AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
1 1
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
10/1/2018
4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
U.S. GENERAL SERVICES ADMINISTRATION
ACQUISITION MANAGEMENT DIVISION / FIELD SUPPORT
401 W WASHINGTON STREET, SUITE 210
PHOENIX, AZ 85003-2117
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
Interested Party
(X) 9A. AMENDMENT OF SOLICITATION
NO.
47PK0518R0015
9B. DATED (SEE ITEM 11)
09/17/2018
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, X is required to sign this document and return 1 copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to correct Proposal Due Date and modify certain pages of technical spec.
A. Insert and incorporate Tech Spec Section 102600 dated 9/20/18, supersedes previous section with same number.
B. Reference Paragraph I.H. Receipt of Offers, change due date to OCTOBER 5, 2018.
C. Reference Spec page 011000-2, para 1.5, delete third and fourth sentence beginning with, "Third Party security..." and ending with "... activities are in the room."
D. All questions to this solicitation will be received until the end of the day 10/1/18.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
NSN 7540-01-152-8070
Previous edition unusable
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 5
USDA NRCS Space Reduction Phoenix Federal Building 100% Construction Document Submittal Phoenix, AZ [UPDATED 20 September 18] 15 December 2017
WALL AND DOOR PROTECTION 102600 - 1
PROPERTY OF THE UNITED STATES GOVERNMENT
FOR OFFICIAL USE ONLY
Do not remove this notice.
Properly destroy documents when no longer needed.
SECTION 102600 - WALL AND DOOR PROTECTION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Corner guards.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product.
1. Include construction details, material descriptions, impact strength, dimensions of individual components and profiles, and finishes.
B. Shop Drawings: For each type of wall and door protection showing locations and extent.
1. Include plans, elevations, sections, and attachment details.
1.4 QUALITY ASSURANCE
A. Installer Qualifications: An employer of workers trained and approved by manufacturer.
1.5 DELIVERY, STORAGE, AND HANDLING
A. Store wall and door protection in original undamaged packages and containers inside well-ventilated area protected from weather, moisture, soiling, extreme temperatures, and humidity.
1. Maintain room temperature within storage area at not less than 70 deg F (21 deg C) during the period plastic materials are stored.
http://contact.arcomnet.com/ContentContact.aspx?sect=102600&ver=06/01/17&format=FL&sid=13782
Phoenix, AZ [UPDATED 20 September 18] 15 December 2017
WALL AND DOOR PROTECTION 102600 - 2
PROPERTY OF THE UNITED STATES GOVERNMENT
FOR OFFICIAL USE ONLY
Do not remove this notice.
Properly destroy documents when no longer needed.
2. Keep plastic materials out of direct sunlight.
3. Store plastic wall- and door-protection components for a minimum of 72 hours, or until plastic material attains a minimum room temperature of 70 deg F (21 deg C).
a. Store corner-guard covers in a vertical position.
1.6 WARRANTY
A. Special Warranty: Manufacturer agrees to repair or replace components of wall- and door-protection units that fail in materials or workmanship within specified warranty period.
1. Failures include, but are not limited to, the following:
a. Structural failures including detachment of components from each other or from the substrates, delamination, and permanent deformation beyond normal use.
b. Deterioration of metals, metal finishes, plastics, and other materials beyond normal use.
2. Warranty Period: Five years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Source Limitations: Obtain products from single source from single manufacturer.
2.2 CORNER GUARDS
A. Flush-Mounted, Plastic Cover Corner Guards: Manufacturer’s standard PVC Free assembly consisting of snap-on, resilient plastic cover that is flush with adjacent wall surface, installed over retainer; including mounting hardware; fabricated with 90 degree turn to match wall condition: full wall height.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. Balco, Inc.
b. Construction Specialties, Inc.
c. InPro Corporation (IPC).
http://www.specagent.com/Lookup?ulid=671 http://www.specagent.com/Lookup?uid=123457107517 http://www.specagent.com/Lookup?uid=123457107518 http://www.specagent.com/Lookup?uid=123457107522
Phoenix, AZ [UPDATED 20 September 18] 15 December 2017
WALL AND DOOR PROTECTION 102600 - 3
PROPERTY OF THE UNITED STATES GOVERNMENT
FOR OFFICIAL USE ONLY
Do not remove this notice.
Properly destroy documents when no longer needed.
2. Cover: Extruded rigid plastic, minimum 0.078 inch wall thickness; in dimensions and profiles indicated on drawings.
3. Profile: Nominal 3-1/2 by 3-1/2 inches (90 by 90 mm).
4. Corner Radius: 1/4 inch (6 mm).
5. Height: 8 feet
6. Color and texture: as indicated on drawings.
7. Continuous retainer: Minimum 0.060 inch thick, one-piece extruded aluminum.
8. Retainer Clips: Manufacturer’s standard impact-absorbing clips
9. Aluminum Cove Base: Nominal 4 inch high.
2.3 MATERIALS
A. Fasteners: Aluminum, nonmagnetic stainless-steel, or other noncorrosive metal screws, bolts, and other fasteners compatible with items being fastened. Use security-type fasteners where exposed to view.
2.4 FABRICATION
A. Fabricate wall and door protection according to requirements indicated for design, performance, dimensions, and member sizes, including thicknesses of components.
2.5 FINISHES
A. Protect finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping.
B. Appearance of Finished Work: Noticeable variations in same piece are not acceptable.
Variations in appearance of adjoining components are acceptable if they are within the range of approved Samples and are assembled or installed to minimize contrast.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates and wall areas, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of the Work.
