This is a bid tabulation document for an Invitation for Bid (IFB) issued by the State of Utah Division of Purchasing on behalf of the Department of Natural Resources for Bullhog Services related to the Tom Patterson Phase I project. The solicitation is limited to prequalified contractors only and requests a single service line item: Bullhog Services with a quantity of 702 units. The project must be completed no later than November 30, 2026, with vendors required to guarantee pricing through project completion. No mandatory site visit or bidders' conference was specified for this procurement.

Six contractors submitted bids for this project: DRD Forestry England Construction ($287,820.00), Hall's HammerTime Construction LLC ($403,650.00), Kolob Mountain Construction LLC ($337,325.04), Razr Bak Restoration ($461,916.00), Wilkinson Construction Company ($339,066.00), and an unnamed sixth bidder ($345,384.00). The bids ranged from a low unit price of $410.00 per unit to a high of $658.00 per unit. DRD Forestry England Construction submitted the lowest total cost proposal at $287,820.00, which equates to a unit price of $410.00 per unit of service. The contract is anticipated to be awarded to the lowest cost responsive and responsible vendor.

View the file

Other files

File Type Posted
TomPattersonPhaseI.dbf DBF file
TomPattersonPhaseI.shp —
TomPattersonPhaseI.cpg —
2-Vendor Prerequisites - IFB Agency.pdf PDF
TomPattersonPhaseI.shp.xml XML file
9-KL27-102 Bids - Official.xlsx XLSX spreadsheet
TomPattersonPhaseI.shx —
3-Att.-A-PO-Terms-and-Conditions (5).docx DOCX document
5-Tom Patterson Phase I Treatment Map.pdf PDF
TomPattersonPhaseI.sbn —
1-Contract Performance Evaluation FOR REFERENCE USE ONLY.pdf PDF
TomPattersonPhaseI.sbx —
TomPattersonPhaseI.prj —
TomPattersonPhaseI_KMZ.kmz KMZ file
6-Tom Patterson Phase I Treatment Map2.pdf PDF
7-Attachment B - Scope of Work.docx DOCX document
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet 1

DRD ForestryEngland ConstructionHall's HammerTime Construction LLCKolob Mountain Construction LLCRazr Bak RestorationWilkinson Construction Company
Total Cost$287,820.00$403,650.00$337,325.04$461,916.00$339,066.00$345,384.00
#ItemsQuantity
RequiredUnit

of

MeasurementUnit
PriceTotal
CostUnit
PriceTotal
CostUnit
PriceTotal
CostUnit
PriceTotal
CostUnit
PriceTotal
CostUnit
PriceTotal

Cost

Basket 1: Totals$287,820.00$403,650.00$337,325.04$461,916.00$339,066.00$345,384.00
#1-1Bullhog Services702Enter unit of measurement$410.00$287,820.00$575.00$403,650.00$480.52$337,325.04$658.00$461,916.00$483.00$339,066.00$492.00$345,384.00