Annex_1_to_RBH_Final_Drawing_(6_SEP_18).pdf

PDF 339 KB Posted

Attached to
CCTV Security System Services
Solicitation number
70Z08418QBB700800
Issued by

About this file

Annex 1 RBH Final Drawing

View the file

Other files

File Type Posted
A0004.docx DOCX document
RBH_CCTV_Drawing_Final_(6_SEP_18)(2).pdf PDF
SSJ_Drawing_Final_(6_SEP_18).pdf PDF
Annex_1_to_SSJ_(La_Puntilla)_Final_Drawing_(6_SEP_18).pdf PDF
Annex_1_to_SSJ_(La_Puntilla)_Drawing_(6_SEP_18).docx.pdf PDF
A0003.docx DOCX document
RBH_CCTV_Drawing_(6_SEP_18).ppt PPT presentation
Attachment_1_revised_Sector_San_Juan.docx DOCX document
Annex_1_to_RBH_Drawing_(6_SEP_18).pdf PDF
Revised_Pgs_6_and_8_of_RFQ.docx DOCX document
Attachment_2__revised_Rio_Bayamon_Housing.docx DOCX document
SSJ_Drawing_(6_SEP_18).pdf PDF
SSJ_Drawing_rev__(4_SEP_18).pdf PDF
Q_and_R_document_dtd_5_Sept_2018.docx DOCX document
Annex_1_to_RBH_revised_Drawing_(4_SEP_18).pdf PDF
Annex_1_to_SSJ_(La_Puntilla)_revised_Drawing_(4_SEP_18).pdf PDF
RBH_CCTV_revised_Drawing_(4_SEP_18).pdf PDF
Q_and_R_document_dtd_4_Sept_2018.docx DOCX document
A0002.docx DOCX document
Drawings.pdf PDF
A0001.docx DOCX document
Solicitation_dtd_24_August_2018.doc DOC document
Past_Performance_Work_Sheet.docx DOCX document
Attachment_1_Sector_San_Juan.docx DOCX document
Attachment_2__Rio_Bayamon_Housing.docx DOCX document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Annex 1, to RBH Camera Placement Drawing (6 SEP 18)

One PDZ Camera on Existing pole (Outside Main Gate)(Total Camera = 1ea)

One Fixed Camera mounted in Short pole in Front of gate house (outside entry gate)(Total

Camera = 1ea)

One Fixed Cameras in Main Gate (mounted on walls in the main gate entrance and exit)(Total

Cameras = 2ea)

Fixed cameras on existing Pole (2 Cameras per pole)(Total Cameras = 16ea)

Fixed camera on existing pole (Building M and Perimeter Corner Pole #18.)(Total Cameras = 2ea)

One PDZ (Dome) and one fixed camera (Box) on existing Pole (Total Cameras + 4ea)

Fixed cameras on new pole, two cameras (Total cameras = 6)

Fixed camera on new pole, one camera per pole (1 Camera)

Fixed Camera on existing Pole (1 camera per pole)(Near Building N)(Total Camera = 1ea)

NVR Location - inside Guard House

Projected Antenna Locations. To be adjusted as per the contractor and Government agreement to maximize equipment capabilities.

Total PDZ Cameras (Pole Mounted) = 3ea

Total Fixed Cameras (Pole Mounted) = 29ea

Total Fixed Cameras (Wall Mounted) – 2ea

New Poles (4)