTECTIVE

LINING. ANY BASE FLOW WITHIN THE CHANNEL SHALL BE CONVEYED PAST THE WORK AREA IN THE

MANNER DESCRIBED IN THIS PLAN UNTIL SUCH RESTORATION IS COMPLETE.

Rh - RED HOOK SILT LOAM, LOW TERRACE

SUBSURFACE DRAIN OR OTHER APPROVED METHOD. FOR

SPECIFICATION WITH THE STANDARD AND ACCORDANCE IN HANDLED

BE SEEPS OR SPRINGS ENCOUNTERED DURING CONSTRUCTION SHALL 7.

SURFACES. FILL SHALL NOT BE PLACED ON SATURATED OR FROZEN 6.

MATERIALS SHALL NOT BE INCORPORATED INTO FILLS.

FROZEN MATERIALS OR SOFT, MUCKY, OR HIGHLY COMPRESSIBLE 5.

SATISFACTORY FILLS.

THAT WOULD INTERFERE WITH OR PREVENT CONSTRUCTION OF

FOREIGN OR OBJECTIONABLE MATERIALS OTHER OR ROOTS, SOD,

FILL MATERIALS SHALL BE FREE OF FROZEN PARTICLES, BRUSH, 4.

TO EXCEED 9 INCHES IN THICKNESS.

NOT ALL EARTHEN FILLS SHALL BE PLACED IN COMPACTED LAYERS 3.

REQUIREMENTS OR CODES.

ACCORDANCE WITH LOCAL BE COMPACTED IN SHALL ETC. CONDUITS,

AND BUILDINGS, STRUCTURES, SUPPORT TO INTENDED FILL

PROBLEMS. SUBSIDENCE OR OTHER RELATED SLIPPAGE, SETTLEMENT,

EROSION, ALL FILLS SHALL BE COMPACTED AS REQUIRED TO REDUCE 2.

OBJECTIONABLE MATERIAL.

REMOVE TREES, VEGETATION, ROOTS, AND OTHER TO TOPSOIL OF

STRIPPED AREAS TO BE FILLED ARE TO BE CLEARED, GRUBBED, AND 1.

SOILS LEGEND

SOILS LIMITATIONS NOTES

SOIL LIMITATIONS

SOIL NAME

C U

T B

A C

K S

C A

V E

C O

R R

O S

IV

E

T O

C O

N C

R E

T E

S

T E

E L

D R

O U

G H

T Y

E A

S

IL

Y E

R O

D

IB

L E

F L

O O

D

IN

G

S E

A S

O N

A L

H

IG

H W

A T

E R

T A

B L

E

D E

P T

H T

O S

A T

U R

A T

E D

Z O

N E

H Y

D R

IC

\H

Y D

R

IC

I N

C L

U S

IO

N

S

P R

O N

E

L O

W S

T R

E N

G T

H

L A

N D

S L

ID

E

S L

O W

P E

R C

O L

A T

IO

N

P

IP

IN

G

P O

O R

S O

U R

C E

O F

T O

P S

O

IL

F R

O S

T A

C T

IO

N

S H

R

IN

K -S

W E

L L

P O

T E

N T

IA

L

S

IN

K H

O L

E

P O

N D

IN

G

W E

T N

E

COMBINATION OF THESE AND/OR OTHER METHODS.

TO ANOTHER SOIL TYPE, IMPORT OTHER SOILS FOR THESE FACILITIES, OR IMPLEMENT

LOCATE FACILITIES THAT MAY BE SUSCEPTIBLE TO DAMAGE FROM SHRINK OR SWELLING

SHRINK-SWELL

PRONE TO FROST, OR IMPLEMENT COMBINATIONS OF THESE AND/OR OTHER METHODS.

FACILITIES ON OTHER SOIL TYPES, DO NOT CONSTRUCT EMBANKMENTS DURING PERIODS

WATER RETENTION BASINS AND STORM WATER DETENTION BASINS, LOCATE THOSE

IMPORT OTHER SOIL FOR EMBANKMENTS OF SEDIMENT BASINS, SEDIMENT TRAPS, STORM

FROST ACTION

TOPSOIL AND STOCKPILE THESE FOR USE DURING RESTORATION.

