This is an official bid results spreadsheet for the State of Utah Division of Purchasing, Department of Natural Resources, documenting the competitive bids received for the Tom Patterson Phase I Bullhog project. The solicitation sought Bullhog Services from prequalified contractors only, with a single contract award anticipated to the lowest cost responsive and responsible vendor. The project consists of one line item (Item #1-1 Bullhog Services) with a quantity of 702 units. No mandatory site visit was required for this invitation for bid. The project must be completed no later than November 30, 2026, and vendors were required to guarantee their pricing through project completion.

Six contractors submitted bids for the Bullhog Services contract: DRD Forestry, England Construction, Hall's HammerTime Construction LLC, Kolob Mountain Construction LLC, Razr Bak Restoration, and Wilkinson Construction Company. The unit prices ranged from $410.00 to $658.00 per unit, with total contract costs spanning from $287,820.00 to $461,916.00. DRD Forestry submitted the lowest responsive bid at $410.00 per unit for a total contract cost of $287,820.00 and was awarded the contract. The contract is subject to a fixed-price structure with vendor responsibility to maintain guaranteed pricing throughout the project performance period ending November 30, 2026.

View the file

Other files

File Type Posted
TomPattersonPhaseI.shp —
TomPattersonPhaseI.cpg —
2-Vendor Prerequisites - IFB Agency.pdf PDF
8-KL27-102 Bids - Unofficial.xlsx XLSX spreadsheet
TomPattersonPhaseI.shp.xml XML file
TomPattersonPhaseI.shx —
3-Att.-A-PO-Terms-and-Conditions (5).docx DOCX document
TomPattersonPhaseI.dbf DBF file
5-Tom Patterson Phase I Treatment Map.pdf PDF
TomPattersonPhaseI.sbn —
1-Contract Performance Evaluation FOR REFERENCE USE ONLY.pdf PDF
TomPattersonPhaseI.sbx —
TomPattersonPhaseI.prj —
TomPattersonPhaseI_KMZ.kmz KMZ file
6-Tom Patterson Phase I Treatment Map2.pdf PDF
7-Attachment B - Scope of Work.docx DOCX document
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet 1

DRD ForestryEngland ConstructionHall's HammerTime Construction LLCKolob Mountain Construction LLCRazr Bak RestorationWilkinson Construction Company
Total Cost$287,820.00$403,650.00$337,325.04$461,916.00$339,066.00$345,384.00
#ItemsQuantity
RequiredUnit

of

MeasurementUnit
PriceTotal
CostUnit
PriceTotal
CostUnit
PriceTotal
CostUnit
PriceTotal
CostUnit
PriceTotal
CostUnit
PriceTotal

Cost

Basket 1: Totals$287,820.00$403,650.00$337,325.04$461,916.00$339,066.00$345,384.00
#1-1Bullhog Services702Enter unit of measurement$410.00$287,820.00$575.00$403,650.00$480.52$337,325.04$658.00$461,916.00$483.00$339,066.00$492.00$345,384.00
AWARDED