B. Examine walls to which wall and door protection will be attached for blocking, grounds, and other solid backing that have been installed in the locations required for secure attachment of support fasteners.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
Phoenix, AZ [UPDATED 20 September 18] 15 December 2017
WALL AND DOOR PROTECTION 102600 - 4
PROPERTY OF THE UNITED STATES GOVERNMENT
FOR OFFICIAL USE ONLY
Do not remove this notice.
Properly destroy documents when no longer needed.
3.2 PREPARATION
A. Complete finishing operations, including painting, before installing wall and door protection.
B. Before installation, clean substrate to remove dust, debris, and loose particles.
3.3 INSTALLATION
A. Installation Quality: Install wall and door protection according to manufacturer's written instructions, level, plumb, and true to line without distortions. Do not use materials with chips, cracks, voids, stains, or other defects that might be visible in the finished Work.
3.4 CLEANING
A. Immediately after completion of installation, clean plastic covers and accessories using a standard ammonia-based household cleaning agent.
B. Remove excess adhesive using methods and materials recommended in writing by manufacturer.
END OF SECTION 102600
| Amend_01 |
| 11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS |
| 13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. |
| USDA_NRCS_Specification update_102600 fl - wall and door protection_180920 |
| PART 1 - GENERAL |
| 1.1 RELATED DOCUMENTS |
| A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. |
| 1.2 SUMMARY |
| A. Section Includes: |
| 1. Corner guards. |
| 1.3 ACTION SUBMITTALS |
| A. Product Data: For each type of product. |
| 1. Include construction details, material descriptions, impact strength, dimensions of individual components and profiles, and finishes. |
| B. Shop Drawings: For each type of wall and door protection showing locations and extent. |
| 1. Include plans, elevations, sections, and attachment details. |
| 1.4 QUALITY ASSURANCE |
| A. Installer Qualifications: An employer of workers trained and approved by manufacturer. |
| 1.5 DELIVERY, STORAGE, AND HANDLING |
| A. Store wall and door protection in original undamaged packages and containers inside well-ventilated area protected from weather, moisture, soiling, extreme temperatures, and humidity. |
| 1. Maintain room temperature within storage area at not less than 70 deg F (21 deg C) during the period plastic materials are stored. |
| 2. Keep plastic materials out of direct sunlight. |
| 3. Store plastic wall- and door-protection components for a minimum of 72 hours, or until plastic material attains a minimum room temperature of 70 deg F (21 deg C). |
| a. Store corner-guard covers in a vertical position. |
| 1.6 WARRANTY |
| A. Special Warranty: Manufacturer agrees to repair or replace components of wall- and door-protection units that fail in materials or workmanship within specified warranty period. |
| 1. Failures include, but are not limited to, the following: |
| a. Structural failures including detachment of components from each other or from the substrates, delamination, and permanent deformation beyond normal use. |
| b. Deterioration of metals, metal finishes, plastics, and other materials beyond normal use. |
2. Warranty Period: Five years from date of Substantial Completion.
| PART 2 - PRODUCTS |
| 2.1 MANUFACTURERS |
| A. Source Limitations: Obtain products from single source from single manufacturer. |
| 2.2 CORNER GUARDS |
| A. Flush-Mounted, Plastic Cover Corner Guards: Manufacturer’s standard PVC Free assembly consisting of snap-on, resilient plastic cover that is flush with adjacent wall surface, installed over retainer; including mounting hardware; fabricated with 90 ... |
| 1. Manufacturers: Subject to compliance with requirements, provide products by one of the following: |
| a. Balco, Inc. |
| b. Construction Specialties, Inc. |
| c. InPro Corporation (IPC). |
| 2. Cover: Extruded rigid plastic, minimum 0.078 inch wall thickness; in dimensions and profiles indicated on drawings. |
| 3. Profile: Nominal 3-1/2 by 3-1/2 inches (90 by 90 mm). |
| 4. Corner Radius: 1/4 inch (6 mm). |
| 5. Height: 8 feet |
| 6. Color and texture: as indicated on drawings. |
| 7. Continuous retainer: Minimum 0.060 inch thick, one-piece extruded aluminum. |
| 8. Retainer Clips: Manufacturer’s standard impact-absorbing clips |
| 9. Aluminum Cove Base: Nominal 4 inch high. |
| 2.3 MATERIALS |
| A. Fasteners: Aluminum, nonmagnetic stainless-steel, or other noncorrosive metal screws, bolts, and other fasteners compatible with items being fastened. Use security-type fasteners where exposed to view. |
| 2.4 FABRICATION |
| A. Fabricate wall and door protection according to requirements indicated for design, performance, dimensions, and member sizes, including thicknesses of components. |
| 2.5 FINISHES |
| A. Protect finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping. |
| B. Appearance of Finished Work: Noticeable variations in same piece are not acceptable. Variations in appearance of adjoining components are acceptable if they are within the range of approved Samples and are assembled or installed to minimize contrast. |
| PART 3 - EXECUTION |
| 3.1 EXAMINATION |
| A. Examine substrates and wall areas, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of the Work. |
| B. Examine walls to which wall and door protection will be attached for blocking, grounds, and other solid backing that have been installed in the locations required for secure attachment of support fasteners. |
| C. Proceed with installation only after unsatisfactory conditions have been corrected. |
| 3.2 PREPARATION |
| A. Complete finishing operations, including painting, before installing wall and door protection. |
| B. Before installation, clean substrate to remove dust, debris, and loose particles. |
| 3.3 INSTALLATION |
| A. Installation Quality: Install wall and door protection according to manufacturer's written instructions, level, plumb, and true to line without distortions. Do not use materials with chips, cracks, voids, stains, or other defects that might be visi... |
| 3.4 CLEANING |
| A. Immediately after completion of installation, clean plastic covers and accessories using a standard ammonia-based household cleaning agent. |
| B. Remove excess adhesive using methods and materials recommended in writing by manufacturer. |
File details come from the government source that posted it.