AND APPLICATION RATES. IDENTIFY SOILS ON-SITE THAT ARE ADEQUATE SOURCES OF

AS TOPSOIL. PERFORM SOIL TESTS TO DETERMINE THE REQUIRED SOIL AMENDMENTS

IDENTIFY AND RESOLVE CHARACTERISTICS THAT RENDER THE SOIL TYPES POORLY SUITED

TOPSOIL

POOR SOURCE OF

COMBINATIONS OF THESE AND/OR OTHER METHODS.

FACILITIES ON OTHER SOIL TYPES, LIMIT EMBANKMENT SLOPE STEEPNESS, OR IMPLEMENT

WATER RETENTION BASINS AND STORM WATER DETENTION BASINS, LOCATE THOSE

IMPORT OTHER SOIL FOR EMBANKMENTS OF SEDIMENT BASINS, SEDIMENT TRAPS, STORM

PIPING

SUCH AS COMPOST AT THOSE LOCATIONS.

TRAFFIC AT THOSE LOCATIONS, TILL SOIL IN THOSE LOCATIONS, ADD SOIL AMENDMENTS

LOCATE INFILTRATION FACILITIES TO ANOTHER SOIL TYPE, RESTRICT CONSTRUCTION

SLOW PERCOLATION

IMPLEMENT A COMBINATION OF THESE AND/OR OTHER METHODS.

FOR CUT/FILL SLOPES, REDUCE SLOPE, INSTALL EROSION CONTROL MATTING, OR

CONSTRUCTION, OR IMPLEMENT A COMBINATION OF THESE AND/OR OTHER METHODS.

LOCATE ROADWAYS TO OTHER SOIL TYPES, IMPORT OTHER SOILS FOR THESE ROADWAY

LANDSLIDE PRONE

LOW STRENGTH \

WATER FILTER BAGS TO DEWATER DISTURBED ARES DURING CONSTRUCTION.

OR IMPLEMENT COMBINATIONS OF THESE AND/OR OTHER METHODS. UTILIZE PUMPED

SELECT VEGETATIVE SPECIES TOLERANT TO WET CONDITIONS, TILE VEGETATED AREAS,

SOILS

WETNESS & HYDRIC

WATER TABLE,

ZONE, SEASONAL HIGH

DEPTH TO SATURATED

AND/OR OTHER METHODS.

PERMANENT LININGS OTHER THAN GRASSES, OR IMPLEMENTING COMBINATIONS OF THESE

INCREASE CHANNEL WIDTH, SELECT VEGETATION WITH A GREATER RETARDANCE, SELECT

PROVIDE TEMPORARY OR PERMANENT CHANNEL LINING, DECREASE CHANNEL GRADE,

EASILY ERODIBLE

AREAS, OR IMPLEMENT COMBINATIONS OF THESE AND/OR OTHER METHODS.

SELECT VEGETATIVE SPECIES TOLERANT TO DRY CONDITIONS, IRRIGATE VEGETATED

DROUGHTY

OTHER METHODS.

MATERIALS IN LIEU OF CONCRETE OR STEEL, OR A COMBINATION OF THESE AND OR

PROTECT CONCRETE AND STEEL WITH PROTECTIVE COATINGS, SELECT ALTERNATIVE

CONCRETE OR STEEL

CORROSIVE TO

MATS, BONDED FIBER MATRIX, OR A COMBINATION OF THESE AND/OR OTHER METHODS.

TRENCHING. STABILIZE BANKS IMMEDIATELY WITH SEED, MULCH, EROSION CONTROL

CONDUCT TRENCHING OPERATIONS IN ACCORDANCE WITH OSHA TECHNICAL MANUAL FOR

CUTBANKS CAVE

RESOLUTIONLIMITATION

SOIL LIMITATION RESOLUTIONS

RED HOOK X X X X X X X XC/S

X

REV

NO

REVISIONS DATE BY APPD

D-9012 CADD (02-90) REVISED (04-17)

D

E C

:4

P

L O

T T

E D

CKD: MJA

HERBERT, ROWLAND & GRUBIC, INC.

