This is Addendum No. 2 to the bidding documents for the Rye Township Heisley Road Culvert Replacement project, issued by JHA Companies on September 15, 2026. The project involves removing two existing 36-inch storm pipes and replacing them with a 10-foot by 4-foot by 30-foot precast concrete box culvert, along with associated site preparation, road restoration, riprap installation, subbase and blacktop paving, guide rail systems, and Jersey barriers. The scope of work is provided on a lump sum bid basis, requiring contractors to calculate quantities independently. Electronic bid submission through the PennBid website is mandatory, with bids due by September 18, 2026 at 11:00 AM. Bids will be opened that same day and presented to the Rye Township Board on September 22, 2026 at 7:00 PM for consideration. A pre-bid conference was held on September 10, 2026 at the Rye Township Building. The contractor is responsible for its own survey and site staking, though JHA Companies will provide a stakeout plan for a fee. Paving is intended to be completed in the current year; however, if fabrication or weather delays occur, final paving may be completed in spring 2027 without penalty.
Key clarifications in this addendum address Jersey barrier specifications (32 inches tall by 24 inches wide or 3 feet 9 inches tall by 24 inches wide standard size), which may be purchased used if in good condition and do not require connection to the box culvert per Detail 5 on Sheet S-2.0. The Township will shut down the road and provide signage during construction. The contractor bears responsibility for spoil removal at its own cost, laydown site facilitation, and is not responsible for permits, box inspections, testing, or utility costs. Asphalt pavement restoration details are provided under Detail 8 on Sheet C-2.01 of the specifications. CAD files are unavailable for distribution to bidders but will be provided to the selected contractor for construction staking purposes. The project is financed by a grant from the Commonwealth of Pennsylvania Department of Community and Economic Development, and Rye Township reserves the right to reject any or all bids.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 3-2026-08-11 Heisley Road Culvert Replacement Plan Set.pdf | ||
| 2-Bidding Documents.pdf | ||
| 6-Bid Results.pdf | ||
| 4-Addendum No. 1.pdf | ||
| 1-Contract Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Heisley Road Culvert Replacement Addendum No. 2, 9/15/2026
ADDENDUM No. 2
FOR
Rye Township
September 15, 2026
A. SCOPE
1. This Addendum No. 1 consists of pages 1 through 5, referenced attachments, and includes information regarding the Bidding Documents.
2. The following revisions, interpretations, and/or supplements pertaining to the
Bidding Documents for the Project are addressed by Addendum No. 2.
B. GENERAL
1. All bids must be submitted electronically through the PennBid website.
2. Bid documents may only be reviewed electronically via the PennBid website.
C. CONTRACTOR QUESTIONS FROM PENNBID
The following answers have been revised from Addendum No. 1:
3. What standard does the "Jersey Barrier" have to meet? It doesn't appear to match up with any current PADOT shapes.
It is intended that a 32” tall x 24” wide base standard size Jersey barrier be used.
It is intended that a 3’-9” tall x 24” wide base standard size Jersey barrier be used.
4. Can the Jersey Barriers be purchased used if in good condition?
Yes, the jersey barriers can be purchased used if in good condition..
Yes, the jersey barriers can be purchased used if in condition, subject to Engineer’s approval.
5. Is there a traffic control plan?
It was intended that the road would be shut down by the township (their own signage) during construction.
It was intended that the road would be shut down by the Township using their own signage during construction.
6. Who's responsible for survey and lay out?
JHA Companies will provide a stakeout plan but the contractor is responsible for their own survey. We can provide that for a fee.
JHA Companies will provide a stakeout plan but the contractor is responsible for their own survey. We can provide that for a fee.
7. Can a asphalt pavement restoration detail be provided?
An asphalt pavement restoration detail can be provided.
The asphalt pavement restoration detail is provided under Detail 8 on Sheet No.
C-2.01.
12. Can you clarify if the contractor is responsible for any permits? box inspections, testing, or utility costs?
The Contractor is not responsible for any permits? box inspections, testing, or utility costs.
The Contractor is not responsible for any permits, box inspections, testing, or utility costs.