220 WEST KENSINGER DRIVE

SUITE 100

CRANBERRY TOWNSHIP, PA. 16066

T-547

JEFFERSON TOWNSHIP

1-0

DES: EJT DWG: EJT

6MERCER

N81°14'27"E

11 12

P

P

EROSION AND SEDIMENT CONTROL PLAN

PROPOSED LEGEND

1000 EXISTING CONTOUR

LOD LIMITS OF DISTURBANCE

SOIL BOUNDARY / SOIL TYPE

PROPOSED COFFERDAM

P

PUMP

PUMP WATER FILTER BAG

CONCRETE WASHOUT

TOPSOIL LOCATIONPROPOSED RIP RAP

Rh

3 5

LIMIT OF DISTURBANCE (TYP.)

COFFERDAM (TYP.)

PUMPED WATER FILTER BAG

CONCRETE WASHOUT

STOCKPILE

TOPSOIL T-547 (HASSEL ROAD)

STA 12+25.00

LIMIT OF WORK

T-547 (HASSEL ROAD)

STA 11+00

LIMIT OF WORK

CONDITIONS WHILE PLACING RIP RAP SCOUR PROTECTION.

CONTRACTOR IS TO PLACE AND RELOCATE PUMP AS NECESSARY TO MAINTAIN DRY WORKING

PUMPED WATER FILTER BAG TO BE USED TO DEWATER WORK AREA BEHIND COFFERDAM.

NOTE:

5 0 5 10 FEET

SCALE

Rh

REV

NO

REVISIONS DATE BY APPD

D-9012 CADD (02-90) REVISED (04-17)

D

E C

:4

P

L O

T T

E D

CKD: MJA

HERBERT, ROWLAND & GRUBIC, INC.

220 WEST KENSINGER DRIVE

SUITE 100

CRANBERRY TOWNSHIP, PA. 16066

T-547

JEFFERSON TOWNSHIP

1-0

DES: EJT DWG: EJT

MERCER

TOPSOIL/DEBRIS

STOCKPILE

EXISTING GROUND

NOT TO SCALE

TOPSOIL/ DEBRIS STOCKPILE DETAIL

INSTALL COMPOST FILTER SOCK

AROUND ENTIRE STOCKPILE

2 BAG MINIMUM HEIGHT ABOVE BASE FLOW

STACKED SANDBAGS OPTION

NOT TO SCALE

SANDBAG DIVERSION DAM OR COFFERDAM

SANDBAGS

IMPERVIOUS MEMBRANE

FLOW ELEVATION

NORMAL STREAM

CLAMPS

FILTER BAG

THE FOLLOWING STANDARDS:

THAN 150 MICRONS. HIGH VOLUME FILTER BAGS SHALL BE MADE FROM WOVEN GEOTEXTILES THAT MEET

STRENGTH, DOUBLE STITCHED "J" TYPE SEAMS. THEY SHALL BE CAPABLE OF TRAPPING PARTICLES LARGER

LOW VOLUME FILTER BAGS SHALL BE MADE FROM NON-WOVEN GEOTEXTILE MATERIAL SEWN WITH HIGH

NOTES:

IMMEDIATELY AND NOT RESUME UNTIL THE PROBLEM IS CORRECTED.

FILTER BAGS SHALL BE INSPECTED DAILY. IF ANY PROBLEM IS DETECTED, PUMPING SHALL CEASE

MANUFACTURER, WHICHEVER IS LESS. PUMP INTAKES SHALL BE FLOATING AND SCREENED.

THE PUMPING RATE SHALL BE NO GREATER THAN 750 GPM OR 1/2 THE MAXIMUM SPECIFIED BY THE

MANUFACTURER AND SECURELY CLAMPED. A PIECE OF PVC PIPE IS RECOMMENDED FOR THIS PURPOSE.

THE PUMP DISCHARGE HOSE SHALL BE INSERTED INTO THE BAGS IN THE MANNER SPECIFIED BY THE

ANY RECEIVING SURFACE WATER OR WHERE GRASSY AREA IS NOT AVAILABLE.

FILTER SOCK SHALL BE INSTALLED BELOW BAGS LOCATED IN HQ OR EV WATERSHEDS, WITHIN 50 FEET OF

NO DOWNSLOPE SEDIMENT BARRIER IS REQUIRED FOR MOST INSTALLATIONS. COMPOST BERM OR COMPOST

STEEPNESS.

NON-ERODIBLE AND NON-POLLUTING MATERIAL MAY BE PLACED UNDER THE BAG TO REDUCE SLOPE

NOT BE PLACED ON SLOPES GREATER THAN 5%. FOR SLOPES EXCEEDING 5%, CLEAN ROCK OR OTHER

BE PROVIDED. BAGS MAY BE PLACED ON FILTER STONE TO INCREASE DISCHARGE CAPACITY. BAGS SHALL

RESISTANT AREAS. WHERE THIS IS NOT POSSIBLE, A GEOTEXTILE UNDERLAYMENT AND FLOW PATH SHALL

BAGS SHALL BE LOCATED IN WELL-VEGETATED (GRASSY) AREA, AND DISCHARGE ONTO STABLE, EROSION

ALREADY ATTACHED.

SHALL BE PLACED ON STRAPS TO FACILITATE REMOVAL UNLESS BAGS COME WITH LIFTING STRAPS

BAGS SHALL BE KEPT AVAILABLE FOR REPLACEMENT OF THOSE THAT HAVE FAILED OR ARE FILLED. BAGS

BE PROVIDED. FILTER BAGS SHALL BE REPLACED WHEN THEY BECOME 1/2 FULL OF SEDIMENT. SPARE

A SUITABLE MEANS OF ACCESSING THE BAG WITH MACHINERY REQUIRED FOR DISPOSAL PURPOSES SHALL

80 SIEVEASTM D-4751AOS % RETAINED

70%ASTM D-4355UV RESISTANCE

350 PSIASTM D-3786MULLEN BURST

110 LBASTM D-4833PUNCTURE

205 LBASTM D-4632GRAB TENSILE

60 LB/INASTM D-4884AVG. WIDE WIDTH STRENGTH

MINIMUM STANDARDTEST METHODPROPERTY

PLAN VIEW

(RECOMMENDED)

STRAPS

HEAVY DUTY LIFTING

PUMP

INTAKE HOSE

WELL VEGETATED, GRASSY AREA

HOSE

DISCHARGE

FILTER BAG

DISCHARGE HOSE

CLAMPS

INTAKE HOSE

PUMP

ELEVATION VIEW

WELL VEGETATED, GRASSY AREA

GRADE

EXISTING

ACCEPTABLE TO ENGINEER AND OWNER.

ALTERNATIVE COFFERDAMS MAY BE UTILIZED BY CONTRACTOR IF 2.

MATERIALS AND CONSTRUCTION REQUIREMENTS.

CONTRACTOR SHALL BE RESPONSIBLE FOR SELECTION OF COFFERDAM 1.

NOTES

25' DIAMETER

PLAN VIEW

24" DIA. COMPOST FILTER

SOCK. 4' MIN. OVERLAP ON

UPSLOPE SIDE OF FILTER RING

2"x2"x36" WOODEN

STAKES PLACED 5' O.C.

DIRECT CONCRETE

WASHOUT WATER INTO

FILTER RING

A

A

MAXIMUM DEPTH OF

CONCRETE WASHOUT

FILTER RING HEIGHT

24" DIA. COMPOST

FILTER SOCK

2"x2"x36"

WOODEN STAKES

PLACED 5' O.C.

M

I N

SECTION A-A

CONCRETE WASH-OUT DETAIL

NOT TO SCALE

NOTES:

1. PROVIDE PROPER SIGNAGE FOR CONCRETE DELIVERY VEHICLE DRIVERS SO THAT THEY

ARE AWARE OF THE PRESENCE OF WASHOUT FACILITIES.