13. Can a scope of work be provided, as far as all work that needs to be completed since this is labeled a lump sum bid?
The scope of work is to remove the existing cross culverts, prepare the site for installation of the concrete box culvert, install the concrete box culvert and associated riprap. Install the road and blacktop and guide rail system.
The scope of work is to remove the existing cross culverts, prepare the site for installation of the concrete box culvert, install the concrete box culvert and associated riprap. Install the road subbase, blacktop and guide rail system and related accessories.
15. Page 180 of the specs states about the project being Tax Exempt. Please confirm if this information is accurate. Thanks.
See Article 21 – Sales and Use Taxes on Sheet 19 of 332 in the Specifications.
See Article 21 – Sales and Use Taxes on Page 19 of 332 in the Specifications.
D. CONTRACTOR QUESTIONS FROM PRE-BID MEETING
3. Can paving be completed next spring if the concrete box culvert delays the project past the time that they shut down the paving company for the winter?
The project is intended to have sufficient time to pave during the current year and not need an extension on the paving timeframe. Every effort will be made by the engineer in the form of fabrication drawing review to ensure efficient turnaround time for the box culvert fabrication. If necessary due to fabrication or weather delays, the final paving can be completed in the spring of 2027.
The project is intended to have sufficient time to pave during the current year and not need an extension on the paving timeframe. Every effort will be made by the engineer in the form of fabrication drawing review to ensure efficient turnaround time for the box culvert fabrication. If necessary due to fabrication or weather delays, the final paving can be completed in the spring of 2027, without a penalty.
4. Can you provide a detail for the Jersey Barrier to the culvert?
It has been decided that the Jersey Barrier does not need to be connected to the box culvert as it is blocked in by the headwall and the blacktop. Therefore, please use detail 5 on sheet S-2.0 for clarity as to the geometric size of the barrier and also the placement of the barrier.
It has been decided that the Jersey Barrier does not need to be connected to the box culvert as it is blocked in by the headwall and the blacktop. Therefore, please use Detail 5 on Sheet S-2.0 for clarity as to the geometric size of the barrier and also the placement of the barrier.
5. Can you look into a laydown site or is that on the contractor?
There is a former parking area nearby, on Heisley Road, that in recent past has been allowed by the owner for parking of township vehicles. It is up to the contractor to facilitate the use of the space for laydown.
There is a former parking area nearby, on Heisley Road, that in the recent past has been allowed by the owner for parking of township vehicles. It is up to the Contractor to facilitate the use of the space for laydown.
6. Does the Township have a spoil site or does it need to be taken off site?
Any leftover spoil from the site will need to be removed from the site by the contractor at his cost.
Any leftover spoil from the site will need to be removed from the site by the Contractor at his cost.
7. What are the dates for the bid and the opening of bids.
The bids will need to be in by Sept 18, 2026, and revealed that day. They will be presented to the Board on September 22, 2026, at 7:00 pm at their regularly scheduled meeting where they may take action on the plans.
The bids will need to be submitted electronically through the PennBid site by Sept 18, 2026, and revealed that day. They will be presented to the Board on September 22, 2026, at 7:00 pm at their regularly scheduled meeting where they may take action on the plans.
8. It was asked if the Township would handle the road shutdown or if the contractor would need to care of that.
The township will be responsible to shut the road down and provide the necessary signage.
The Township will be responsible to shut the road down and provide the necessary signage during construction.
9. Provide the quantities of excavation and backfill.
The bid is a lump sum bid and it is the responsibility of the contractor bidding to provide the amounts and total price for the cost of the project.
The bid is on a lump sum basis, and it is the responsibility of the Contractor bidding to provide the quantity amounts and total price for the cost of the project.
10. Can we provide the CAD file so that they can verify the quantities?
The CAD files are unavailable for distribution at this time. The CAD files will be provided to the selected contractor for construction staking purposes.
The CAD files are unavailable for distribution at this time. The CAD files will be provided to the selected Contractor for construction staking purposes.
Bidders are required to acknowledge receipt of this Addendum No. 1 on page 2 of the Bid Form.