2. WASHOUT FACILITIES SHOULD NOT BE PLACED WITHIN 50' OF STORM DRAINS, OPEN

DITCHES, OR SURFACE WATERS. UNDER NO CIRCUMSTANCES SHOULD WASH WATER BE

ALLOWED TO ENTER ANY SURFACE WATERS.

3. WHEREVER POSSIBLE, CONCRETE WASHOUTS SHOULD BE LOCATED ON SLOPES NOT

4. A SUITABLE IMPERVIOUS GEOMEMBRANE SHOULD BE PLACED AT THE LOCATION OF THE

WASHOUT. COMPOST SOCKS SHOULD BE STAKED IN THE MANNER RECOMMENDED BY THE

MANUFACTURER AROUND PERIMETER OF THE GEOMEMBRANE SO AS TO FORM A RING

WITHIN THE ENDS OF THE SOCK LOCATED AT THE UPSLOPE CORNER. CARE MUST BE

TAKEN TO ENSURE CONTINUOUS CONTACT OF THE SOCK WITH THE GEOMEMBRANE AT

ALL LOCATIONS. WHERE NECESSARY, 18" SOCKS MAY BE STACKED ONTO 24" SOCKS

AND STAKED SO AS TO FORM A TRIANGULAR CROSS SECTION.

GEOMEMBRANE

NOT TO SCALE

PUMPED WATER FILTER BAG

EROSION AND SEDIMENT CONTROL DETAILS

DISTRICT COUNTY ROUTE SECTION SHEET

OF

REV

NO

REVISIONS DATE BY APPD

D-9012 CADD (02-90) REVISED (04-17)

D

E C

:4

P

L O

T T

E D

HERBERT, ROWLAND & GRUBIC, INC.

220 WEST KENSINGER DRIVE

SUITE 100

CRANBERRY TOWNSHIP, PA. 16066

T-547

JEFFERSON TOWNSHIP

1-0

DES: EJT DWG: EJT

MERCER

DISTRICT COUNTY ROUTE SECTION SHEET

OF

REV

NO

REVISIONS DATE BY APPD

D-9012 CADD (02-90) REVISED (04-17)

D

E C

:4

P

L O

T T

E D

HERBERT, ROWLAND & GRUBIC, INC.

220 WEST KENSINGER DRIVE

SUITE 100

CRANBERRY TOWNSHIP, PA. 16066

T-547

JEFFERSON TOWNSHIP

1-0

DES: EJT DWG: EJT

MERCER

REV

NO

REVISIONS DATE BY APPD

D-9012 CADD (02-90) REVISED (04-17)

D

E C

:5

P

L O

T T

E D

CKD: MJA

HERBERT, ROWLAND & GRUBIC, INC.

220 WEST KENSINGER DRIVE

SUITE 100

CRANBERRY TOWNSHIP, PA. 16066

T-547

JEFFERSON TOWNSHIP

1-0

DES: EJT DWG: EJT

6MERCER

F L

O W

F L

O W

DISTURBED AREA

UNDISTURBED AREA

SECTION

PLAN VIEW

DISTURBED AREA UNDISTURBED AREA

MESH SHALL BE CUT OPEN AND THE MULCH SPREAD AS A SOIL SUPPLEMENT.

THE SOCK MAY BE LEFT IN PLACE AND VEGETATED OR REMOVED. IN THE LATTER CASE, THE

UPON STABILIZATION OF THE AREA TRIBUTARY TO THE SOCK, STAKES SHALL BE REMOVED.

S RECOMMENDATIONS.’ACCORDING TO MANUFACTURER

PHOTODEGRADABLE SOCKS AFTER 1 YEAR. POLYPROPYLENE SOCKS SHALL BE REPLACED

BIODEGRADABLE COMPOST FILTER SOCKS SHALL BE REPLACED AFTER 6 MONTHS;

REPLACED WITHIN 24 HOURS OF INSPECTION.

S SPECIFICATIONS OR ’DAMAGED SOCKS SHALL BE REPAIRED ACCORDING TO MANUFACTURER

COMPOST FILTER SOCKS SHALL BE INSPECTED WEEKLY AND AFTER EACH RUNOFF EVENT.

PLAN.

HEIGHT OF THE BARRIER AND DISPOSED IN THE MANNER DESCRIBED ELSEWHERE IN THE

ACCUMULATED SEDIMENT SHALL BE REMOVED WHEN IT REACHES 1/2 THE ABOVE GROUND

TRAFFIC SHALL NOT BE PERMITTED TO CROSS COMPOST FILTER SOCKS.

THAT SPECIFIED FOR THE SIZE OF THE SOCK AND THE SLOPE OF ITS TRIBUTARY AREA.

BARRIER ALIGNMENT. MAXIMUM SLOPE LENGTH ABOVE ANY BARRIER SHALL NOT EXCEED

BARRIER SHALL BE EXTENDED AT LEAST 8 FEET UP SLOPE AT 45 DEGREES TO THE MAIN

COMPOST FILTER SOCK SHALL BE PLACED AT EXISTING LEVEL GRADE. BOTH ENDS OF THE

CONTROL MANUAL.

MANUAL. COMPOST SHALL MEET THE STANDARDS OF TABLE 4.2 OF THE PA DEP EROSION

SOCK FABRIC SHALL MEET STANDARDS OF TABLE 4.1 OF THE PA DEP EROSION CONTROL

NOTES:

COMPOST FILTER SOCK

FILTER MEDIA

BLOWN/PLACED

PLACED 10 FT ON CENTER

2 IN. x 2 IN. WOODEN STAKES

CONTOURS

EXISTING

SOCK

FILTER

COMPOST PLACED 10 FT ON CENTER

2 IN. x 2 IN. WOODEN STAKES

M

IN

COMPOST FILTER SOCK DETAIL

NOT TO SCALE

STAPLE PATTERN GUIDE

E

DC

BA

1.2 STAPLES PER SY0.7 STAPLES PER SY

3.5 STAPLES PER SY1.75 STAPLES PER SY

3.8 STAPLES PER SY

1 1/2'

3'

3'

3'

20"

10"

20"

RECOMMENDATIONS.

SITE CONDITIONS. CONSULT MANUFACTURER FOR SPECIFIC

INCREASED STAPLE RATES MAY BE NECESSARY DEPENDING UPON 2.

AN ALTERNATE MATTING BE USED.

MATTING ONLY. CONSULT MANUFACTURER FOR PATTERN SHOULD

STAPLE PATTERN INDICATED IS FOR USE WITH SPECIFIED 1.

NOTES

NOT TO SCALE

2 YEARS1 YEAR6 MONTHS9 MONTHS6 MONTHS

LOGEVITY

MINIMUM FUNCTIONAL

100% @ 1000 HRS100% @ 1000 HRS-23% @ 1000 HRS23% @ 1000 HRS

(ASTM G-155)

ORIGINAL STRENGTH

ULTRAVIOLET STABILITY %

202 PSI44 PSI26 PSI26 PSI-TENSILE STRENGTH

1/8"3/8"3/8"3/8"3/8"MESH OPENING

32"

24"

18"

12"

32"

24"

18"

12"

32"

24"

18"

12"

32"

24"

18"

12"

18"

12"

DIAMETERS

SOCK

PHOTO-DEGRADABLEPHOTO-DEGRADABLEBIO-DEGRADABLEPHOTO-DEGRADABLEPHOTO-DEGRADABLE

CHARACTERISTICS

MATERIAL

SOCK FABRICS COMPOSED OF BURLAP MAY BE USED ON PROJECTS LASTING 6 MONTHS OR LESS.

3/16" MAX. APERTURE SIZE

VIA NEEDLE PUMCH)

(WOVEN LAYER AND NON-WOVEN FLEECE MECHANICALLY FUSED

COMPOSITE POLYPROPYLENE FABRIC

OUTER FILTRATION MESH

3/4"x3/4" MAX. APERTURE SIZE

FUSION-WELDED JUNCTURES

CONTINUOUSLY WOUND

HDPE BIAXIAL NET

INNER CONTAINMENT NETTING

TWO-PLY SYSTEMS

(MFPP)

POLYPROPYLENE

MULTI-FILAMENT

HEAVY DUTY

(MFPP)

POLYPROPYLENE

MULTI-FILAMENT

5 MIL HDPE5 MIL HDPE3 MIL HDPEMATERIAL TYPE

COMPOST SOCK FABRIC MINIMUM SPECIFICATIONS

5.0 dS/m (mmhos/cm) MAX.SOLUBLE SALT CONCENTRATION

SIEVE

30% - 50% PASS THROUGH 3/8"

PARTICLE SIZE

30% - 60%MOISTURE CONTENT

5.5 - 8.5pH

FIBROUS AND ELONGATEDORGANIC PORTION

25% - 100% (DRY WEIGHT BASIS)ORGANIC MATTER CONTENT

COMPOST STANDARDS

EROSION CONTROL MULCH BLANKET INSTALLATION

NOT TO SCALE

AND STAPLED.

OVERLAPPED 4" (MIN.)

BLANKET EDGES

FLOW

IN DIRECTION OF WATER

SLOPE, ROLL BLANKETS

STARTING AT TOP OF

COMPACT SOIL.

STAPLE, BACKFILL AND

IN 6" x 6" ANCHOR TRENCH, INSTALL BEGINNING OF ROLL

OF BLANKET.

PRIOR TO INSTALLATION

FERTILIZER, & SEED)

APPLICATION OF LIME,

(INCLUDING

PREPARE SEED BED

BLANKETED.

LENGTH OF SLOPE BEING

PATTERN FOR STEEPNESS AND

RECOMMENDED STAPLING

REFER TO MANUFACTURER'S

STAPLE SECURELY.

DOWNSLOPE BLANKET (SHINGLE STYLE).

UPSLOPE BLANKET OVERLYING THE

OVERLAP BLANKET ENDS 6" (MIN.) WITH THE

CONTACT.

MAINTAIN GOOD SOIL

BE STRETCHED; IT MUST

THE BLANKET SHOULD NOT

RESTORED OR REPLACED WITHIN 4 CALENDAR DAYS.

THROUGHOUT THE BLANKETED AREA. DAMAGED OR DISPLACED BLANKETS SHALL BE

UNTIL PERENNIAL VEGETATION IS ESTABLISHED TO A MINIMUM UNIFORM 70% COVERAGE

BLANKETED AREAS SHALL BE INSPECTED WEEKLY AND AFTER EACH RUNOFF EVENT 6.

RECOMMENDATIONS.

THE BLANKET SHALL BE STAPLED IN ACCORDANCE WITH MANUFACTURER'S 5.

MAINTAIN DIRECT CONTACT WITH SOIL. DO NOT STRETCH BLANKET.

THROUGHOUT ENTIRE LENGTH. LAY BLANKET LOOSELY AND STAKE OR STAPLE TO

BLANKET SHALL HAVE GOOD CONTINUOUS CONTACT WITH UNDERLYING SOIL 4.

SLOPE SURFACE SHALL BE FREE OF ROCKS, CLODS, STICKS, AND GRASS.3.

SLOPE.

PROVIDE ANCHOR TRENCH AT TOE OF SLOPE IN SIMILAR FASHION AS AT TOP OF 2.

PLAN DRAWINGS PRIOR TO INSTALLING THE BLANKET.

SEED AND SOIL AMENDMENTS SHALL BE APPLIED ACCORDING TO THE RATES IN THE 1.

NOTES

5 5

EROSION AND SEDIMENT CONTROL DETAILS

01 - T0033660447ESC_GN
02 - T0033660447ESC_GN
03 - T0033660447ESC_PL
04 - T0033660447ESC_DT
05 - T0033660447ESC_DT

File details come from the government source that posted it. Updated .